↑ Parent Menu⌂ Main Menu
← Chapter 1.1 Introduction to Railway Ground Hazard Risk Management
GHRM
Railway Ground Hazard Risk Management · 1.0 · Introduction
Sections · click a car to open it

1.1.9 Risk Control Hierarchy

Formerly Geo Rail Chapter 7.2 — Railway Geo-Hazard Risk Management

A systematic framework for identifying, assessing, and controlling landslide, hydraulic-erosion, and subsidence hazards along the active railway corridor.
Authors: Daniel P. Colwell and Mario Ruel
1.1.9 Risk Control Hierarchy

Risk Control is any conscious action — or documented decision not to act — that reduces the frequency, severity, or unpredictability of a loss. The preferred approach is always proactive mitigation of the loss exposure itself, which is almost always more cost-effective than absorbing the cost of a derailment or unplanned service disruption. In order of preference:

  1. Reduce the hazard condition through mitigative stabilization (regrading, drainage improvement, ground improvement, rock scaling/bolting).
  2. Protect the track against the hazard with physical works — flumes, rock or snow sheds, barriers, catchment nets.
  3. Warn trains in the event a hazard is triggered — used when the extent of the hazard practically precludes the first two approaches, and targeted either at the hazardous event itself (a slide- or rockfall-detection fence) or at the triggering peril (an earthquake or weather notification system, per Section 1.1.8).

Once a site is prioritized through the risk-resolution matrix (Section 1.1.7), the applicable risk-control measure typically falls into one of four categories: Drainage Modifications, Engineering (regrading, retaining structures, rock reinforcement), Ground Improvements (see Chapter 7.2, Section 7.2.16 — Ground Improvement Technology Library), and Structural Installations (sheds, fences, nets, culvert replacement). The single most under-respected principle across every category is drainage: a railroad should invest roughly 3% of its operating budget on drainage and ditch maintenance, but in practice that spending competes with — and often loses to — rail and crossing work, until poor drainage becomes the problem that stops service.

Life-cycle costing and RAMS as the frame for risk controls

Profillidis places maintenance and renewal decisions inside two cost concepts — the life-cycle cost of each component (from conception through operation to the end of its economic life) and life-cycle costing, the systematic economic evaluation of those costs over an analysis period — and inside a global performance concept known as RAMS:

  • Reliability — probability that a component performs its required function under given conditions for a given time;
  • Availability — ability to perform that function at a given moment, provided the external resources (people, funding) are in place;
  • Maintainability — probability that a maintenance action can be completed within a stated time using stated procedures and resources;
  • Safety — freedom from unacceptable risk of harm.

For outsourced maintenance he recommends sensitivity analysis of the critical contract terms, confirming that both life-cycle cost and track quality improve, quantifying the probability of non-delivery, and identifying fallback solutions. These are the same questions a ground-hazard risk control should answer before it is selected.

After Profillidis (2014), §16.11. Full reference under Supplemental References.

Project management · Cretu et al. (2011)

Project Risk Response Strategies for Threats and Opportunities

The risk control hierarchy in this chapter addresses the operating hazard. Project risks to the remediation itself (its cost, schedule and constructability) need a parallel set of responses. Cretu et al. use the PMI categories. For threats the options are avoid (change scope so the risk cannot occur), transfer (shift it to a party better able to manage it, usually at a price), mitigate (lower its probability or impact, which is usually cheaper early in the project than late) and accept. Acceptance must be active, with a reserve set aside; ignoring a risk and hoping is not acceptance. For opportunities the options are exploit (make the benefit certain), share (for example a value engineering incentive clause that splits contractor-proposed savings with the owner) and enhance (raise its probability or size). The test for each response is whether its cost is less than the expected impact it removes.

