Formerly Geo Rail Chapter 5.3 — Geotechnical Report Preparation
A close-out report records what was actually built: the ground conditions met, the changes made during construction and the verification and monitoring results. It is a stand-alone report that cross-references, but does not replace, the design report, and it becomes part of the owner's record for the asset (Lindsay and Kemp, 2012, pp. 1503–1507). For a railroad, it is the document the next engineer will look for when the earthwork or structure needs attention.
| Item | What to include |
|---|---|
| Site and works | Brief description of the site, the geotechnical works and the design basis, with references to the design report and specifications |
| As-built record | As-built drawings; changes from the issued-for-construction design and the reasons for them |
| Ground conditions met | Where they differed from the investigation, with photographs dated and oriented |
| Verification | Compaction and material test results, load and integrity tests, inspection records |
| Monitoring | Instrument records, trigger exceedances and the action taken; status of instruments left in place |
| Constructability feedback | What worked and what did not, for future specifications (for example fill that was just outside the grading envelope and how it was compacted) |
| Quality and safety | Non-conformances and their resolution; health and safety issues relevant to future maintenance |
| Data | Where the source records are kept and in what format |
After Lindsay and Kemp (2012), Sections 101.1–101.6.
Paraphrased from the published sources below; values are converted to English units. Individual railroads, clients and projects are not named.