2.6.7 Other Hazards of Organic Soils

Peat and organic soil are mostly water held in plant remains. They are the weakest and most compressible ground a railroad crosses: they settle for decades through secondary compression, carry little load, and keep moving long after the fill is placed.
Author: Daniel P. Colwell
2.6.7 Other Hazards of Organic Soils
HazardRecognitionEngineering response
Oxidation and shrinkage on drainageLowering the water table (new ditches, dewatering) exposes peat to airExpect continuing subsidence, commonly about 0.5 to 2 in. per year, at the surface of drained peat; avoid deep ditches next to track on peat
GasMethane and hydrogen sulfide; bubbling in borings; low unit weightVentilate excavations and confined spaces; account for low saturation in unit weight
Acidic, corrosive waterpH below 5; high sulfateCorrosion protection for steel piles and culverts; sulfate-resistant concrete
Bog bursts and lateral spreadingBulging of peat beyond the toe; tension cracks in the fillToe berms; slow loading; reinforcement
Peat firesDried peat can smolder undergroundKeep peat wet; fire watch during dry-season maintenance near bogs
FreezingFrozen peat is strong in winter and weak after thaw; peat insulates permafrostSchedule work to frozen ground conditions where possible; in permafrost regions, preserve the insulating peat layer