1.1.10 Grade & Slope Stabilization Program — Roles and Process

Formerly Geo Rail Chapter 7.2 — Railway Geo-Hazard Risk Management

A systematic framework for identifying, assessing, and controlling landslide, hydraulic-erosion, and subsidence hazards along the active railway corridor.
Authors: Daniel P. Colwell and Mario Ruel
1.1.10 Grade & Slope Stabilization Program — Roles and Process

Responsibility for a funded stabilization program is split cleanly: the geotechnical (Geotech) group owns the yearly hazard inventory and stabilization plan; the Design & Construction group implements it. The full process runs from ground-level field data through executive sign-off to construction and follow-up monitoring:

Ground Hazard Inventory → Hazard Assessment / Data Management → Grade & Slope Stabilization Plan (feeding the overall business plan) → Detailed Scoping and Site Assessment → Review by Senior Management → Executive Ratification → Implementation → Monitoring (by both Engineering and Geotechnical personnel) → Stabilization Effectiveness Review, feeding results back into the Ground Hazard Inventory.

RoleResponsibility (typical RACI)
Field EngineerPrime — day-to-day accountability for site conditions and contingency response
Assistant Chief Engineer / Senior Manager, Design & Construction; Senior Manager of Engineering; Signals Maintainer; Track SupervisorConsulted
Senior Geotechnical EngineerInformed

Stabilization work moves through four phases — Plan → Design & Permitting → Implementation → Effectiveness — with effectiveness confirmed through follow-up geotechnical inspections over a minimum two-year evaluation period, tracked against ongoing track-inspection results. Priority setting for the following year's construction season is typically completed roughly eight months in advance, which provides lead time to communicate the plan with stakeholders, design the mitigative works, secure regulatory approvals, and solicit competitive tenders. A shared hazard database (Section 1.1.8) is what makes year-over-year prioritization defensible rather than anecdotal.

Severity scale and risk-control categories

Sites are rated on a five-level conditional-assessment scale (Severe, High, Elevated, Guarded, Low) that feeds the probability × consequence matrix. Prioritized sites then receive one of four categories of risk control: drainage modifications, engineering, ground improvements or structural installations. Effectiveness is confirmed by follow-up geotechnical inspection over a minimum two-year evaluation period. The course gives approximate geotechnical monitoring budgets of $4–15M/year in the West, $2.5–4M/year in the East and $2.5–4M/year in the U.S., with capital spending up to $9M/year in the West.

Figure 1.1-26. Five-level conditional-assessment severity scale.
Figure 1.1-26. Five-level conditional-assessment severity scale.
Figure 1.1-27. The four risk-control categories: drainage modifications, engineering, ground improvements, structural installations.
Figure 1.1-27. The four risk-control categories: drainage modifications, engineering, ground improvements, structural installations.

After Geotechnology for Railroaders Program, Module 1; §10; slope stabilization process slides adapted from material by D. Colwell. Full reference under Supplemental References.

Writing the rehabilitation plan

A rehabilitation plan has to justify the work as well as describe it. It should show a careful analysis of the existing track, bridges and facilities, tied to a clear statement of what the client needs the line to do. The same outline works for track, bridges and terminal facilities, and it fits the Plan phase of the stabilization program above.

Table 1-S2. Contents of a rehabilitation plan
SectionContentNotes
1. Operating requirementsCurrent and expected traffic: commodities, car types and numbers, train lengths, terminal and support facility needsUse the traffic data checklist, Chapter 3.9, Table 5-S4
2. Description of track, bridges and facilitiesWritten description and condition, track maps and photographs. Give every track, bridge and turnout a unique designation. Station each track from 0+00 at the switch point where it leaves the main track; for a main track, start at the ownership limit or connection with the serving railroadStationing fixes work locations and quantities and gives permanent reference marks for later inspections; on mainline work, tie stations to mileposts (Chapter 3.9, §5.4)
3. DeficienciesEach major deficiency and how it keeps the facility from supporting the required operation; comparison with current design criteria; photographsDraw on the condition, structural and operational evaluations
4. Work planRemedial action and work limits for each deficiency, and why each action was chosen over the alternativesIf the plan doubles as contract documents, it must include full details of the work
5. Cost estimateCost for each work-plan itemMajor rehabilitation: cost the major items and add allowances for minor work. Single-stage plan: break the estimate down to contract level

Points the work plan should address:

  • Standardize. When analysis calls for a heavier rail section, retiring the lighter rail often lets the owner standardize on one or two sections. That means less stock to carry and fewer hard-to-find joint bars.
  • Right-size the network. Remove track that is no longer needed. Reuse serviceable material on tracks with lower traffic and load demands. Plan the sale, transfer or disposal of scrap and salvage.
  • Gage. Regage track where existing gage is less than 56-1/4 in. or more than 57 in.

