1.1.11 Incident Frequency and the Business Case

Formerly Geo Rail Chapter 7.2 — Railway Geo-Hazard Risk Management

A systematic framework for identifying, assessing, and controlling landslide, hydraulic-erosion, and subsidence hazards along the active railway corridor.
Authors: Daniel P. Colwell and Mario Ruel
1.1.11 Incident Frequency and the Business Case

Natural hazards are a significant, but not the predominant, cause of railway service disruption — in mountain territory they are actually less frequent than most other engineering-related incidents, accounting for on the order of 17% of engineering incidents by count. What makes them a distinct budget priority is that each incident carries a much higher average impact: roughly $1.5M per event in documented industry experience, working out to on the order of half of total engineering-incident cost despite the comparatively low incident count.

Because major geo-hazard occurrences fluctuate substantially year to year, the natural organizational tendency is to stay vigilant immediately after a significant event and then relax attention until the next one. A funded, followed R.M. plan is specifically designed to break that cycle — it forces sustained, proactive, yearly mitigation spending regardless of how recently an incident actually occurred. Because the consequence side of the risk equation is so high for natural-hazard scenarios, the same incident-cost data that justifies the program in the first place is also the strongest argument for securing its funding: a documented plan that is not consistently followed is worse, from both a safety and a liability standpoint, than having no plan at all.

European accident statistics and causes

Under European Regulation 1192/2003 a significant rail accident involves at least one rail vehicle in motion and results in at least one person killed or seriously injured, significant damage (at least €150,000) to rolling stock, track, other installations or the environment, or extensive interruption of traffic. In 2011 the 27 EU countries recorded 2,685 significant accidents, with 2,325 people killed or seriously injured. Of the fatalities, 60% were unauthorized persons, 29% level-crossing users, 5% passengers and 2% employees.

Figure 1.1-7. Effects of railway accidents in the 27 EU countries, 2011, by accident type (killed, seriously injured). Profillidis Table 22.4.
Figure 1.1-7. Effects of railway accidents in the 27 EU countries, 2011, by accident type (killed, seriously injured). Profillidis Table 22.4.

The causes listed by the book include inadequate track maintenance leading to derailment, mechanical failure of wheels and rails, an earthquake while a train is moving, and a collapsed bridge — the ground-hazard and track-support categories this manual addresses — alongside level crossings, signaling, switching and human factors. Accidents causing fatalities per billion train-km in the United Kingdom fell steadily from about 11 (1967–71) to below 1 (2007–10). For comparison, the book puts the risk of death at 7 times higher by car and 2 times higher by bus than by rail, and a route comparison for hazardous materials gave rail a risk factor about six times lower than road.

Figure 1.1-8. Accidents causing fatalities per billion train-km, United Kingdom, 1967–2010. Profillidis Fig. 22.17.
Figure 1.1-8. Accidents causing fatalities per billion train-km, United Kingdom, 1967–2010. Profillidis Fig. 22.17.
Figure 1.1-28. Service disruption causes: mechanical, geo-hazards, track failure, train handling, other.
Figure 1.1-28. Service disruption causes: mechanical, geo-hazards, track failure, train handling, other.

After Profillidis (2014), §22.6, Table 22.4, Fig. 22.17. Full reference under Supplemental References.

Service disruption by cause

In mountain territory, natural hazards account for about 17% of engineering-related service incidents by count, but at roughly $1.5M per event they make up about 52% of engineering incident cost. The course also recommends spending about 3% of the operating budget on drainage and ditch maintenance. In practice that spending tends to lose out to rail and crossing work until poor drainage stops service.

After Geotechnology for Railroaders Program, Module 1; §01, §09. Full reference under Supplemental References.

Substructure decisions and life-cycle cost

Why the business case is hard to make. Selig and Waters note that substructure practice has been empirical. Trials take years to show results, maintenance and performance records are poor, and service demands keep changing. Technology spending is also the first thing cut because it shows no short-term return. A geotechnical recommendation therefore needs a cost argument as well as an engineering one.

Four points that support that argument.

  • Axle load. Ballast maintenance cost scales roughly with the fourth power of ballast pressure. A 20% heavier axle about doubles it (Chapter 2.3, §2.2).
  • Inherent track quality. Two sections 0.6 mile apart carried the same traffic. The good one (profile standard deviation 0.059 in.) needed 2 tampings in 5 years. The poor one (0.13 in.) needed 6. Quality built in at construction or renewal pays back over the whole cycle.
  • Tamping policy. Tamp when the geometry needs it, not on a calendar. Each tamping breaks ballast and shortens its remaining life.
  • Least-cost planning. The Chrismer–Selig maintenance model takes ballast gradation, Abrasion Number, annual MGT and the wheel-load distribution. It predicts settlement and remaining ballast life year by year for each option: tamp, undercut or clean, shoulder clean, plow or sled, or do nothing. It converts each option to an equivalent annual cost per mile, discounted to year 0. Compare options to the end of the current ballast life, and vary ballast type and the settlement limit to find the cheapest plan.

After Selig & Waters (1994), chs. 1, 8, 15 and 16. Full reference under Supplemental References.

