6.6.5 Squeezing and Swelling Ground

Inspection, assessment, repair and clearance improvement of existing railroad tunnels and their portals.
Author: Daniel P. Colwell
6.6.5 Squeezing and Swelling Ground

Some rocks keep moving into a tunnel long after it was built:

  • Squeezing is time-dependent shear deformation of weak rock (clay shale, fault gouge, weathered schist) around the opening when stresses exceed the rock mass strength.
  • Swelling is volume increase when certain rocks take up water: clay shales and mudstones with swelling clay minerals, and anhydrite that hydrates to gypsum.

In old railroad tunnels both usually show as floor heave, with the track rising and needing repeated surfacing, and as inward movement and cracking of the walls. Wetting by leakage or a blocked drain often starts or speeds up swelling.

Aksoy and Gulsev Uyar describe a design approach for such rocks in which the support is sized so that deformation does not exceed an amount set by analysis, using time-dependent rock mass parameters and three-dimensional models, rather than trying to stop deformation altogether ([S4], Ch. 6). For an existing tunnel, the practical steps are to keep water away from the swelling rock, measure the movement and its rate, and design any invert slab or wall strengthening for the measured behavior.

For railroad work: Where a tunnel needs frequent surfacing for floor heave, survey the track profile and the tunnel profile at the same stations on each visit, and take cores of the invert rock for swelling tests. Restore the invert drainage first. A structural invert slab may be needed, but placing it without dealing with the water usually only moves the problem.