2.6.15 Mass Stabilization of Peat Beside and Beneath Track

Peat and organic soil are mostly water held in plant remains. They are the weakest and most compressible ground a railroad crosses: they settle for decades through secondary compression, carry little load, and keep moving long after the fill is placed.
Author: Daniel P. Colwell
2.6.15 Mass Stabilization of Peat Beside and Beneath Track

Mass stabilization mixes a dry binder, usually portland cement, into peat or soft organic soil in place, turning it into a stiff cement-modified soil without excavation. It was developed in Scandinavia and is now used in the northern United States and Canada. The track applications described in a 2014 conference paper include treated zones along both sides of an embankment to confine it, treated pads that act as working platforms for pile rigs, column walls that damp train vibration, and treated embankment beside a lake to carry heavier freight. Excavator-mounted power mixers with a pressure feeder suit railway work to about 25 ft; crane-supported augers go deeper. High-rail excavators allow spot treatment along an operating line.

2.6.15.1 Design quantities

Table 2.6-10. Published mass stabilization data
ItemValue
Binder addition rate, typical range100 to 350 lb per cu yd
Peat and silt beside a high-speed line, sulfate-resistant cement170 lb/cu yd (100 kg/m³) gave about 5 psi (40 kPa) shear strength
Working platform for 55-ton (50-tonne) pile rigs, ordinary cement340 lb/cu yd (200 kg/m³), 15 ft thick
Embankment beside a lake500 ft long, 30 ft wide, 23 ft deep
Binder share of project cost50 to 70%

Dry injection uses the water already in the soil and generally needs less cement than wet grout mixing, whose water-cement ratio must exceed 1 to be pumpable.

The addition rate is set by a bench-scale mix design: several binders and rates are mixed into samples of the actual soil, cured and tested for strength and, where needed, permeability. Because binder dominates the cost, the cheapest mix that meets the strength target is chosen. GPS-guided mixing heads with metered binder feed record each block for quality control.

2.6.15.2 Worked example: treated strip beside an embankment

Table 2.6-11. 500 ft × 30 ft × 23 ft deep at 170 lb/cu yd (calculator output)
ResultValue
Treated volume12,778 cu yd
Cement1,086 tons
Per foot of track2.17 tons/ft
Addition rate101 kg/m³

About 1,100 tons of cement for 500 ft of track shows why the binder rate must come from testing rather than a rule of thumb: each 10 lb/cu yd saved removes about 64 tons here. Settlement of untreated peat under fill is covered in Chapter 6.2; the alternative of floating the track on helical piles is described in a 2018 conference paper listed below.

Open the mass stabilization calculator →
Treated volume, binder tonnage at a chosen addition rate, binder per foot of track, and an order-of-magnitude cost from the binder share.

Example 2.6-3: Binder Quantity for a Mass-Stabilized Strip

This is the strip of Table 2.6-11, worked by hand. Binder is 50 to 70% of the cost of mass stabilization, so the quantity, and how sensitive it is to the addition rate, is the first number an owner needs.

Mass-stabilizedblockW = 30 ftD = 23 ftL = 500 ftVolume = ? Cement tons, per ft, metric = ?Binder r = 170 lb/cu ydGivenL × W × D = 500 × 30 × 23 ftr = 170 lb/cu ydRequiredTreated volumeCement tonnage, per ft of track, and in metric unitsBlack = given; red = required
Given and required for Example 2.6-3.

Given

VariableValueDescription
L × W × D500 ft × 30 ft × 23 ftTreated block beside the embankment
r170 lb/cu ydBinder addition rate

Required

  • Treated volume
  • Cement tonnage, per foot of track, and in metric units

Equations

  1. Eq. 1: V = L W D / 27 — cubic yards
  2. Eq. 2: B = V r / 2,000 — tons of binder
  3. Eq. 3: 1 lb/cu yd = 0.593 kg/m³ — unit conversion

Steps

Step 1 · Volume (Eq. 1)
500 × 30 × 23 / 27 = 345,000 / 27
V = 12,778 cu yd
↓
Step 2 · Binder (Eq. 2)
12,778 × 170 / 2,000
B = 1,086 tons; 1,086 / 500 = 2.17 tons/ft
↓
Step 3 · Metric rate (Eq. 3)
170 × 0.593
101 kg/m³
↓
Step 4 · Sensitivity
12,778 × 10 / 2,000
Each 10 lb/cu yd changes the binder by about 64 tons
↓
Solution
12,778 cu yd; 1,086 tons of cement; 2.17 tons per foot.

Solution

12,778 cu yd treated; 1,086 tons of cement, or 2.17 tons per foot of track, at 101 kg/m³.

At this scale every 10 lb/cu yd saved removes about 64 tons of cement, which is why the addition rate is set by a bench-scale mix design on the actual peat rather than by a rule of thumb.

2.6.15.3 Sources in the library

These documents are in the reference library. The summaries above are paraphrased; equations and tabulated limits are standard or published values. Individual railroads are not named.

  • AREMA conference paper (2014): stabilization of marginal soil in new and existing right-of-way (mass stabilization, Finnish rail projects).Find source ↗
  • AREMA conference paper (2015): rapid subgrade stabilization by injection on high-volume main line over peat and organic silt.Find source ↗
  • AREMA conference paper (2018): track support on a floating soil beam carried by helical piles.Find source ↗
  • AREMA conference paper (2012): settlement of a passenger maintenance yard built on fill over bay mud.Find source ↗
  • AREMA Manual for Railway Engineering, Chapter 1 Roadway and Ballast (2012, Volume 1), Part 1, Section 1.6 Alternative ground improvement methods.Official page ↗