Project management · Rad (2002)

Schedule Compression Cost and Expected-Value Risk Funds

Rad treats cost, schedule and scope as linked. Changing any one moves the others.

Duration. Each activity has an optimum duration, the one that uses the optimum crew size and shift length and so has minimum cost. Departing from it costs more in either direction:

Generic cost-duration curve for an activity, with minimum effort at the normal (optimum) duration and rising cost toward the compress/crash end and the extended-duration end.
Figure 1-PM9. Generic cost-duration curve for an activity, with minimum effort at the normal (optimum) duration and rising cost toward the compress/crash end and the extended-duration end. Source: Rad (2002), Figure 6-7.
  • His rule of thumb is that halving an activity’s duration roughly doubles the total effort.
  • Experience suggests a crash limit of about 50% of optimum duration, and he advises compressing only to a point just above it.
  • Stretching an activity out also costs more, because of extra start-stop cycles and lost continuity. In his ratio, doubling the duration also roughly doubles the effort.

His crew example: one task takes 30 worker-days with 5 people over 6 days, 44 worker-days with 11 people over 4 days, and 60 worker-days with 20 people over 3 days. The losses come from congestion, extra communication and errors.

A schedule can be shortened in two ways:

  • rearrange the network logic so phases overlap (fast tracking), which saves time but makes rework expensive when errors appear;
  • add crews or shifts to critical-path activities.

He warns against padding the baseline with buffers to give away later. Once discovered, it ruins credibility.

Risk. For risk funding he describes a simple expected-value method. For each risk event, estimate the probability of occurrence and the cost if it occurs, and multiply them. The sum is the risk-related contingency. It can go into the project budget or into a separate earmarked fund, depending on how the project is financed.

For railroad work: Both ideas fit the business case for ground-hazard mitigation. For the expected-value calculation, an illustrative register might include:

  • a 10% chance of a $400,000 rock-excavation overrun, worth $40,000;
  • a 5% chance of a $1.2M emergency slide repair during construction, worth $60,000.

These give a defensible contingency line. The project-specific numbers must come from the investigation and the railroad’s own incident records.

For schedule compression, track-window and possession limits often force remediation work into compressed durations. The extra crews, equipment standby and lower productivity that follow should be priced explicitly, not assumed free. When comparing a short-window intensive program with a longer program under a slow order, include the slow-order delay costs and the compression premium in the same comparison.

Source: Rad, P. F. (2002). Project Estimating and Cost Management. Vienna, VA: Management Concepts, pp. 88–96. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Project management · Sullivan et al. (2015)

Benefit–Cost Ratios for Remediation Alternatives: Use the Incremental Test

Sullivan et al. define the conventional B–C ratio as:

B–C = PW(benefits) / [initial investment − PW(salvage) + PW(O&M)]

The modified ratio instead subtracts O&M from the numerator. The two give different numbers but always the same accept/reject decision, as long as the ratio is tested against 1.0. The same holds whether disbenefits are subtracted from benefits or added to costs, and whether a maintenance saving is counted as a benefit or as a reduced cost.

The trap is choosing among mutually exclusive alternatives by the highest ratio. The correct procedure (Figure 10-3) has four steps:

Flowchart of the incremental benefit–cost procedure for choosing among mutually exclusive alternatives.
Figure 1-PM10. Flowchart of the incremental benefit–cost procedure for choosing among mutually exclusive alternatives. Source: Sullivan et al. (2015), Figure 10-3.
  1. Rank the alternatives by equivalent cost.
  2. Accept the cheapest alternative whose B–C is at least 1.0 as the baseline.
  3. Test each more costly alternative on the increment over the baseline, ΔB/ΔC.
  4. If the increment’s ratio is at least 1.0, that alternative becomes the new baseline. Repeat until every alternative has been tested.

In their Example 10-7 at 10% over 50 years, Project A has B–C = 1.34. The B−A increment fails (0.91), but the C−A increment passes (1.16), so C is selected. A has the highest ratio of the three, yet it is not the right choice.

Their case study on a railroad grade-crossing overpass shows why the evaluator’s point of view matters. The city counts the delay to the 2,000 vehicles a day held at the crossing, plus avoided accident costs: about $257,000/yr in benefits against $88,500/yr in annualized costs, for B–C = 2.91. The railroad’s own $30,000/yr saving on crossing protection and claims is left out of the city’s ratio. That saving is worth about $199,000 to the railroad at its 15% cost of capital over 40 years, which gives a sound basis for asking the railroad to contribute.

For railroad work: for a chronic slope or subgrade problem, list the mutually exclusive alternatives:

  • (0) Continue as now: slow order plus recurring maintenance.
  • (1) Drainage only.
  • (2) Buttress or regrading.
  • (3) A structural fix such as piles or a wall.

For each alternative, count as benefits the avoided train-delay cost of the slow order, the avoided maintenance, and the reduction in expected incident losses. Run the incremental test rather than ranking by ratio. Where public grant funding is involved, show the analysis from both the public and the railroad point of view, with the discount rate each one uses.

Source: Sullivan, W. G., Wicks, E. M. and Koelling, C. P. (2015). Engineering Economy, 16th ed. Upper Saddle River, NJ: Pearson, pp. 449–467. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.