Chapter 8.3 — Memorandums

Short technical documents: when to write a memorandum instead of a report, how to structure it, and the review it needs before it goes out.
Author: Daniel P. Colwell

This chapter covers the memorandums used on ground hazard and geotechnical work: project update memos, field and reconnaissance memos, technical memos and recommendation addenda. A memorandum is often the most-read document on a job, because it answers one question quickly; that makes its structure and review as important as a full report's.

Further reading — ICE Manual of Geotechnical Engineering
The chapters below cover the same ground in more depth. They are cited, not reproduced; see Appendix G for the full cross-reference and edition notes.
8.3.0 Purpose and Overview

A memorandum answers a limited question or records a decision, in a few pages. It is the right document when the question is narrow, the audience is the project team, and the answer is needed sooner than a full report allows. Busy readers prefer it: one client's project manager asked that reconnaissance summaries be kept to about one page, with the photographs delivered as a map file rather than pages of prints.

8.3.1 Types of Memorandums
Table 8.3-1. Memorandum types
TypePurposeTypical lengthExample
Project update memoRecord a change in scope, the reason and the effect1 to 3 pagesBorings added at one reach; RFP revised; estimate updated
Field or reconnaissance memoReport what was found on a site visit1 to 2 pages plus photo mapAccess, clearing, boring relocations, open items
Data transmittalSend logs or laboratory data without interpretation1 page plus attachmentsPreliminary boring logs for the designer
Technical memoAnswer one engineering question3 to 10 pagesStability of steepened slopes at four reaches
Recommendation addendumAdd to or revise an issued report3 to 10 pagesMemorandum addendum to an earlier final geotechnical report, with new logs and quantities
Emergency assessment letterGive a decision within a day or two of a failure2 pages plus photos and a sketchSee Section 8.4.1
8.3.2 Memorandum or Report?
Table 8.3-2. Choosing the document
Choose a memorandum whenChoose a report when
The question is narrow (one reach, one structure, one decision)The project needs a complete record of conditions and recommendations
The audience is the project teamThe document will go to bidders, regulators or the public
The answer is needed in daysThere is time for full review
It adds to an issued reportIt replaces or stands alone
The content is a decision or a changeThe content is a design basis
A memorandum is still an engineering document. If it contains interpretation or recommendations, it carries the same responsibility as a report (Chapter 8.1) and gets the same technical review.
8.3.3 Structure and Content

A memorandum works when the reader gets the answer in the first paragraph. The structure below follows a project update memo used in practice.

Table 8.3-3. Memorandum structure
PartContent
Header blockPrepared by, date, project, client and project numbers, subconsultant and key dates
1. SummaryThe finding or decision and its effect, in a short paragraph
2. Finding or backgroundWhat was found and why it matters, in bullets
3. DetailsTables of borings, quantities, results; figures
4. ChangesWhat changed from the previous version (for revisions)
5. Cost or schedule effectNet change and new totals, where relevant
6. Files updatedWhere the revised documents and map files are saved
7. Open itemsWhat still needs a decision, and from whom
LimitationsWhat the memo is based on and what it does not cover

Write in plain sentences with short bullets. Give boring IDs, stations and dates exactly; round quantities sensibly; and keep observation, interpretation and recommendation in separate paragraphs.

Summary
Answer first
▬▸
Finding
What and why
▬▸
Details
Tables and figures
▬▸
Effect
Cost, schedule
▬▸
Open items
Who decides what
8.3.4 Figures and Attachments

Attach only what the reader needs to act: a boring location plan matched in style across figures, preliminary logs, a photo map with clickable photo locations, the revised RFP or estimate. Reference the files by name and location so the team can find the current version, and move superseded files out of the working folder so nobody uses them by mistake.

A typical reconnaissance photograph used in a field memo. One or two captioned photos in the memo, with the full set in a map file, usually says more than a photo appendix.
Figure 8.3-1. A typical reconnaissance photograph used in a field memo. One or two captioned photos in the memo, with the full set in a map file, usually says more than a photo appendix.
8.3.5 Review and Quality Assurance
Table 8.3-4. Memorandum review checklist
CheckReviewer
The summary answers the question in the first paragraphAuthor, then technical reviewer
Numbers agree with the tables, the estimate and the map fileAuthor
Boring IDs, stations, coordinates and dates are correct and consistentAuthor
Interpretation and recommendations are supported by the dataTechnical reviewer
Open items name who decidesProject manager
Draft status is marked until finalAuthor
No client-confidential data leave the project teamProject manager

Mark drafts clearly ("draft, pending internal review") until they are issued, and record the revision history in the header for update memos.

8.3.6 Example: Project Update Memo

The outline below is condensed from a project update memo on a siding re-grade, with client details removed.

Table 8.3-5. Example project update memo (condensed)
PartContent
SummaryA design check found that the west reach had embankment work but no planned borings. Three borings were added and all borings renumbered west to east, giving 10 borings and 132 ft of drilling. The drilling RFP was revised and the estimate updated.
FindingThe only nearby boring was a 4-ft hand auger on the other side of the track, in topsoil only; a creek and box culvert nearby suggest soft alluvium under the fill; the reach is about 2.7 miles from the others and needs a separate setup.
DetailsBoring table: ID, reach, station, offset, depth, coring, coordinates, previous ID.
Changes (RFP Revision 2)Reach added to site reference and access; borings renumbered; totals 10 borings, 132 ft, 15-ft coring contingency, up to 16 Shelby tubes; laboratory quantities updated.
Cost effectSubconsultant rates are placeholders (previous invoice plus 20 percent) until the quote is received.
Files updatedRFP, map files, figures, project pages and cost workbook; superseded files moved out.
Open itemsConfirm the new boring locations with the geotechnical lead; draw the access route; replace placeholder rates when the quote arrives.
8.3.7 Cross-References
Table 8.3-6. Related chapters
TopicRefer to
Report types and the emergency assessment letterSection 8.4.1
Exploration versus investigationChapter 8.1
Change ordersChapter 8.2
Reconnaissance summaryChapter 3.4
Drilling RFP revisionsChapter 3.3