6.6.0 Purpose and Overview

Inspection, assessment, repair and clearance improvement of existing railroad tunnels and their portals.
Author: Daniel P. Colwell
6.6.0 Purpose and Overview

Most railroad tunnels in North America were driven between the 1850s and the 1930s. They were built for smaller equipment, often by hand or with early drilling and black powder, and lined (if at all) with timber, brick, stone masonry or unreinforced concrete. Many are now more than a century old and carry heavier, taller and more frequent trains than they were designed for. This chapter is about keeping those tunnels safe and in service:

Design of new tunnels (excavation methods, NATM and TBM tunneling, support design for new openings) is outside the scope of this chapter. Settlement of track above a new tunnel driven beneath the railroad is covered in Chapter 6.2, Section 6.2.7. Blasting near track is covered in Chapter 5.3, Section 5.3.27.

For railroad work: A tunnel failure closes the line, often for weeks, and there may be no practical detour. Treat each tunnel as an asset with its own inspection record, risk rating and repair plan, and inspect it with the same care as a bridge. Keep the original construction records, later repair records and every inspection report together, because the history of a tunnel explains most of its defects.