| Problem | Methods | Notes |
|---|---|---|
| Loose rock in unlined sections | Scaling; spot or systematic rock bolts; wire mesh; shotcrete | Design from mapping and the Q-system check (Section 6.6.4). Test bolts in place (Chapter 6.3, Section 6.3.7). |
| Spalling and delamination of concrete | Remove loose material; patch with repair mortar or shotcrete; mesh or netting as interim protection | Find and fix the water source first. |
| Lost mortar and loose masonry | Repointing; replacing units; stitching or anchoring rings | Use mortar compatible with the original (often lime-based). |
| Voids behind the lining | Contact grouting through drilled holes, starting low and working up | Control grout pressure to avoid damaging the lining; provide drainage. |
| Water inflow | Chemical or cementitious grouting of leaks; drainage behind the lining; channels and drain pipes on the lining surface | Never seal without a drainage path. |
| Deteriorated or under-strength lining | Shotcrete overlay (plain, mesh or fibre-reinforced); steel ribs or arches; new cast or precast lining | Check clearance first; an overlay reduces it. |
| Floor heave | Restore drainage; structural invert slab; rock bolts in the invert | See Section 6.6.5. |
| Portal instability | Slope stabilization; portal extension or canopy; rockfall protection | See Section 6.6.6. |
Repairs in an operating tunnel are done in short windows, often at night, and must leave the track safe for traffic at the end of each shift. Materials and methods that can be installed in stages, and that cure quickly, are preferred. Ventilation and dust control are needed for shotcrete and grouting.
For railroad work: Repairs that reduce clearance (shotcrete overlays, ribs, new linings) must be checked against the clearance envelope before design is finished, using the laser-scan profile. Record each repair by station in the tunnel file so later inspections can tell repair from original lining.