6.6.1 Railroad Tunnel Types and Typical Problems

Inspection, assessment, repair and clearance improvement of existing railroad tunnels and their portals.
Author: Daniel P. Colwell
6.6.1 Railroad Tunnel Types and Typical Problems

The lining type, or lack of one, controls what can go wrong and how a tunnel should be inspected and repaired.

Table 6.6-1. Railroad tunnel types and their typical problems
TypeWhere foundTypical problemsNotes
Unlined rockStrong, massive rock (granite, gneiss, quartzite, massive sandstone and limestone)Loose blocks and rockfall from the crown and walls; slaking of shale and mudstone layers; water and iceScaling and spot bolting are the usual maintenance. Weak beds within strong rock are the most common source of falls.
Timber-lined (sets and lagging)Weaker or blocky rock in early tunnelsDecay, insect damage, fire, crushed or displaced sets, voids behind laggingMany were later replaced or encased in concrete or shotcrete. Remaining timber is a fire and collapse hazard.
Brick or stone masonry archSoil, weak rock and portals of 19th-century tunnelsLost mortar, ring separation, bulging, dropped stones, water through joints, freeze-thaw damageMasonry arches carry load by compression; loss of shape or of mortar in joints reduces capacity.
Plain (unreinforced) concreteLinings placed from about 1900 onward, often over timber or masonryCracking, spalling, cold-joint leakage, voids behind the lining, alkali-silica reaction, freeze-thaw near portalsVoids behind old linings are common where concrete was placed against timber or loose rock.
Reinforced concrete or shotcreteRehabilitation work and later tunnelsCorrosion of reinforcement where water and deicing salts reach it, delamination, drummy shotcreteCheck cover and chloride where leakage is heavy.
Steel liner plate or ribsRepairs, short tunnels, portal extensionsCorrosion at the invert and where water dripsSection loss at the base of ribs is the usual weak point.

Problems that apply to all types are water inflow and ice, clearance that is too small for modern equipment, drainage that has silted or frozen, and portals where the slopes above are unstable.

For railroad work: The type of lining often changes along a tunnel: rock in the middle, masonry or concrete near the portals and through weak zones. Record the lining type and its limits by station (or distance from a portal) in the inventory, because the inspection method, the defects to look for and the repair options change at each boundary.