6.6.8 Clearance Improvement Projects

Inspection, assessment, repair and clearance improvement of existing railroad tunnels and their portals.
Author: Daniel P. Colwell
6.6.8 Clearance Improvement Projects

Double-stack container trains, tri-level auto racks and high-cube cars need more vertical clearance than most old tunnels provide. Clearance diagrams and the equipment outlines they must accommodate are covered in AREMA Chapter 28, Clearances [S8], and in each railroad’s own clearance standards; the route criterion governs. The usual ways to gain clearance are:

Table 6.6-3. Ways to increase tunnel clearance
MethodHow it worksMain issues
Track lowering (undercutting)Excavate the floor and lower the trackUndermining of sidewall footings; drainage outfalls; grade change at the ends; rock excavation in the invert, sometimes by blasting
Crown notchingCut notches in the crown or upper walls where the car corners need roomOnly in sound rock or thick linings; weakens a masonry or plain concrete arch
Liner replacementRemove the old lining and install a thinner modern lining (shotcrete, precast)Temporary support of the ground while the lining is out; long track outages
EnlargementExcavate the rock to a larger profile and relineBlasting or mechanical excavation beside live track; staged work
DaylightingRemove the tunnel and replace it with an open cutLarge excavation and slopes; feasible for short, shallow tunnels
New parallel boreBuild a new tunnel and retire or reuse the old oneCost; usually only where the old tunnel is in very poor condition

Laser-scanned profiles at close spacing are the basis of any clearance study: they show the tight spots, which are often local (a sagging section of lining, a misaligned ring, a low spot in an arch) rather than the whole tunnel. Excavation by blasting must meet the vibration limits of Section 5.3.27, with the lining itself treated as the structure to protect.

Example 6.6-2: Track Lowering for Double-Stack Clearance in a Masonry Arch Tunnel

Problem Statement

A Class I railroad located in Pennsylvania wants to run double-stack trains through a 19th-century brick-lined tunnel. The laser-scan profile shows a semicircular arch. The railroad’s clearance criterion for the route requires 21.0 ft above top of rail over a width of 5.0 ft either side of centerline. The engineer must find how much the track must be lowered and whether lowering will undermine the sidewall footings.

sidewallfooting Existing top of rail (TOR) Top of subgrade (2.0 ft below TOR) Footing base (3.5 ft below TOR) Springline (9.6 ft above TOR) Required envelope: 21.0 ft corner ±5.0 ft R = 10 ft GivenSemicircular arch, R = 10 ftSpringline 9.6 ft above TOREnvelope: 21.0 ft aboveTOR over ±5.0 ftTrack section 2.0 ftFooting base 3.5 ftbelow TOR Required(a) Clearance at center and at ±5.0 ft(b) Track lowering(c) New subgrade vs footing base
Figure 6.6-2. Example 6.6-2: masonry arch tunnel and the clearance envelope for double-stack service (not to scale vertically).

Given

VariableValueDescription
R10 ftRadius of the semicircular arch
hs9.6 ftHeight of springline above existing top of rail at centerline
Hreq21.0 ft over ±5.0 ftRequired clearance envelope (route criterion)
t2.0 ftTrack section, top of rail to top of subgrade
zf3.5 ftDepth of sidewall footing base below existing top of rail

Required

  • (a) Existing clearance at centerline and at ±5.0 ft
  • (b) Required track lowering
  • (c) New top of subgrade compared with the footing base

Equations

  1. y(x) = hs + √(R2 − x2) — arch height above TOR at offset x
  2. Δ = Hreq − min y(x) over the envelope width
  3. zsg,new = Δ + t — new top of subgrade below existing TOR

Steps

Step 1 · (a) Clearance at centerline
9.6 + √(100 − 0) = 9.6 + 10.0
19.6 ft
↓
Step 2 · (a) Clearance at ±5.0 ft
9.6 + √(100 − 25) = 9.6 + 8.66
18.26 ft (governs)
Spot check: 8.662 + 5.02 = 75.0 + 25.0 = 100 = R2 ✓.
↓
Step 3 · (b) Lowering
21.0 − 18.26
Δ = 2.74 ft; use 2.75 ft (33 in.)
↓
Step 4 · (c) New top of subgrade
2.75 + 2.0 = 4.75 ft below existing TOR, against footing base at 3.5 ft
New subgrade is 1.25 ft below the footing base
↓
Solution
Clearance is 19.6 ft at centerline and 18.26 ft at the envelope corners; the track must come down about 2.75 ft, which puts the new subgrade 1.25 ft below the footing base.

Solution

Clearance is 19.6 ft at centerline and 18.26 ft at the envelope corners; the track must come down about 2.75 ft, which puts the new subgrade 1.25 ft below the footing base.

The arch corners govern, not the crown: lowering by only the 1.4-ft crown deficit would leave the container corners 1.34 ft short. Lowering the track 2.75 ft with the same 2.0-ft track section exposes the sidewall footings by 1.25 ft, which is not acceptable for a masonry arch that relies on its footings to resist thrust. Options are to underpin the footings (for example with micropiles or a concrete toe wall, Chapter 6.1), to build a structural invert slab that ties the walls together and lets the track section be thinner, or to choose a different method such as liner replacement. Check the grade and drainage at both ends: a 2.75-ft drop must be run out over a long approach on each side, and the invert drains must still reach an outfall. Confirm the profile at many stations, because the arch shape varies along an old tunnel.

Open the arch tunnel clearance calculator →

For railroad work: Ask for a laser-scan clearance survey before choosing a method, and check every tight spot, not only a typical section. Design track lowering together with the footing and drainage details, and plan staged work within track windows with the lining monitored throughout.