After UFC 4-860-01FA (2004), ch. 5, §6. Full reference under Supplemental References.

Project management · Haidar (2016)

Program Management Framework for a Multi-Site Stabilization Program

Haidar distinguishes program management, the coordinated delivery of a group of related projects, from managing each project on its own. A program passes through four stages: identification, planning, delivery and closure. Within it, the program manager handles pre-construction work (planning, site evaluation, cost and time parameters, bid packages), construction (contract award, procurement, cost and schedule monitoring, quality, safety, status reporting) and post-construction work (punch lists, open issues, warranty follow-up).

His program framework has four parts:

  1. Vision – aims, objectives and responsibilities, with senior sponsorship.
  2. Design and approach – how the projects depend on one another: which must come first, which can run concurrently and which come last.
  3. Resourcing – identify resources now for projects starting immediately, and only the required levels for later projects.
  4. Benefits realization – measure at the end whether the benefits stated at the start were achieved.

Program planning follows a fixed order: define objectives, agree the approach, agree roles, set communication channels, agree project priorities, then complete the project plans. At program level, each project becomes one activity in a higher-level network, and the planning is “macro”: cash flow, mobilization, crew allocation, heavy equipment distribution and delivery of critical materials. The benefits Haidar lists are a shared resource pool, less idle time, resource leveling across projects, knowledge carried from one project to the next, and reuse of equipment.

For railroad work: an annual grade and slope stabilization program, with dozens of sites across a division, fits this model directly. Treat each site as an activity in a program network, and plan the shared resources that actually limit delivery. These are track time on each subdivision, work trains and ballast or riprap supply, drill rigs and specialty contractors, flagging resources and the geotechnical staff who review designs. Sites on the same subdivision can be grouped so that one outage and one mobilization serve several repairs. The vision and benefits measures should be the railroad’s own, for example permanent slow orders removed or a lower ground-hazard incident rate on the treated segments. Closure includes handing over as-builts and monitoring records to the hazard inventory so that the next program year starts from current data.

Contrast between a single project (mobilization, construction, delivery) and a program of several projects sharing finance, design, construction and resources.
Figure 1-PM5. Contrast between a single project (mobilization, construction, delivery) and a program of several projects sharing finance, design, construction and resources. Source: Haidar (2016), Fig. 1.1.

Source: Haidar, A. D. (2016). Construction Program Management – Decision Making and Optimization Techniques. Cham, Switzerland: Springer International Publishing, pp. 2–13. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Project management · Oberlender (2000)

Measuring Progress with Weight Multipliers and an Integrated Cost/Schedule/Work Curve

Oberlender warns that tracking only cost and time can mislead. A project may have spent half its budget at the schedule midpoint with only 20% of the work done; the cost and time curves look normal, and the overrun shows up too late to correct. His remedy is to measure work accomplished as a third variable, expressed as percent complete so that unlike units (cubic yards, pounds, drawings) can be combined.

Before work starts, the project manager and the people doing the work agree on weight multipliers that sum to 1.0, along with the expected timing of each task. His illustrative weights for design are shown below.

Table 1-PM1. Illustrative weight multipliers for design work (after Oberlender 2000, Table 9-5)

Design taskWeightTiming (% of duration)
Review backup material0.050–10
Design calculations0.1010–25
Initial drafting0.2515–45
Final calculations0.2035–60
Production drawings0.3050–90
Drawing approval0.1090–100

Superimposing the weighted tasks produces a planned work/time curve, which is plotted with the cost/time S-curve on a single integrated graph. Actual cost and actual work are then posted at each report date. His construction example shows why weighting matters: on a job with 18 drilled piers, all 18 have been drilled, steel is set in 9 and concrete placed in 3. Counting only cubic yards of concrete would show the piers 3/18 complete and ignore the drilling and steel already in place.

Individual weighted work/time lines for three facilities (top) superimposed into a composite planned work curve for the whole project (bottom).
Figure 1-PM6. Individual weighted work/time lines for three facilities (top) superimposed into a composite planned work curve for the whole project (bottom). Source: Oberlender (2000), Figure 9-8.
Integrated graph with planned and actual cost on the left axis and planned and actual percent work on the right axis, plotted against time to a report date.
Figure 1-PM7. Integrated graph with planned and actual cost on the left axis and planned and actual percent work on the right axis, plotted against time to a report date. Source: Oberlender (2000), Figure 9-9.

He adds that if a sponsor sets a milestone such as “60% design,” both parties must agree in advance on what 60% means.

For railroad work: A Grade & Slope Stabilization program carries many sites at once, each at a different stage. Assign each site weights that the program team agrees on at the start, for example investigation, analysis/concept, final design and GSPs, track-window construction, and post-construction monitoring. Program progress then becomes the budget-weighted sum across sites, not a count of sites “done.” Define the 30/60/90 review milestones in writing with the railroad’s engineering group. At the construction stage, weight sub-steps the same way (for example, for soldier piles: drilled, steel set, concreted, lagging placed) so that progress during short work windows is credited accurately.

