2.6.11 Practical Recommendations
Peat and organic soil are mostly water held in plant remains. They are the weakest and most compressible ground a railroad crosses: they settle for decades through secondary compression, carry little load, and keep moving long after the fill is placed.
Map the extent and thickness of organic soils with probing, closely spaced borings or CPTu and ground-penetrating radar; one boring is not representative of a bog.
Run organic content (ASTM D2974) and moisture content on every sample; classify peat by fiber content.
Run consolidation tests with long load increments to measure secondary compression; report Cα/Cc.
Compute settlement in thin sublayers and account for submergence of the fill.
For widenings, design for differential settlement between old and new tracks, not just total settlement.
Use lightweight fill, surcharging or column support where settlement must be limited; basal reinforcement only for stability.
Do not lower the water table next to track on peat without estimating oxidation settlement.
Monitor fills on peat with settlement plates, piezometers and inclinometers, and expect settlement to continue after construction.