8.4.7 Geotechnical Special Provisions (GSP) Integration

Formerly Geo Rail Chapter 5.3 — Geotechnical Report Preparation

The geotechnical report is the primary contract deliverable.
Authors: Daniel P. Colwell and Mario Ruel
8.4.7 Geotechnical Special Provisions (GSP) Integration

GSP are the contract-ready construction specification sections derived from the geotechnical design. They are included as an appendix to the GDR/FGR and are incorporated by reference into the project's construction contract. Owner railroads commonly require GSP for sole-source projects.

8.4.7.1 GSP Structure

Each GSP section follows:

  1. Scope — what work is covered
  2. Materials — specification by ASTM, AASHTO, or AREMA standard; approval process
  3. Equipment — type, minimum weight/energy, restrictions
  4. Construction Methods — sequence, lift thickness, moisture conditioning
  5. Testing and Acceptance — frequency, method, pass/fail criteria
  6. Measurement and Payment — unit, pay item description

See Appendix C of this manual for complete GSP template language for: earthwork, fill compaction, ballast/subballast, ground improvement, deep foundations, dewatering, and instrumentation.

8.4.7.2 GSP Coordination with Structural Engineer

The geotechnical consultant produces GSP for geotechnical work only. Structural concrete, steel, and track work GSPs are the responsibility of the structural and track engineers. At the pre-design meeting, confirm the division of GSP responsibility in writing to avoid gaps or duplications.

Supplemental reference

What a Class I earthwork specification actually says: Class I railroad private sidetracks (2016)

GSPs should not contradict the owner’s own standard specification. The Class I railroad Standard Specifications for Private Sidetracks contains these geotechnical requirements:

ItemRequirement
Unsuitable material in cutsRemove AASHTO A-2-6, A-2-7, A-4, A-5, A-6, A-7 to at least 2 ft below subgrade, ditch line to ditch line (more if local conditions require)
Muck in fill sectionsRemove A-8 within the toes of slope; where fill exceeds 10 ft, excavate a width of 3× the fill height
Embankment lifts≤ 6 in. loose; no frozen or organic material; not on frozen ground; bench into existing slopes; no stones > 6 in. within 2 ft of subgrade
Embankment density95% of modified Proctor (ASTM D1557), with moisture adjusted
Finished subgrade± 0.10 ft of design; no depressions that hold water
Subballast95% modified Proctor; ± 0.10 ft; not placed on wet or rutted roadbed; AREMA Ch. 1 §2.11 materials; gradation (graded aggregate / crusher run) 1½ in. 100/100, No. 10 30–55 / 15–45, No. 200 5–12 / 5–12
Geotextile (when specified)On finished subgrade, no equipment on bare fabric, 2-ft end overlaps, 18-in. side overlaps, no longitudinal overlaps between ballast toes, turned down 2 ft at abutments
Around structuresNo wet or impervious fill; 6-in. layers placed evenly on both sides; no large stones within 2 ft of arches, boxes or large pipes
Riprap¼ to 16 ft3 angular stone, minimum 3 ft thick on slopes in contact with streams

Check against Section 5.3.2.1: the client compaction table there lists 90% relative compaction for Class I railroad embankments. The Class I railroad sidetrack specification requires 95% of modified Proctor for embankments as well as subballast. Confirm the governing Class I railroad document for each project and cite it in the GSP.

Source: A Class I railroad (2016). Standard Specifications for Private Sidetracks (Industrial Sidetrack Manual), September 15, 2016

Project management · Haidar (2016)

Float, Float Ownership and Geotechnical Hold Points in Special Provisions

Haidar defines four kinds of float in arrow notation, where activity ij has duration dij and T(E) and T(L) are the earliest and latest event times:

Table E-PM1. Float definitions (after Haidar 2016, Eqs. 3.6–3.8)

FloatDefinitionMeaning
Total (TF)T(L,j) − [T(E,i) + dij]Delay that will not move completion; belongs to the path and is shared by every activity on it
Free (FF)T(E,j) − [T(E,i) + dij]Delay that will not move the early start of any successor; belongs to the activity
InterferingTF − FFPortion that, if used, takes float from successors
IndependentSuccessor early start − predecessor late finish − durationFloat available even in the worst case for both neighbors

Because total float is shared, using it on one activity reduces it for all later activities on the path. Haidar stresses that the contract should say who owns float. The common default is that the project owns it and whoever uses it first gets it. An extension of time is then due only when an owner-caused event is predicted to push total float below zero on a path that is critical to completion. A contractor who wants a private buffer should show it as a time contingency in the baseline. NEC3 Clause 63.3 preserves terminal float when planned completion is earlier than the contract date. He also notes that in resource-constrained schedules the float concept, and sometimes the critical path itself, breaks down.