Source: Oberlender, G. D. (2000). Project Management for Engineering and Construction, 2nd ed. Boston: McGraw-Hill, pp. 134–138, 200–206. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Project management · Levy (2007)

Contractor Safety Programs, EMR and the Cost of Accidents

Levy (2007) outlines the components of a contractor safety program: a policy statement signed by top management; the objectives of the accident prevention program (planning work to minimize loss, prompt detection and correction of unsafe acts and conditions, enforced PPE and guarding, tool and equipment inspection, and training through orientation, periodic meetings and accident investigation); the duties of a safety director; the responsibilities of field supervisors, who are the first line of defense and run weekly toolbox talks; injury and illness reporting, with no discretion left to supervisors about what to report; working rules; a hazard communication program with safety data sheets on file; and a consistent progressive discipline policy.

He reproduces OSHA’s Construction Focused Inspection guideline, which checks for a designated competent person with authority to correct hazards and a project safety plan that includes a safety analysis at project start and at critical stages, identification of activities that need an engineer or competent person, procedures for hazardous operations such as cranes and trenching, documentation of inspections, hazard reports, incidents and near misses, and an emergency response plan. The four leading construction hazards cited are falls, struck-by, caught-in/between (including cave-ins) and electrical.

Levy also shows why safety matters financially. Workers’ compensation premium equals EMR × manual rate × payroll units (payroll ÷ 100). In his hypothetical example, the same $1.4 million payroll costs about $79,966 in total insurance with an EMR of 0.77 and premium credits, versus $187,859 at an EMR of 1.00, a difference of $107,893 in one year. Citing an insurer’s chart, he notes indirect accident costs are three to five times the insured cost, and that at a 2% profit margin $50,000 of new sales is needed to pay for a $1,000 accident.

For railroad work: A grade and slope stabilization program should require each contractor and drilling subcontractor to submit its safety program, EMR and recent OSHA history before award, and a site-specific plan that addresses roadway worker protection, excavation support next to track, and operation of equipment near live track. The plan’s project safety analysis should be repeated at critical stages, such as opening an excavation in the embankment toe or working during a track window.

Source: Levy, S. M. (2007). Project Management in Construction, 5th ed. New York: McGraw-Hill, pp. 300–315. Summarized and paraphrased. Full reference under Supplemental References.

Project management · Bissonette (2016)

Prioritizing Responses by Timing and Cost per Severity Point; the Risk Burn-Down Plan

Bissonette scores individual risks as probability rating × impact rating on a 5 × 5 matrix. In his example, scores of 10 or more are above tolerance and require a response, 4 or less go on a watch list, and those in between are decided case by case. He then adds three prioritization refinements that help when funds cannot cover every response:

  • Event timing. A risk whose outcome will not be known until late in the schedule is more disruptive if it occurs, so actions that reduce it or bring its decision point earlier deserve priority.
  • Incremental response cost. Two risks with equal scores rarely cost the same to treat.
  • Cost per severity point reduction. Divide the response cost by the drop in score it achieves, allowing for residual risk, and fund the responses that buy the most reduction per dollar first.

He also uses a risk burn-down schedule, a plot of the summed severity scores over time that assumes the planned responses succeed. In his notional seven-month project, three risks initially total 40. Planned responses bring the total to 14 at the start of work, and it then steps down to 10, 8 and 5 as supplier, prototype and fabrication milestones pass, reaching 0 in month six. The baseline curve is compared with actual status to show when risk reduction is falling behind. He cautions that the absolute total is meaningful only within one project, not between projects.

Planned burn-down of the summed risk-severity score for a notional project, stepping from 14 to 0 over seven months as risk-retiring milestones are reached.
Figure 1-PM8. Planned burn-down of the summed risk-severity score for a notional project, stepping from 14 to 0 over seven months as risk-retiring milestones are reached. Source: Bissonette (2016), Figure 8.8.

For railroad work: In a grade and slope stabilization program, cost per severity point gives a defensible way to rank sites competing for one year’s budget. A low-cost ditch cleanout or horizontal drain that sharply lowers the probability score at one cut may outrank a costly wall at another site whose score falls by about the same amount. Timing matters as well. Investigation at sites where the remedy depends on unknown ground conditions should be scheduled early, so that the uncertainty is resolved before the work window. A program-level burn-down built from the planned completion dates of each site’s mitigation gives management a simple view of whether risk on the network is falling as planned.

Source: Bissonette, M. M. (2016). Project Risk Management: A Practical Implementation Approach. Newtown Square, PA: Project Management Institute, Ch. 2.2 (unpaginated e-book; PDF pp. 105–118). Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.