2.6.13 Practice Questions

Peat and organic soil are mostly water held in plant remains. They are the weakest and most compressible ground a railroad crosses: they settle for decades through secondary compression, carry little load, and keep moving long after the fill is placed.
Author: Daniel P. Colwell
2.6.13 Practice Questions
Each question is worked in the same five parts as the examples.
Question 2.6-1: Classify a Peat Sample

Problem Statement

A Class I railroad is extending a passing track across a bog, and a sample from beneath the alignment has the organic content and fiber content shown. The engineer must classify the peat and say what the classification means for compressibility and drainage under the new track.

Sapric < 33%Hemic 33–67%Fibric > 67%0100%Fiber contentsample: 45%Organic content 62% (ASTM D2974); peat if > 30%Classification = ? Compressibility and drainage?GivenOC = 62% (ash content)Fiber = 45%Peat: OC > 30%Fibric > 67; hemic 33–67; sapric < 33RequiredClassificationMeaning for compressibility and drainageBlack = given; red = required
Given and required for Question 2.6-1.

Given

VariableValueDescription
OC62%Organic content by ash content (ASTM D2974)
Fiber45%Fiber content
CriteriaTable 2.6-2 and the von Post/ASTM fiber classesPeat: organic content > 30%; fibric > 67%, hemic 33 to 67%, sapric < 33% fibers

Required

  • Classification

Equations

No equation is needed; the answer follows from the criteria listed under Given.

Steps

Step 1 · Organic soil or peat?
62% is between 30% and 75%
Peat (USCS PT)
↓
Step 2 · Degree of decomposition
45% fibers is between 33% and 67%
Hemic
↓
Solution
Hemic peat (PT).

Solution

Hemic peat, USCS PT.

Hemic peat is moderately decomposed: more compressible and less permeable than fibrous (fibric) peat, but less so than amorphous (sapric) peat. The class guides the choice of starting values in Table 2.6-9 until tests are available.

Question 2.6-2: Single-Stage Fill Height on Peat

Problem Statement

A Class I railroad needs to place fill on peat for a new siding across a bog. The peat has the undrained strength shown, and the required factor of safety is 1.3. The engineer must find the maximum fill height that can be placed in one stage.

The strip bearing screen of Example 2.5-1 applied to peat.

Peat bog, su = 250 psfFill γ = 120 pcfHmax = ?Givensu = 250 psfγ = 120 pcf (fill)FS = 1.3RequiredMaximum single-stage fill heightBlack = given; red = required
Given and required for Question 2.6-2.

Given

VariableValueDescription
su250 psfUndrained strength
γ120 pcfFill
FS1.3Required

Required

  • Maximum single-stage fill height

Equations

  1. Eq. 2.6-4: Hmax = 5.14 su / (γ FS) — wide fill, undrained; same form as Eq. 2.5-10

Steps

Step 1 · Hmax (Eq. 2.6-4)
5.14 × 250 / (120 × 1.3) = 1,285 / 156
Hmax = 8.2 ft
↓
Solution
Hmax = 8.2 ft.

Solution

About 8.2 ft of fill in one stage.

Higher fills need staged construction or lightweight fill. On peat the screen is only a starting point: peat strength varies widely over short distances, and lateral squeeze can occur before bearing failure, so the fill should be placed with settlement plates and toe inclinometers.

Question 2.6-3: Secondary Settlement of Peat Over 25 Years

Problem Statement

A railroad embankment across a peat bog completed primary consolidation six months after construction. The railroad wants to know how much more the track will settle over the next 25 years to plan surfacing. The engineer must estimate the secondary settlement of the 8-ft peat layer.

Secondary compression continues long after the excess pore pressure is gone, and in peat it is a large part of the total.

0.1110100Time (years, log)Settlementtp = 6 months25 yrSs = ?Peat H = 8 ft; Cα/(1+ep) = 0.03GivenH = 8 ftCα/(1+ep) = 0.03tp = 6 monthst = 25 yearsRequiredSecondary settlement from 6 months to 25 yearsBlack = given; red = required
Given and required for Question 2.6-3.

Given

VariableValueDescription
H8 ftPeat thickness
Cα/(1 + ep)0.03Secondary compression ratio
tp6 monthsEnd of primary consolidation
t25 yearsEnd of the period

Required

  • Secondary settlement between 6 months and 25 years

Equations

  1. Eq. 2.6-3b: Ss = H [Cα/(1 + ep)] log(t/tp) — secondary settlement

Steps

Step 1 · Time ratio
25 / 0.5
50
↓
Step 2 · Ss (Eq. 2.6-3b)
8 × 0.03 × log 50 = 0.24 × 1.70
Ss = 0.41 ft (about 5 in.)
↓
Solution
About 5 in. of secondary settlement.

Solution

About 0.41 ft (5 in.) between 6 months and 25 years.

Because settlement follows the logarithm of time, half of it (about 2.5 in.) occurs in the first 3.5 years after primary consolidation and the rest over the following 21 years. Track over peat should be expected to need surfacing for decades.