4.1.10 Practical Recommendations

Borings and sampling form the physical backbone of every geotechnical investigation we conduct for railroad clients.
Authors: Daniel P. Colwell and Mario Ruel
4.1.10 Practical Recommendations
  1. Energy calibration at every mobilization. Do not assume a fixed E_m for any rig or hammer configuration. Measure hammer energy with an instrumented anvil at the start of each field mobilization and after any hammer change. Record energy measurements for all SPT borings, on every railroad project, as a quality floor.
  2. Casing in heaving sands. When HSA reveals running sand conditions below the water table, advance steel casing before continuing SPT sampling. Heave into the auger stem produces N-values that are artificially low and results in unconservative design parameters for foundations and retaining structures. This is especially important for Class I railroad projects in the alluvial Great Plains, where highly permeable sandy gravels are common below shallow water tables.
  3. Shelby tube conditioning before push. Clean the borehole base of disturbed cuttings before inserting the Shelby tube by washing and bailing. Any disturbed material at the base of the borehole enters the tube first, contaminating the upper portion of the sample and degrading consolidation test results. Document borehole conditioning in the field log for every undisturbed sample.
  4. Core box photography protocol. Photograph core boxes immediately after recovery and before any handling or logging. Photograph again after geologist marking with depth lines and piece numbers. Submit both sets of photographs. Keep this two-step photographic record on every project. Establish this habit across all clients — it protects us in the event of sample loss or dispute.
  5. ROW and RWP compliance — pre-field confirmation. Confirm that all field personnel hold current Roadway Worker Protection certification for the specific railroad before mobilization. Owner railroads may require RWP training from their own approved provider, and a certification from one railroad may not be accepted by another. Short lines vary by property — confirm requirements with the local operating division engineering contact before each mobilization. Failure to confirm RWP certification prior to field work is a contract compliance failure, not merely a safety matter, and is grounds for termination of on-site access.
  6. Drilling fluid management on the owner railroads. Document drilling fluid type, additives and disposal method in the field log and the investigation report. Use low-toxicity, biodegradable additives wherever possible. On the railroad's projects in areas subject to provincial environmental regulation, submit a fluid management plan to the client's environmental coordinator before field mobilization.
Supplemental reference

Block samples and the Swedish foil sampler

Hunt describes two sampling methods for soils that thin-walled tubes handle poorly:

  • Block samples from test pits. Particularly useful in residual soils that are hard to tube-sample. The block is hand-trimmed from the pit wall with a knife, coated with paraffin on the exposed faces, cut loose, turned over and coated on the remaining face, then boxed for shipment. Weaker soils with some cohesion are trimmed into small cylinders instead. On the right-of-way, a test pit in the embankment slope or track zone needs the same flagging and track-protection approvals as a boring, plus a backfill and compaction plan the railroad accepts.
  • Swedish foil sampler. Produces continuous high-quality samples (tube typically 8 ft long) in soft, sensitive clays. Thin steel foils unreel from the cutting edge and line the sample so that it does not rub against the tube wall. Its main use is locating the shear zone in a slope failure — a direct application to railroad embankment slides on soft clay.
Block samples in various stages of trimming and sampling.
Supplemental Figure 6-S3. Block samples in various stages of trimming and sampling. Source: U.S. Army Corps of Engineers (2001). Geotechnical Investigations. EM 1110-1-1804.

Source: Hunt, R. E. (2005). Geotechnical Investigation Methods: A Field Guide for Geotechnical Engineers. CRC Press

Project management · Haidar (2016)

Estimating Drilling Program Durations from Quantity and Production Rate

Haidar gives the basic duration relation used in CPM scheduling:

Activity duration = Work quantity ÷ Production rate (Haidar Eq. 3.1)

The time unit (hours, shifts, days) may be anything, provided it is used consistently throughout the schedule. He notes that the estimates need not be exact. When every duration is reasonable, over- and under-estimates tend to offset, and spending too much effort refining individual durations makes the schedule harder to build without making it better. He lists the factors that control how accurate an estimate will be: number of projects, complexity, design duration, construction method, resource availability, work quantity, labor and equipment productivity, quality of field management, geography and site conditions, and concurrent activities. He recommends getting each estimate from the person who will manage the work.

On logic, Haidar recognizes three relationships: predecessor, successor, and concurrent (independent). Concurrent means only that neither activity depends on the other, not that they must run at the same time. There is usually more than one correct sequence, and choosing among them requires knowing how the work is actually built.

For railroad work: split the drilling quantity by method, because production differs widely. Soil drilling with SPT intervals, Shelby tube sampling, rock coring and in-hole testing each need their own quantity and rate. Production rates should come from the firm’s own driller records for similar ground and access, not from catalog figures. Express the rate per effective hour under track protection. As an illustration only: 480 ft of soil drilling at 30 ft per effective hour is 16 effective hours. If a track window yields about 5 effective hours after protection setup, moves between holes and clearing, the work needs 4 windows. Add separate activities for rock coring, grouting or backfill, and the move-in and move-out of each site. Off-track work, such as CPT soundings from an access road or borings at the embankment toe, is often concurrent with on-track borings and can fill time when windows are cancelled. Record actual footage and hours each shift so that the next program’s production rates are better than this one’s.

Source: Haidar, A. D. (2016). Construction Program Management – Decision Making and Optimization Techniques. Cham, Switzerland: Springer International Publishing, pp. 64–66. Summarized and paraphrased. Full reference under Supplemental References.

Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IS-01 SPT energy & procedure correction N₆₀Use: All soils tested by SPT (ASTM D1586). Normalizes blow count to 60% of theoretical free-fall energy, the basis for most U.S. correlations. Limits: CE ranges ~0.5–1.6 depending on hammer type; use measured energy (ASTM D4633, withdrawn 2025) where available. Rod-length factor ranges differ between Skempton (1986) and Youd et al. (2001).