Hollow-stem auger drilling is the preferred method for most railroad embankment, subgrade, and shallow foundation investigations where soil conditions permit. HSA allows continuous sample recovery through the auger stem without removing the drill string, minimizing borehole disturbance and reducing the risk of borehole collapse in granular soils above the water table.

Applicable client contexts:
Limitations: HSA is not appropriate in running sands below the water table (where heave into the auger stem is common), in hard or cemented soils, in rock, or where boring depths exceed approximately 100–120 ft. In these conditions, mud rotary or air rotary methods are substituted.
Equipment specifications:
Mud rotary drilling uses a pressurized fluid — typically a bentonite-water slurry — to cool the bit, carry cuttings to the surface, and stabilize the borehole wall. It is the preferred method for deep investigations (greater than approximately 100 ft), for offshore or waterway bridge site investigations, and for any condition where borehole stability cannot be maintained with HSA.
Applicable client contexts:
Critical operational note for railroad right-of-way: All drilling fluid returns must be captured and removed from the ROW. Drilling mud discharged onto active track subgrade will breach most railroad right-of-way agreements and can lead to suspension of field work. We require closed-loop mud pits or portable fluid containment systems on all mud rotary jobs conducted within 50 ft of active track.
Air rotary drilling uses compressed air (and in some cases air-foam mixtures) to circulate cuttings and cool the bit. It is the preferred method in rock or very hard soils where drilling fluid is impractical, and is commonly used to advance through casing in overburden before transitioning to diamond core in the rock zone.
Applicable client contexts:
Diamond core drilling recovers continuous cylindrical cores of intact rock for geomechanical characterization. Core drilling is required for any railroad structure with rock-socketed drilled shaft foundations, for tunnel portal and cut investigations, and for any project where bearing on rock or side resistance in rock is a foundation design parameter.
Core barrel sizes used in railroad practice:
| Size | OD (in.) | Core Diameter (in.) | Typical Use |
|---|---|---|---|
| NQ | 2.98 | 1.88 | Deep exploration; limited recovery in fractured rock |
| HQ | 3.78 | 2.50 | Standard size for most railroad bridge foundations |
| PQ | 4.83 | 3.35 | Large-diameter cores; used for tunnel and major structure investigations |
Some owner railroads require HQ-size core or larger for bridge foundation investigations where drilled shafts are anticipated; confirm when the work is scoped.
Shallow subgrade samples are taken with shovels, backhoes or hand augers; hand-auger depth is limited by how easily the auger can be pulled, so a powered auger sometimes advances the hole. Deep embankment sampling uses a drilling contractor: split-spoon SPT (ASTM D1586; 2-in. sampler driven 18 in. by a 140-lb hammer falling 30 in.) and Shelby tubes (ASTM D1587, withdrawn 2024; 3-in. × 30-in. thin-wall tube pushed hydraulically). For mud spots and soft track, a hand-dug trench across the shoulder is often the fastest way to see the layering, the water and the failure zone. At one Class I railroad subgrade repair, test pits confirmed subgrade conditions before the toe berm and cross trenches were designed.






After Geotechnology for Railroaders Program, Module 2, Module 3, Module 6.2; Module 2 §10; Module 3 §11; Module 6.2 §02. Full reference under Supplemental References.
Case study: 4.1.14.1 Auger versus core: when crushed rock is logged as soil (Look 2023), in Section 4.1.14 Case Studies.