↑ Parent Menu⌂ Main Menu
← Chapter 1.1 Introduction to Railway Ground Hazard Risk Management
GHRM
Railway Ground Hazard Risk Management · 1.0 · Introduction
Sections · click a car to open it

1.1.14 Case Studies

Formerly Geo Rail Chapter 7.2 — Railway Geo-Hazard Risk Management

A systematic framework for identifying, assessing, and controlling landslide, hydraulic-erosion, and subsidence hazards along the active railway corridor.
Authors: Daniel P. Colwell and Mario Ruel
1.1.14 Case Studies

Field case studies by Burt G. Look, from Earthworks: Theory to Practice – Design and Construction (CRC Press/Balkema, 2023), chosen for this chapter’s topics. Each is summarized from the book with its key figures and a closing note on railroad application added by the authors of this manual. Credit for the case material belongs to Look; see item S13 under Supplemental References.

Case Study 1.15.1 — St Lucia riverbank slide: back-analysis gives probabilities, and the repair length
Case study · Look (2023) §9.8

Related section: 1.1.5 Hydraulic Erosion Hazards

Look (1999) back-analyzed a riverbank failure on the Brisbane River at St Lucia, in front of a boat shed. Soil variability was combined with tidal water levels, using known mean high and low water spring levels as the time factor for groundwater. The adjacent stable bank had an annual probability of failure of about 10−3 at operating water levels. At the slide itself the calculated probability was 14%, and along the “stable” length of the boat shed it was 7.5%.

The first advice was to move the boat shed, but the owner considered it important enough to keep. Repairs cost 2.5 times the structure at risk. The 7.5% figure justified extending the works along the whole shed: two rows of timber piles at the failure, one row along the rest.

Four activating factors combined: vegetation removed a few weeks earlier; topsoil and a concrete path placed at the crest; an unusual tide on the day; and a new boat service that had started a few weeks before. Deep-seated failures like this are costly but rare. Shallow failures are far more common and call for regular inspection and maintenance before they grow.

For railroad work: where track runs along a river, back-analysis of a failed reach can set the extent of the repair along the “stable” bank next to it. Vegetation clearing, fill at the crest and new wave sources such as boat traffic or channel work are triggers to log in the hazard inventory.

Ground profile at the St Lucia failure: upper and lower alluvium over phyllite, with the activating factors (modified from Look 1999).
Figure 1-LK1. Ground profile at the St Lucia failure: upper and lower alluvium over phyllite, with the activating factors (modified from Look 1999). Source: Look (2023), Figure 9.9-2, p. 307.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §9.8, pp. 304. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Case Study 1.15.2 — Brisbane 2010/11: landslides whose cost bore no relation to the damage
Case study · Look (2023) §9.3.3

Related section: 1.1.7 Risk Scenarios and Risk Estimation

Brisbane’s 2010/11 summer brought 37.5 in of rain against a 16.3 in average. Rockfalls from urban road cuts, road failures at cross-drainage, fill failures at creek banks and extensive slides along the Brisbane River followed. The emergency phase lasted three months, with repairs continuing for years. Look draws out several points for landslide risk management:

  • Exposure peaks just after failure. The public is most at risk in the period before stabilization, and public frustration rises with any delay. Sometimes a less certain solution delivered quickly carries less risk than waiting for a confident one.
  • Damage value is not consequence. Property damage was often negligible, yet minor damage sometimes needed stabilization as large as cases with major structural damage. A slide taking the back fence and a 3 ft strip of yard from a house worth AU$500,000 led to remediation over AU$1 million: 5% of the lot affected, up to 200% of its value to fix. Reinstating land, not repairing the house, drives the cost.
  • Consequences beyond property and life. Road closures with no feasible detour, business losses, reputation, political and social effects are rarely included in a quantitative risk analysis.
  • Aggregation changes the label. A road with many small slides can be called high-risk even when each slide is low- to medium-risk and the history shows negligible events for 20 years.

His examples run from a blocked drain on a gated private road (insignificant) through a local road with diverted traffic and load limits (low to medium) to a slip on a blind curve, caused by undersized culverts sending water across the road, where barriers and signals cut a major consequence to minor.

For railroad work: in a ground hazard risk estimate (Section 1.1.7), the consequence term should include remediation and reinstatement cost, service interruption and detour feasibility, not only the value of what is damaged. Immediate controls such as slow orders, patrols and protective barriers move a site down the consequence scale while the permanent fix is designed.

Local road on a blind curve: a major consequence reduced to minor with barriers and signal-controlled single-lane traffic.
Figure 1-LK2. Local road on a blind curve: a major consequence reduced to minor with barriers and signal-controlled single-lane traffic. Source: Look (2023), Figure 9.3-7, p. 283.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §9.3.3, pp. 280–284. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Case Study 1.15.3 — Regional landslide hazard zoning by GIS
Case study · Look (2023) §9.9

Related section: 1.1.8 Purpose-Built Assessment Tools

Look sets four scales of slope assessment side by side: limit equilibrium (deterministic or probabilistic site study), finite element with strength reduction, monitoring (an observational, site-specific approach), and GIS hazard weighting for regional planning. Look (2005) describes a GIS study for a fast-growing Shire in Queensland, commissioned for planning, with no significant landslips on record and little landslide data.

Weighting factors were applied to lithology and structure, slope morphometry, relative relief, slope aspect, land cover and environmental factors. Risk was assessed by laying existing and proposed development over the hazard map, with extra attention to travel distance and to areas near waterways that are prone to slips in floods. Practical points:

  • Facet size changes the answer. A 16 ft × 16 ft grid gave inconsistencies; 66 ft × 66 ft was used for most layers and 1,640 ft × 1,640 ft for relative relief above 980 ft elevation.
  • Scale, facet size and data reliability all affect the output, and weightings depend on the data available.
  • The model was calibrated against site observations and the existing slip record.
  • A low-hazard zone is not necessarily a low-risk zone. The map is a screening tool that triggers site-specific assessment.

For railroad work: network-scale ground hazard screening is the same problem with a linear asset. Calibrate the weightings against the railroad’s own incident and slow-order history, and treat the output as a list of where to look, not a risk rating.

GIS information layers: data, weighted layers, analysis and calibration against existing slips and site inspection.
Figure 1-LK3. GIS information layers: data, weighted layers, analysis and calibration against existing slips and site inspection. Source: Look (2023), Figure 9.10-1, p. 307.

Source: Look, B. G. (2023). Earthworks: Theory to Practice – Design and Construction. CRC Press/Balkema. Case study §9.9, pp. 304–308. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

← Previous · 1.0 Introduction Chapter 1.0 — Manual Overview
Next · 2.0 The Underworld → Chapter 2.1 — Track Foundation Elements