Two of the authors’ examples translate directly. In the first, a retaining wall carried a geologic cost risk, and the risk could be avoided altogether by buying additional land and building an embankment instead. In the second, an owner planned to furnish a tunnel boring machine to the contractor. The team judged that this invited productivity claims and transferred the risk by requiring the contractor to supply its own machine. For extreme, unmodelable events the authors add disaster contingency planning: assume the event happens and prepare actionable recovery steps in advance. A response plan should record the pre- and post-response probability and impact, the action steps, the owner, the timeline and the cost of the response.

For railroad work: Typical avoidance options are realigning a short track segment away from an active slide or replacing a marginal wall with a flatter embankment where right-of-way allows. Typical mitigation options are added borings or test pits before letting, horizontal drains installed ahead of the main work, or staging excavation to match the available track windows. Allocating subsurface risk through the contract is a form of transfer or sharing. A geotechnical baseline and a differing-site-conditions clause let bidders price the baseline rather than carry an unpriced contingency. For accepted risks, set aside a named reserve. Prepare a contingency plan for a reactivation during construction that covers slow-order limits, emergency material stockpiles and who has authority to stop work.

Source: Cretu, O., Stewart, R. and Berends, T. (2011). Risk Management for Design and Construction. Hoboken, NJ: John Wiley & Sons, pp. 153–157, 162–164. Summarized and paraphrased. Full reference under Supplemental References.

Project management · Goldbloom (1989)

Contractual Risk Allocation as a Risk Control

Goldbloom sees the contract as a risk-transfer tool and warns that it is often misused. He says every exculpatory clause an owner adds is a risk the bidder will price into its bid. His allocation principle has three parts:

  • the owner assumes the risks it controls or can bear better;
  • the contractor takes the risks within its control: means and methods, scheduling, procurement, subcontractors, job safety and timely completion;
  • risks neither party controls are shared.

The owner-side risks he lists are differing subsurface conditions, full disclosure of known information, site access, prompt review of submittals, timely payment, escalation on long contracts, and large variations in estimated quantities.

His quantity-variation mechanism works like this. A bidder spreads fixed costs (mobilization, supervision, overhead, profit) over the bid quantity. If the quantity falls, the bidder under-recovers. If it rises, the bidder over-recovers. He cites a transit-authority clause that reprices a major item when the final quantity is more than 25% above or below the estimate. The adjustment applies only to the portion beyond 125% or below 75%, and the clause also allows a time extension. Related drafting points:

  • Call bid quantities estimated, not approximate, because “approximate” implies a tight tolerance.
  • State units of measure without ambiguity.
  • Watch for unbalanced bids that load early items.

Among the information the designer must disclose, he lists the railroad’s train schedule and any other operating limits that restrict the contractor. He also summarizes typical railway provisions:

  • the railroad approves construction methods within its right-of-way;
  • railroad protective liability insurance is required;
  • equipment may not foul an operating track without permission;
  • railroad flaggers are paid by the owner when the work is required by the contract, and by the contractor when the work is for the contractor’s own convenience.

He defines fouling as coming within a specified distance of track centerline, typically 10 to 12 ft, and notes that a machine whose failure could bring it inside that limit is also fouling.

For railroad work: In the risk control hierarchy, contract allocation sits beside engineering and operational controls. For slide repairs and subgrade programs:

  • put the unknown quantities (undercut depth, rock, unsuitable material) on unit-price items with a variation clause, not into a lump sum;
  • disclose track-window availability, slow-order limits and flagging rules in the bid documents;
  • keep differing-site-condition risk with the railroad, and pair it with a good factual report.

Hiding these risks raises the bid price and leads to more disputes. It does not reduce the risk.

Source: Goldbloom, J. (1989). Engineering Construction Specifications: The Road to Better Quality, Lower Cost, Reduced Litigation. New York: Van Nostrand Reinhold, pp. 39–40, 68, 182–186, 300–301. Summarized and paraphrased. Full reference under Supplemental References.

← Previous · 1.0 Introduction Chapter 1.0 — Manual Overview
Next · 2.0 The Underworld → Chapter 2.1 — Track Foundation Elements