Formerly Geo Rail Chapter 5.3 — Geotechnical Report Preparation
GSP are the contract-ready construction specification sections derived from the geotechnical design. They are included as an appendix to the GDR/FGR and are incorporated by reference into the project's construction contract. Owner railroads commonly require GSP for sole-source projects.
Each GSP section follows:
See Appendix C of this manual for complete GSP template language for: earthwork, fill compaction, ballast/subballast, ground improvement, deep foundations, dewatering, and instrumentation.
The geotechnical consultant produces GSP for geotechnical work only. Structural concrete, steel, and track work GSPs are the responsibility of the structural and track engineers. At the pre-design meeting, confirm the division of GSP responsibility in writing to avoid gaps or duplications.
GSPs should not contradict the owner’s own standard specification. The Class I railroad Standard Specifications for Private Sidetracks contains these geotechnical requirements:
| Item | Requirement |
|---|---|
| Unsuitable material in cuts | Remove AASHTO A-2-6, A-2-7, A-4, A-5, A-6, A-7 to at least 2 ft below subgrade, ditch line to ditch line (more if local conditions require) |
| Muck in fill sections | Remove A-8 within the toes of slope; where fill exceeds 10 ft, excavate a width of 3× the fill height |
| Embankment lifts | ≤ 6 in. loose; no frozen or organic material; not on frozen ground; bench into existing slopes; no stones > 6 in. within 2 ft of subgrade |
| Embankment density | 95% of modified Proctor (ASTM D1557), with moisture adjusted |
| Finished subgrade | ± 0.10 ft of design; no depressions that hold water |
| Subballast | 95% modified Proctor; ± 0.10 ft; not placed on wet or rutted roadbed; AREMA Ch. 1 §2.11 materials; gradation (graded aggregate / crusher run) 1½ in. 100/100, No. 10 30–55 / 15–45, No. 200 5–12 / 5–12 |
| Geotextile (when specified) | On finished subgrade, no equipment on bare fabric, 2-ft end overlaps, 18-in. side overlaps, no longitudinal overlaps between ballast toes, turned down 2 ft at abutments |
| Around structures | No wet or impervious fill; 6-in. layers placed evenly on both sides; no large stones within 2 ft of arches, boxes or large pipes |
| Riprap | ¼ to 16 ft3 angular stone, minimum 3 ft thick on slopes in contact with streams |
Check against Section 5.3.2.1: the client compaction table there lists 90% relative compaction for Class I railroad embankments. The Class I railroad sidetrack specification requires 95% of modified Proctor for embankments as well as subballast. Confirm the governing Class I railroad document for each project and cite it in the GSP.
Source: A Class I railroad (2016). Standard Specifications for Private Sidetracks (Industrial Sidetrack Manual), September 15, 2016
Haidar defines four kinds of float in arrow notation, where activity ij has duration dij and T(E) and T(L) are the earliest and latest event times:
Table E-PM1. Float definitions (after Haidar 2016, Eqs. 3.6–3.8)
| Float | Definition | Meaning |
|---|---|---|
| Total (TF) | T(L,j) − [T(E,i) + dij] | Delay that will not move completion; belongs to the path and is shared by every activity on it |
| Free (FF) | T(E,j) − [T(E,i) + dij] | Delay that will not move the early start of any successor; belongs to the activity |
| Interfering | TF − FF | Portion that, if used, takes float from successors |
| Independent | Successor early start − predecessor late finish − duration | Float available even in the worst case for both neighbors |
Because total float is shared, using it on one activity reduces it for all later activities on the path. Haidar stresses that the contract should say who owns float. The common default is that the project owns it and whoever uses it first gets it. An extension of time is then due only when an owner-caused event is predicted to push total float below zero on a path that is critical to completion. A contractor who wants a private buffer should show it as a time contingency in the baseline. NEC3 Clause 63.3 preserves terminal float when planned completion is earlier than the contract date. He also notes that in resource-constrained schedules the float concept, and sometimes the critical path itself, breaks down.

For railroad work: GSPs often create geotechnical hold points that act as schedule constraints. Examples include a settlement or piezometer monitoring period before the next fill lift or before final track surfacing, a load test before production piles, and a curing and verification period for treated ground. Write each hold point into the GSP with a stated minimum duration and the measurable criterion that ends it, so that bidders put it in the baseline schedule rather than treating it as float. Say whether an extension caused by monitoring results is an excusable delay, and coordinate that wording with the railroad’s contract staff. Treat track windows and outages as fixed constraints in the same way. A hold point that is clearly specified seldom produces a dispute; an unstated one usually does.
Source: Haidar, A. D. (2016). Construction Program Management – Decision Making and Optimization Techniques. Cham, Switzerland: Springer International Publishing, pp. 71–75, 78. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
The ASCE guide recommends a planned specification production process instead of copying the last similar job. Copied specifications carry irrelevant requirements and repeat past omissions. Small projects are not exempt: the guide notes that small jobs often produce large claims because of careless or incomplete documents.
Its flow chart has thirteen steps:

Steps 10 to 12 often repeat. Reviews should include field staff who will inspect the work and experienced construction people who can spot constructability problems.
The first document produced should be a scope-of-work memorandum. It lists the areas and types of work, the items furnished by the owner or others, and the specification sections and drawings required. The memorandum is a management tool and not a contract document. Its content later goes into the Summary of Work and the agreement, which lets technical sections stay generic.
Other points from the guide:
For railroad work: Treat GSP integration as a scheduled, budgeted deliverable, not a task for the end of the report. A geotechnical scope memo for a culvert replacement or slide repair would record:
Get the railroad’s standard specifications and agreement forms at Step 2, since many Class I railroads have their own. Include the resident engineer or construction manager in the constructability review.
Source: ASCE Construction Institute Committee on Specifications (L. Eckersley, Chair) (2013). Preparation of Construction Specifications for Civil Projects. Reston, VA: American Society of Civil Engineers, pp. 6–12, 16–17, 22–23, 29–30. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.
Spain’s commentary on how the CESMM3 measurement rules work gives several points that apply directly when a geotechnical report feeds a bid package.
Spain’s data chapter gives bulking factors for converting excavated volume to loose volume:
Table E-PM2. Table: Bulkage of excavation, percent increase over in-place volume (after Spain 1995, Chapter 9)
| Material | Bulkage (%) |
|---|---|
| Soil (general) | 25 |
| Gravel | 15 |
| Sand | 12.5 |
| Heavy clay | 30 |
| Rock | 30 |
| Chalk | 50 |
For railroad work: when the report’s recommendations become special provisions:
Source: Spain, B. (1995). Taking Off Quantities: Civil Engineering. London: E & FN Spon, pp. 10–11, 19, 23, 194. Summarized and paraphrased. Full reference under Supplemental References.
Where rock excavation needs blasting, the GSP should set the limits and the submittals, and leave the blast design to the contractor’s licensed blaster. The engineer reviews the blast plan against the limits. The engineer does not approve the explosive design itself.
Items for the special provision:
Blast plan review checklist:
For railroad work: Ask for a revised plan whenever the monitoring shows the site attenuates less than assumed, the excavation moves closer to a structure, or the rock changes. Keep the blast logs and seismograph records in the project file with the as-built face survey. They are the evidence if a damage claim follows.
Source: FHWA (1991); 30 CFR 816.61–816.68. Summarized and paraphrased. Full references under S18, S19. Monitoring details in Chapter 5.3, Section 5.3.27.