Float shown as the time between the early and late completion of the last project in a program.
Figure E-PM2. Float shown as the time between the early and late completion of the last project in a program. Source: Haidar (2016), Fig. 3.9.

For railroad work: GSPs often create geotechnical hold points that act as schedule constraints. Examples include a settlement or piezometer monitoring period before the next fill lift or before final track surfacing, a load test before production piles, and a curing and verification period for treated ground. Write each hold point into the GSP with a stated minimum duration and the measurable criterion that ends it, so that bidders put it in the baseline schedule rather than treating it as float. Say whether an extension caused by monitoring results is an excusable delay, and coordinate that wording with the railroad’s contract staff. Treat track windows and outages as fixed constraints in the same way. A hold point that is clearly specified seldom produces a dispute; an unstated one usually does.

Source: Haidar, A. D. (2016). Construction Program Management – Decision Making and Optimization Techniques. Cham, Switzerland: Springer International Publishing, pp. 71–75, 78. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Project management · ASCE (2013)

Planning GSP Production: Scope-of-Work Memorandum and Review Flow

The ASCE guide recommends a planned specification production process instead of copying the last similar job. Copied specifications carry irrelevant requirements and repeat past omissions. Small projects are not exempt: the guide notes that small jobs often produce large claims because of careless or incomplete documents.

Its flow chart has thirteen steps:

  1. Agree the scope and specification philosophy with the owner.
  2. Obtain the owner’s contract terms and standard specifications.
  3. Review them for applicability to the project.
  4. Outline the required sections and set a production schedule.
  5. Draft outline specifications. Decide early on special clauses such as differing site conditions, price escalation, schedule incentives and dispute review boards.
  6. Hold technical reviews.
  7. Owner review.
  8. Expand the drafts.
  9. Constructability and engineering review.
  10. Owner review.
  11. Resolve comments in meetings.
  12. Prepare and submit the final draft.
  13. Owner issues the documents for bid.
Specification production in three stages (conceptual, preliminary review, intermediate/final), showing where owner reviews, technical reviews and constructability reviews fall before documents are issued for bid.
Figure E-PM3. Specification production in three stages (conceptual, preliminary review, intermediate/final), showing where owner reviews, technical reviews and constructability reviews fall before documents are issued for bid. Source: ASCE (2013), Specification Processing Flow Chart.

Steps 10 to 12 often repeat. Reviews should include field staff who will inspect the work and experienced construction people who can spot constructability problems.

The first document produced should be a scope-of-work memorandum. It lists the areas and types of work, the items furnished by the owner or others, and the specification sections and drawings required. The memorandum is a management tool and not a contract document. Its content later goes into the Summary of Work and the agreement, which lets technical sections stay generic.

Other points from the guide:

  • Drawings carry quantities, dimensions and geometry. Specifications carry quality. Duplicating information between them almost always produces conflicts.
  • Assign testing responsibility explicitly, and state which results mean acceptance or rejection.
  • Research field conditions during design. A clause that makes the contractor verify existing conditions does not replace that research. Resolve known unknowns with the owner as contract requirements.

For railroad work: Treat GSP integration as a scheduled, budgeted deliverable, not a task for the end of the report. A geotechnical scope memo for a culvert replacement or slide repair would record:

  • which GSPs are needed (earthwork, shoring, dewatering, ground improvement, instrumentation);
  • which items the railroad supplies, such as ballast, flaggers, track work by railroad forces and disposal sites;
  • how each GSP ties to the factual and interpretive reports.

Get the railroad’s standard specifications and agreement forms at Step 2, since many Class I railroads have their own. Include the resident engineer or construction manager in the constructability review.

