New sidings, second main tracks and grade raises run for miles along an existing embankment, and the boring program has to sample the existing roadbed, the embankment and the cut slopes as well as the ground beneath. AREMA Chapter 1, Part 1, notes that new construction next to existing track may need only a few widely spaced borings unless problem areas show up, while creeping failures under existing track need exploration deep enough to intercept the failure plane, supplemented by trenches, test pits, inclinometers, piezometers and CPT. A Class I railroad's public projects geotechnical requirements turn this into a pattern, used by the calculator.
| Location | Borings | Depth |
|---|---|---|
| Each quarter mile, representing the prevailing cut or fill | Top of existing grade (between edge of ballast and shoulder), midslope, ditch line just off the toe | To stable track and embankment subgrade or foundation |
| Cut sections | Add one boring at the top of the cut slope, near the right-of-way line | Cut height plus 5 ft below the proposed ditch flowline; bulk samples for classification and modified Proctor |
| Culverts to be extended | One at each end | For sub-excavation and stabilization advice to limit differential settlement |
| Bridges, walls and unique structures | As the structure requires | Per structure design |
The report should also give stripping depth, sub-excavation, benching, compaction, ditch depth and grade, subballast thickness by the AREMA method, and stable fore and back slopes from stability analysis.
| Result | Value |
|---|---|
| Boring series | 13 |
| Total borings | 56 |
| Total footage | 1,280 ft |
| Average depth | 22.9 ft |
Borings on top of grade sit within a few feet of the live track, so each needs flagging and track time; in this example 13 of the 56 borings are of that kind. The logs should record ballast, subballast and fouling thicknesses, which feed Chapters 2.1 and 6.4. A geotechnical engineer should walk the corridor first and move or add borings where the reconnaissance shows soft ground, seepage or slope movement.
Open the corridor boring calculator →
Quarter-mile boring series, top-of-cut borrow borings, culvert-end and structure borings, with counts and footage.
These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads are not named.