4.1.1 Background — Why Boring Quality Drives Railroad Deliverable Value

Borings and sampling form the physical backbone of every geotechnical investigation we conduct for railroad clients.
Authors: Daniel P. Colwell and Mario Ruel
4.1.1 Background — Why Boring Quality Drives Railroad Deliverable Value

For railroad clients, a boring log is not merely a field record — it is a legal and contractual document. Owner railroads commonly require subsurface investigation records in an approved format, retained for the life of the facility. Confirm the owner railroad's minimum boring log content and sample chain-of-custody requirements when the work is scoped. When our boring logs and sample records are weak, inaccurate, or incomplete, we expose both the client and our firm to design liability, change order disputes, and construction failures.

AREMA's Manual for Railway Engineering (MRE), Chapter 1, Part 1 (Section 2.1, Exploration and Testing), gives guidance on investigations for roadbed and earthwork. AREMA Chapters 8 and 15 define the Cooper E-80 live load and impact allowances for structures, and this manual uses dynamic load factors of about 1.3 to 1.5 for track substructure (Chapter 2.3). Subsurface data must cover the depths these loads influence for the track and structure configuration at hand. Our boring programs must be designed with these loading demands explicitly in mind, and the report should state how each boring depth was chosen.

Boring logs should meet the minimum data requirements of ASTM D5434 and be accompanied by a chain-of-custody record for all SPT and undisturbed samples. Record water content at every sample interval and describe drilling fluid returns during mud rotary drilling.

Our commitment to boring quality is therefore both a technical and a business imperative. A well-executed boring program, thoroughly documented and delivered in the client's preferred format, is a direct competitive advantage in railroad geotechnical practice.

Sampling for UIC subgrade classification

The UIC subgrade classes ( Chapter 2.3, Section 2.3.4 ) are assigned from a short list of parameters. If track-subgrade borings are to support that classification, or a comparison with it, the sampling plan must recover them through the top 6.5 ft of subgrade, the depth Profillidis gives as mechanically affected by train loading:

  • fines content (% finer than about 60 µm), with breaks at 5%, 15% and 40%: bag or jar samples for gradation from every stratum change;
  • plasticity index (PI > 7 is a class break for silty sands and schists): samples for Atterberg limits;
  • rock quality as Los Angeles abrasion (breaks at LA 30 and 40) and susceptibility to weathering: core or bulk rock suitable for LA testing;
  • moisture condition and groundwater, which move a soil up or down a class (“good” vs. “bad” hydrogeology): water levels, moisture contents and seasonal observations;
  • problem materials that make a soil S0 regardless of strength: organics, soluble rock (gypsum, rock salt), quick clay, contaminated ground.

After Profillidis (2014), §7.2, §9.5, Table 9.2. Full reference under Supplemental References.