Tunnels fit the GHRM risk framework of Chapter 3.8: a likelihood (frequency) rating from 1 to 5 for each element, a consequence (severity) rating, and a current risk from their combination. Table 6.6-5 gives the likelihood levels for the main tunnel elements, with the reasoning for each level.
| Rating | Lining (concrete, masonry) | Unlined rock | Water and ice | Portal | Rationale |
|---|---|---|---|---|---|
| 1 Very low | Sound; hairline cracks only; no voids found | Massive rock, Q > 10; no falls on record | Dry or damp; no ice | Stable slopes; no rockfall | No defect that could develop into a failure within the inspection cycle. |
| 2 Low | Minor cracks and spalls; stable over several inspections | Q 4–10; occasional small falls removed by scaling | Minor drips; small ice removed routinely | Minor raveling caught by the ditch | Defects present but stable; routine maintenance controls them. |
| 3 Moderate | Cracks or spalls over the track; small voids; loose masonry units | Q 1–4, or a weak bed or fault in otherwise good rock; repeated falls from one location | Steady leaks; ice in the clearance envelope some winters | Rockfall reaching the track occasionally; old instability | A defect that could reach the track or the train between inspections; needs a repair plan and closer inspection. |
| 4 High | Widening crown cracks; delamination over the track; voids above the crown; lost mortar over large areas | Q 0.1–1 without adequate support; recent falls onto track | Heavy inflow; ice in the envelope every winter; washing of fines | Active slope movement above the portal; recent rockfall onto track | Deterioration is active and a failure affecting traffic is plausible within the next year; monitor and repair soon, with interim protection. |
| 5 Severe | Arch deformation; new large cracks or spalling; falling material | Q < 0.1 unsupported, squeezing ground, or a fall that left an overhang | Inflow carrying sediment; ice blocking the envelope | Movement of the portal structure; large blocks perched above the portal | Failure is likely or under way; restrict or stop traffic until made safe. |
Consequence depends on train speed, traffic, whether passengers or hazardous materials are carried, the length of an outage (often much longer for a tunnel than for an open line), and whether a detour exists. Combine the ratings with the 5×5 matrix of Chapter 3.8. Risk reduction ratings for the chosen repair follow the same chapter.
For railroad work: Rate each tunnel by segment (portal zones, lining types, fault zones) rather than as a whole, because one bad segment controls the risk. Re-rate after every in-depth inspection and after any event, and feed monitored changes into the live rating described in Chapter 3.8.