4.1.5 Rock Core Recovery and RQD

Borings and sampling form the physical backbone of every geotechnical investigation we conduct for railroad clients.
Authors: Daniel P. Colwell and Mario Ruel
4.1.5 Rock Core Recovery and RQD
4.1.5.1 Core Recovery

Total Core Recovery (TCR) is the length of core recovered expressed as a percentage of the length drilled:

TCR vs SCR vs RQD
TCR vs SCR vs RQD
TCR = Length of core recovered (ft)Length of core run (ft) × 100%
Inputs for the equations in this section (1)
SymbolWhat it isComes fromHow to get itTypical range
TCRLength of core recovered (ft) Length of core run (ft) × 100%Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
4.1.5.2 Rock Quality Designation (RQD)

RQD quantifies the degree of fracturing in a rock mass. It is defined as the percentage of a core run consisting of intact pieces 4 inches or longer in length:

RQD = ∑ lengths of intact core pieces ≥ 4 in.Total length of core run × 100%
RQD (%)Rock Quality
0–25Very Poor
25–50Poor
50–75Fair
75–90Good
90–100Excellent

Measure RQD on every core run and report it on the boring log alongside TCR, hardness (field estimate) and the visual rock description. Photograph all core boxes before and after the geologist's review, and submit the photos with the boring data package.

Inputs for the equations in this section (1)
SymbolWhat it isComes fromHow to get itTypical range
RQD∑ lengths of intact core pieces ≥ 4 inField mapping / core loggingFrom core logs and outcrop mapping using the cited rating tables (RQD per ASTM D6032; joint spacing, condition, water).see rating tables
Supplemental reference

Measuring RQD consistently

USBR’s field rules (after Deere) remove most of the logger-to-logger scatter in RQD:

  • Count only pieces of solid core ≥ 4 in., measured along the centerline of the core, regardless of core diameter.
  • Fit pieces broken by handling or drilling (mechanical breaks) back together and count them as one piece if they make the 4-in. length. Log mechanical breaks separately from natural fractures.
  • Record RQD per run (not per box), with the run length as the denominator.
  • Best applied to N-size or larger core; may not be meaningful for very low-strength, fissile or foliated rock that breaks along foliation.
  • RQD can be estimated at outcrops or cut faces from the volumetric joint count: RQD ≈ 115 − 10.8 Jv (Jv = volumetric joint count, joints per ft summed over three directions), or from line surveys that simulate a 5- or 10-ft run. Oriented line surveys include all fracture orientations and avoid the directional bias of vertical core — useful for rock cut slopes.
RQD computation example: sum of solid pieces ≥ 0.33 ft (4 in.), excluding mechanical breaks (MB), divided by run length — here 2.4 / 4.7 × 100 = 51%. BJ = bedding joint, JT = joint.
Supplemental Figure 6-S5. RQD computation example: sum of solid pieces ≥ 0.33 ft (4 in.), excluding mechanical breaks (MB), divided by run length — here 2.4 / 4.7 × 100 = 51%. BJ = bedding joint, JT = joint. Source: U.S. Bureau of Reclamation (1998). Engineering Geology Field Manual, 2nd ed., Vol. I, Ch. 5 (Discontinuities), p. 96.

Table 6-S1. USBR fracture density descriptors (excludes mechanical breaks)

CodeDescriptorCriteria
FD0UnfracturedNo observed fractures
FD1Very slightly fracturedCore mostly in lengths > 3 ft
FD3Slightly fracturedMostly 1–3 ft, few scattered lengths < 1 ft or > 3 ft
FD5Moderately fracturedMostly 0.33–1.0 ft, most about 0.67 ft
FD7Intensely fracturedAverage 0.1–0.33 ft with fragmented intervals
FD9Very intensely fracturedMostly chips and fragments with a few short core lengths

Even-numbered codes (FD2, FD4, FD6, FD8) are used for intervals “in between” two descriptors. Report fracture frequency (natural fractures per foot) alongside RQD; a full entry reads, for example, “Slightly fractured (FD3), core in 0.8–4.7 ft lengths, mostly 1.7 ft; 25% bedding joints / 75% joints.”

Source: U.S. Bureau of Reclamation (1998). Engineering Geology Field Manual, 2nd ed., Vol. I, Ch. 5 (Discontinuities)

Supplemental reference

Core barrel selection

Table 6-S2. Rock core drilling methods (GEC 5, Table 5(b), after Day, 1999)

MethodSampleBest applicationLimitations
Rotary coring, conventional double tube (ASTM D2113, withdrawn 2023)0.9–4 in. core up to 10 ft long; standard 2.1 in. (NX-class)Continuous core in sound rockCore lost in fractured or variable rock; bedding and joint dip visible but not strike
Wire-line coring1.1–3.3 in. core, 5–10 ft runsFractured rock (less caving during core removal); deep holes with faster cycle timeSame core-loss and orientation limits
Triple-tube with plastic liner1.1–2.1 in. core encased in linerSwelling clays, shales and soft rock that swell or slake in airSmaller sample; more complex equipment

For railroad cut slopes and bridge foundations in shale, specify triple-tube (split inner tube or liner) coring: shale and claystone that slake on contact with drilling water are routinely logged as “poor RQD” when the fracturing is actually drilling-induced.

Source: Sabatini, P. J. et al. (2002). Evaluation of Soil and Rock Properties. Geotechnical Engineering Circular No. 5, FHWA-IF-02-034 (superseded by GEC 5, Geotechnical Site Characterization, FHWA-NHI-16-072 (2017))

Typical diamond coring bit.
Supplemental Figure 6-S4. Typical diamond coring bit. Source: U.S. Army Corps of Engineers (2001). Geotechnical Investigations. EM 1110-1-1804.