Pile Group Load Distribution

Companion to Chapter 6.1 · Foundation Engineering: Bearing Capacity, Section 6.1.21 Load Distribution in a Pile Group. English units throughout.

Sketch of the inputs

pgrpcentroidP at (xP, yP)xyPlan of the cap: pile loads p = P/n ± My·x/Σx² ± Mx·y/Σy² about the centroid.

Plan of a rigid pile cap with an eccentric load; the group acts as a section in combined axial load and bending. Not to scale.

Use and limitations

This calculator implements the method described in the manual section linked above. It is for planning, checking and teaching; design values must come from site-specific data, the governing railroad and agency standards, and the judgment of the responsible engineer.