Practice questions use the five-part format: Given, Required, Equations, Steps and Solution.
A crown crack in the plain concrete lining of a single-track tunnel on a Class I railroad located in West Virginia is being monitored with a crack gauge. The railroad has set an action level of 0.050 in. of opening, at which a slow order is imposed and an in-depth inspection is made. Six readings have been taken two months apart over one year. The engineer must estimate the opening rate and how long remains before the action level is reached, and say what should be done now.
| Variable | Value | Description |
|---|---|---|
| t | 0, 2, 4, 6, 8, 10 months | Reading times |
| w | 0.018, 0.021, 0.023, 0.026, 0.030, 0.033 in. | Crack opening readings |
| wA | 0.050 in. | Action level |
The crack is opening about 0.0015 in. per month and will reach the 0.050-in. action level in roughly a year if the trend continues.
A steady opening over a full year, through all seasons, is not a seasonal (thermal) cycle: it shows continuing movement of the lining, so the crack should be treated as structural. Do not wait for the action level. Arrange an in-depth inspection now: map all cracks in that section, measure the crown profile by laser scan to check for flattening, run GPR along the crown to look for voids above the lining, and check the drainage. Increase the reading frequency to monthly, add a second gauge and convergence pins, and record temperature with each reading. If the rate increases, or the inspection finds a void or flattening, plan contact grouting or a lining repair and consider interim protection over the track.