The FHWA Highway and Rail Transit Tunnel Inspection Manual [S1] and the later Tunnel Operations, Maintenance, Inspection, and Evaluation (TOMIE) Manual [S2] set out the inventory, inspection and condition-rating practice now used for tunnels. The 2005 manual has since been superseded by the TOMIE Manual, which the National Tunnel Inspection Standards (23 CFR 650 Subpart E, 2015) incorporate by reference for highway tunnels on public roads. The standards do not apply to freight railroad tunnels, but their inspection intervals, element-by-element condition states and reporting of critical findings are a sound model for a railroad program. For railroad tunnels, the AREMA Manual for Railway Engineering covers design, maintenance and construction, and ventilation in Chapter 1, Part 8 [S8]. Railroads follow their own programs, but the same approach applies.
Laser scanning records the whole surface in 3D with images, so the data can be measured later and compared with the next scan. In rock tunnels it has been used for fracture mapping, locating water leakage, overbreak and underbreak, checking shotcrete thickness and monitoring deformation ([S4], Ch. 18). For railroad tunnels, a mobile scan from a track vehicle gives the clearance profile at close spacing along the whole tunnel in one track window.
Record each defect with its location (station, clock position or offset from centerline, height), type, size, and a photograph, and give it a condition rating. The FHWA manuals rate tunnel elements from 9 (new) to 0 (failed). GHRM uses the 1-to-5 risk scale of Chapter 3.8, and Table 6.6-6 in Section 6.6.11 maps tunnel defects to that scale.
For railroad work: Inspect from a work train or hi-rail vehicle with lights and a lift, under track protection, and allow enough window time to sound the lining and not only look at it. Mark each defect on the lining with a paint number and station so it can be found again. Re-scan after any reported change, and compare the scans to find movement that a visual inspection would miss.