1.1.15 Ground Hazard Risk Screening Matrix and Corridor Risk

Formerly Geo Rail Chapter 7.2 — Railway Geo-Hazard Risk Management

A systematic framework for identifying, assessing, and controlling landslide, hydraulic-erosion, and subsidence hazards along the active railway corridor.
Authors: Daniel P. Colwell and Mario Ruel
1.1.15 Ground Hazard Risk Screening Matrix and Corridor Risk

A Class I railroad's published framework for ground hazards follows the Canadian risk management standard CAN/CSA-Q850: start the program, run a preliminary analysis (identify and classify hazards and write risk scenarios), estimate frequency and consequence, evaluate whether the risk is acceptable, choose controls, then act and monitor, feeding the results back to the start. The framework stresses that how operating employees perceive a hazard matters as much as its frequency and consequence, so communication runs through every step. This section adds the screening matrix and a corridor check to the risk ratings of Chapter 3.8.

1.1.15.1 Classification, scenarios and the risk resolution matrix

Hazards are first split into landslides and hydraulic erosion. Landslides are subdivided by material (rock, debris, earth, snow and ice) and by movement type (fall, topple, slide, flow, spread, subsidence) following Cruden and Varnes. Earth is further split into non-cohesive soils, whose saturated slopes can liquefy and fail with little warning, and cohesive and organic soils, except that sensitive and quick clays behave like the non-cohesive group. Erosion is split into seepage erosion and surface erosion (washouts). A risk scenario links a hazard (a condition) to a peril (the trigger: intense or prolonged rain, rapid snowmelt, rain on snow, high stream flow, freeze-thaw, earthquake) and a loss (injury, property, liability, environment, lost service). River erosion that oversteepens a slope, followed by a storm that triggers an earth slide under the track, is the typical chain. The scenarios the framework rates as most critical are rock falls, debris flows, earth slides in silt and fine sand, river erosion, and washouts from beaver dam failure and rapid runoff, because they are frequent, give little warning and have severe consequences.

Table 1.1-3. Risk resolution matrix (commuter rail system safety manual, as used in the framework)
ProbabilityCatastrophicCriticalMarginalNegligible
FrequentUnacceptableUnacceptableUnacceptableTolerable with mitigation
ProbableUnacceptableUnacceptableTolerable with mitigationTolerable with mitigation
OccasionalUnacceptableTolerable with mitigationTolerable with mitigationTolerable
RemoteTolerable with mitigationTolerable with mitigationTolerable with mitigationTolerable
ImprobableTolerable with mitigationTolerable with mitigationTolerable with mitigationTolerable

Severity: catastrophic = death or major system loss; critical = permanent partial disability or major damage; marginal = minor injury or damage; negligible = first aid or minor impairment.

Controls are preferred in this order: reduce the hazard (stabilize the slope or channel), protect the track from it (sheds, barriers, catchment ditches and nets, flumes), and only then warn trains (slide detector fences, or notices triggered by rainfall or earthquake magnitude). Warning systems suit hazards too long or too large to remove. Priorities are set in an annual grade stabilization plan, prepared well ahead of the work season so designs, permits and bids can be completed.

The framework also warns that many sites each of low individual risk can add up to a high risk for the corridor, especially when one storm or earthquake can trigger several of them. If pi is the estimated annual probability of an event at site i, the chance of at least one event in the corridor in a year is 1 − Π(1 − pi), assuming the sites are independent. A shared trigger makes the events correlated: the chance of at least one event is then a little lower than this value, but the chance of several sites failing in the same storm, and the size of the loss, are much higher.

1.1.15.2 Worked example: five sites on one subdivision

Table 1.1-4. Hazard register screened with the calculator
SiteScenarioProbability, severityResult
1 rock cutRock fall onto trackProbable, critical; p = 0.15/yrUnacceptable
2 fill over creekWashout of embankmentRemote, catastrophic; p = 0.01/yrTolerable with mitigation
3 silt cut slopeEarth slide (non-cohesive)Probable, marginal; p = 0.20/yrTolerable with mitigation
4 culvert below beaver pondWashout from dam breachOccasional, critical; p = 0.03/yrTolerable with mitigation
5 ditch-line seepageSeepage erosionRemote, negligible; p = 0.10/yrTolerable
CorridorAt least one event0.412 per year; 0.995 over 10 years

Only the rock cut is unacceptable on its own, but the subdivision as a whole can expect an event in about two years out of five. That is the case for corridor-wide measures such as rainfall-triggered inspection or slow orders in addition to site work.

Open the risk screening calculator →
Place each hazard site in the probability-severity matrix, sort the register, and compute the corridor probability of at least one event.

1.1.15.3 Sources in the library

These documents are in the reference library. The method summaries above are paraphrased; equations are standard or published forms.

  • A Risk Management Framework for Ground Hazards along a Class I railroad (conference paper): Q850 process, hazard classification, risk scenarios, risk resolution matrix, control hierarchy, earthquake and weather notification. Risk Management folder.Find source ↗Library entry
  • Cruden and Varnes (1996), landslide types and processes, as cited in the framework.Find source ↗