2.6.6 Railroad Design Options Over Peat

Peat and organic soil are mostly water held in plant remains. They are the weakest and most compressible ground a railroad crosses: they settle for decades through secondary compression, carry little load, and keep moving long after the fill is placed.
Author: Daniel P. Colwell
2.6.6 Railroad Design Options Over Peat
Table 2.6-7: Options for Track and Embankments Over Peat and Organic Soil
OptionHow it worksBest forCautions
Excavate and replaceRemove peat and backfill with granular soilPeat less than about 10 to 15 ft thick; new alignmentsTrack outage; dewatering; disposal of peat; soft bottom
DisplacementPush fill through the peat by end-dumping, sometimes with blastingShallow bogs with a firm basePeat pockets left in the fill cause long-term settlement
Preloading and surchargingPlace fill above grade, wait for primary consolidation, then remove the surchargeMost cases where time is availableStability during loading; monitoring; secondary compression continues
Lightweight fillReduce the added load with expanded polystyrene (EPS) geofoam (1 to 2 pcf), expanded shale or clay aggregate (about 45 to 65 pcf), tire-derived aggregate (about 45 to 60 pcf) or wood chipsWidening and raising existing track; limiting settlementEPS buoyancy and fuel resistance; cover thickness; tire-derived aggregate layer limits for heating
Basal geosynthetic reinforcementHigh-strength geotextile or geogrid at the base spreads the load and resists spreadingFills where stability governsDoes not reduce settlement
Column-supported embankmentPiles, rigid inclusions or deep mixed columns with a load transfer platformHigh fills; tight settlement limits; bridge approachesCost; drag on piles
Mass stabilizationMix binder (cement or cement with slag) into the peat in placeShallow peat up to about 15 to 20 ftLaboratory mix design required; high binder demand in fibric peat
Floating track on matsDistribute load with log corduroy, timber or geosynthetic matsHistoric practice; temporary accessOngoing settlement and maintenance
CAD drawing sheet showing preferred bricklayer and herringbone GEOTERRA mat layout patterns, a side-to-side temporary layout, the GEOTERRA material specificatio
Photo 2.6.6-1. Typical GEOTERRA Mat Layouts — including the Material Specification table and Unit Dimensions diagram. Presto Geosystems, GEOTERRA–A1.DWG.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
CAD drawing sheet showing the PadLoc connection device detail, the GEOTERRA earth anchor detail, and a labeled GEOTERRA system cross-section
Photo 2.6.6-2. GEOTERRA System Components — PadLoc® Connection Device detail, Earth Anchor detail, and system cross-section. Presto Geosystems, GEOTERRA–B1.DWG.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
CAD drawing sheet showing five labeled GEOTERRA typical cross-section designs, from a basic non-woven geotextile layer up to a full drainage-cell assembly with
Photo 2.6.6-3. GEOTERRA Design Guidelines — five typical cross-section designs, from Design 1 (units and connection device only) up to Design 5 (units, drainage cell, and dual high-strength/non-woven geotextile layers), with their typical applications. Presto Geosystems, GEOTERRA–C1.DWG.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
Photograph of the T-handled Torsion Tool, a long thin metal rod with a slotted end and a perpendicular T-shaped handle
Photo 2.6.6-4. Torsion Tool. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
Photograph of the Earth Anchor Drive Rod, a long thin metal rod with a red protective cap at the striking end
Photo 2.6.6-5. Earth Anchor Drive Rod. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
Photograph of the Earth Anchor Set Tool, a T-handled rod with a length of chain ending in a hook
Photo 2.6.6-6. Earth Anchor Set Tool. Credit: photographer not stated in the source.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
CAD drawing sheet showing four GEOTERRA pre-assembled mat sections being connected together with connector units for truck or container transportation, plus mat
Photo 2.6.6-7. GEOTERRA Pre-Assembled Mats for Truck/Container Transportation — connecting pre-assembled mat sections with connector units, plus mat laying dimensions. Presto Geosystems, GEOTERRA–D1.DWG.Source: Presto Geosystems product literature (GEOWEB® / GEOTERRA®).
Installation of a Ringtrac geotextile encased sand column
Photo 2.6.6-8. Completed Ringtrac® geotextile encased sand column. (Photograph courtesy of Huesker, Inc.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Ringtrac geotextile encased sand columns at Muhlenberger Loch
Photo 2.6.6-9. Ringtrac® geotextile encased sand columns at Mühlenberger Loch. (Photograph courtesy of Huesker, Inc.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
VCC vibratory rig
Photo 2.6.6-10. VCC vibratory rig. (Photograph courtesy of James Collin.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Full view of vibratory rig
Photo 2.6.6-11. Full view of vibratory rig. (Photograph courtesy of James Collin.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
VCC installation
Photo 2.6.6-12. VCC installation. (Photograph courtesy of James Collin.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Successive installation of VCCs
Photo 2.6.6-13. Successive installation of VCCs. (Photograph courtesy of James Collin.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.
Withdrawal of vibratory probe during VCC installation
Photo 2.6.6-14. Withdrawal of vibratory probe during VCC installation. (Photograph courtesy of James Collin.)Source: FHWA / SHRP2 R02, GeoTechTools.org technology photo sheet.

See Chapter 7.2 and the ground improvement technology library (Section 7.2.16) for details of each method.

Compensated fill

Where settlement must be limited, design the new load to replace the weight of material removed or to keep the added stress small:

Δσnet = Σ γi hi (new fill) − γremoved hremoved

Eq. 2.6-5 (net added stress on the peat)

For example, replacing 4 ft of soil fill (120 pcf, 480 psf) with 4 ft of lightweight aggregate (55 pcf, 220 psf) cuts the added stress by more than half; see Example 2.6-2.