Formerly Geo Rail Chapter 7.2 — Railway Geo-Hazard Risk Management
A ground hazard program for an operating railroad is an asset management system for earthworks. UK practice describes the system and the cycle it follows, and the parts map directly onto this manual (McGinnity and Saffari, 2012, pp. 1067–1068, 1073).
| Part | What it contains | In this manual |
|---|---|---|
| Asset catalogue | Inventory of every cut, fill and natural slope with its condition | Chapter 3.2 (desktop study); risk app and KMZ inventory |
| Performance requirements | Safety and reliability, level of service, regulatory duties, cost | Chapter 3.8, Section 3.8.35 (acceptable probability of failure) |
| Condition appraisal | Inspection regime: defect definitions, condition rating, inspection frequency, data collection | Chapter 3.4 (reconnaissance); Chapter 3.8 (ratings) |
| Risk register | Each earthwork's hazards, likelihood, consequence and controls | Chapter 3.8; Chapter 3.8 |
| Strategy and plan | Whole-life cost and deterioration models; priorities for maintenance, repair and renewal | Chapter 3.7 (cost); lifecycle-cost and risk-contingency calculators |
Managing earthworks only after they fail is disruptive and costs more over the life of the asset. A proactive system cycles through condition appraisal, maintenance and repair or renewal, with the data from each inspection feeding the next round of priorities. The questions an asset manager must answer are relative ones: which earthwork needs attention first, how limited funds are best spent, which mechanism is likely (deep-seated, shallow or excessive track movement), what the consequence would be (derailment, delay or nuisance), and when problems are likely to develop (O'Brien, 2013, Table 1, p. 19).
UK practice reduces risk to “as low as reasonably practicable” (ALARP): a safety improvement is made unless its cost is grossly disproportionate to the risk it removes. Whole-life costing compares renewal against continued maintenance but should be used with care for earthworks expected to last indefinitely, because performance requirements, future funding and the discount rate are hard to estimate (McGinnity and Saffari, 2012, pp. 1067–1068). Section 3.8.35 gives the acceptable-probability criteria this manual uses.
Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.