Source: ASCE Construction Institute Committee on Specifications (L. Eckersley, Chair) (2013). Preparation of Construction Specifications for Civil Projects. Reston, VA: American Society of Civil Engineers, pp. 6–12, 16–17, 22–23, 29–30. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Project management · Spain (1995)

Defining Rock, Uncertain Work and Bulking When Linking the Report to the Bid Documents

Spain’s commentary on how the CESMM3 measurement rules work gives several points that apply directly when a geotechnical report feeds a bid package.

  • Define rock in geological terms, tied to the borehole logs. The definition of rock decides how much rock excavation is paid, so it belongs in the preamble to the bid schedule. Spain advises against the familiar wording “material which in the opinion of the Engineer can only be removed by blasting, pneumatic tools or wedges,” because it leaves the taker-off, the estimator and the site staff uncertain. He recommends using the same terms as the boring logs.
  • Measure the full excavation depth across layers. The commencing surface is the top of the whole excavation and the excavated surface is its bottom, however many layers lie between them. Stripping over a cut-and-fill site can produce two items for the same work. A note in the preamble, or a wider item description, avoids that.
  • Measure net, from the drawings. Round sensibly, considering the effect on the total.
  • Use a provisional sum, not provisional quantities. Where the design is not developed enough for real quantities, carry the work as a provisional sum in the general items. Do not use provisional quantities, which invite high rates on small items that pay off when the quantities grow. Carry a separate general contingency.

Spain’s data chapter gives bulking factors for converting excavated volume to loose volume:

Table E-PM2. Table: Bulkage of excavation, percent increase over in-place volume (after Spain 1995, Chapter 9)

MaterialBulkage (%)
Soil (general)25
Gravel15
Sand12.5
Heavy clay30
Rock30
Chalk50

For railroad work: when the report’s recommendations become special provisions:

  • Write the rock-excavation definition from the logged descriptions, such as weathering grade, RQD and refusal criteria, so that the pay line matches the subsurface profile in the report.
  • Carry the uncertain parts as a provisional sum, with the reason stated in the report. Examples are the depth of soft subgrade below a planned undercut and the extent of a slide that is still moving.
  • State plainly that bid quantities are neat in-place volumes. Haul and disposal volumes are then the contractor’s calculation, using bulking factors like those above or values measured on site.

Source: Spain, B. (1995). Taking Off Quantities: Civil Engineering. London: E & FN Spon, pp. 10–11, 19, 23, 194. Summarized and paraphrased. Full reference under Supplemental References.

Supplemental reference · Blasting

Blasting Special Provision and Blast Plan Review

Where rock excavation needs blasting, the GSP should set the limits and the submittals, and leave the blast design to the contractor’s licensed blaster. The engineer reviews the blast plan against the limits. The engineer does not approve the explosive design itself.

Items for the special provision:

  • Vibration and airblast limits at each structure, track and signal location (scaled distance Ds or monitored PPV, Table 5.3-17, and the owner railroad’s stricter limits).
  • Controlled perimeter blasting on permanent faces, a test section, and the face acceptance criterion (Chapter 6.3, Section 6.3.7).
  • Pre-blast condition survey, seismograph monitoring by the engineer or an independent firm, and alert and stop levels.
  • Coordination of shot times with train operations, track protection, flyrock control and post-blast inspection before trains are released.

Blast plan review checklist:

  1. Licensed blaster named; permits listed; storage and transport by the contractor under its permits.
  2. Plan and section showing hole layout, depth, perimeter-control holes, and the distance from the nearest hole to every structure and to track centerline.
  3. Maximum charge per delay and the resulting scaled distance to each structure, compared with the specified Ds, or the predicted PPV compared with the limit (Example 5.3-9).
  4. Seismograph locations and the response if the alert or stop level is reached.
  5. Flyrock control (blasting mats, stemming, face orientation away from the track) and an exclusion zone that covers the track.
  6. Shot schedule within track windows, the warning procedure, and the post-blast inspection and all-clear procedure.
  7. Pre-blast survey complete before the first shot.

For railroad work: Ask for a revised plan whenever the monitoring shows the site attenuates less than assumed, the excavation moves closer to a structure, or the rock changes. Keep the blast logs and seismograph records in the project file with the as-built face survey. They are the evidence if a damage claim follows.

Source: FHWA (1991); 30 CFR 816.61–816.68. Summarized and paraphrased. Full references under S18, S19. Monitoring details in Chapter 5.3, Section 5.3.27.