Monitoring tells whether a defect is stable or getting worse, and how fast. The common tools for existing tunnels are:
Set alert and action levels for each instrument from the expected behavior and the consequences, tie each level to an action (more frequent readings, a slow order, closure and inspection), and give the plan to the dispatcher and track supervisor. Observation-based methods, in which measured deformation is back-analyzed to update the rock parameters and the support, are described by Sharifzadeh et al. ([S4], Ch. 15).
For railroad work: Readings are only useful if someone looks at them. Assign a responsible engineer for each monitored tunnel, plot each instrument against time with its alert and action levels, and review the plots on a set schedule and after any event. Use the trend, not a single reading, to decide what to do; see Question 6.6-1.