4.1.15 Boring Programs for Track Widening and New Track

Borings and sampling form the physical backbone of every geotechnical investigation we conduct for railroad clients.
Authors: Daniel P. Colwell and Mario Ruel
4.1.15 Boring Programs for Track Widening and New Track

New sidings, second main tracks and grade raises run for miles along an existing embankment, and the boring program has to sample the existing roadbed, the embankment and the cut slopes as well as the ground beneath. AREMA Chapter 1, Part 1, notes that new construction next to existing track may need only a few widely spaced borings unless problem areas show up, while creeping failures under existing track need exploration deep enough to intercept the failure plane, supplemented by trenches, test pits, inclinometers, piezometers and CPT. A Class I railroad's public projects geotechnical requirements turn this into a pattern, used by the calculator.

4.1.15.1 The boring series

Table 4.1-1. Corridor boring pattern (railroad public projects requirements)
LocationBoringsDepth
Each quarter mile, representing the prevailing cut or fillTop of existing grade (between edge of ballast and shoulder), midslope, ditch line just off the toeTo stable track and embankment subgrade or foundation
Cut sectionsAdd one boring at the top of the cut slope, near the right-of-way lineCut height plus 5 ft below the proposed ditch flowline; bulk samples for classification and modified Proctor
Culverts to be extendedOne at each endFor sub-excavation and stabilization advice to limit differential settlement
Bridges, walls and unique structuresAs the structure requiresPer structure design

The report should also give stripping depth, sub-excavation, benching, compaction, ditch depth and grade, subballast thickness by the AREMA method, and stable fore and back slopes from stability analysis.

4.1.15.2 Worked example: three-mile second main track

Table 4.1-2. 13 series (40% in cut), 4 culvert extensions, 4 structure borings (calculator output)
ResultValue
Boring series13
Total borings56
Total footage1,280 ft
Average depth22.9 ft

Borings on top of grade sit within a few feet of the live track, so each needs flagging and track time; in this example 13 of the 56 borings are of that kind. The logs should record ballast, subballast and fouling thicknesses, which feed Chapters 2.1 and 6.4. A geotechnical engineer should walk the corridor first and move or add borings where the reconnaissance shows soft ground, seepage or slope movement.

Open the corridor boring calculator →
Quarter-mile boring series, top-of-cut borrow borings, culvert-end and structure borings, with counts and footage.

4.1.15.3 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads are not named.

← Previous · 3.0 Risk Management Chapter 3.10 — Mining and Man-Made Hazards
Next · 5.0 Testing → Chapter 5.1 — In Situ Testing