8.4.6 GDR vs. FGR: Client Distinctions

Formerly Geo Rail Chapter 5.3 — Geotechnical Report Preparation

The geotechnical report is the primary contract deliverable.
Authors: Daniel P. Colwell and Mario Ruel
8.4.6 GDR vs. FGR: Client Distinctions
Table 8.4-2. GDR vs. FGR Requirements
RailroadGDR Allowed?FGR Always Required?GSP Required in Report?Calc Appendix Required?Notes
AREMAPer projectPer projectRecommendedRecommendedAREMA has no mandatory format

Owner railroads may set different values. Confirm them against the owner railroad's current standards when the work is scoped.

Project management · Twort and Rees (2004)

Unforeseen Ground Conditions Claims and What the Report Must Support

Twort and Rees treat claims for unforeseen ground conditions as among the hardest a resident engineer handles. Their discussion is based on Clause 12 of the UK ICE conditions, which is broadly comparable to the differing-site-conditions clauses in North American contracts. The contractor may claim for physical conditions, other than weather, that could not reasonably have been foreseen by an experienced contractor. Their main points:

  • Deleting the clause does not remove the risk. Bidders simply add a premium, and the owner pays it whether or not bad ground is found. Bidders usually cannot drill their own borings, so price is their only defense.
  • “Everything” descriptions do not work. Describing the excavation as “all materials including boulders, rock and running sand” does not override the clause, because the extent of each material is still undefined.
  • Magnitude is the usual issue. Often the event itself was foreseeable and what was unforeseen was its scale. Their example is a hard siltstone band that was logged in the borings but then stayed in the tunnel crown for a long distance. If borings show variable ground, a contractor cannot be expected to have foreseen uniformly bad ground.
  • Payment. The contractor recovers costs reasonably incurred plus a reasonable profit: labor (including standing time and uneconomic working), materials (including abandoned temporary measures), plant working and standing, site overheads and justified head-office costs. The resident engineer’s own daily records are the check.
  • Prevention. Their first precaution for minimizing claims is an adequate site investigation, followed by complete design and documents before bidding.

The authors note that a fair clause often means the owner pays no more than if the condition had been known and written into the contract.

For railroad work: The decision to issue a factual report only, or a factual report with a design report, determines what an “experienced contractor” can reasonably be expected to have foreseen. To make a later claim decidable:

  • Describe the variability, not just the average. Show the range of depth to firm subgrade along the track and the stations where borings are widely spaced.
  • State plainly where conditions between borings are interpreted rather than observed.
  • Put quantities that depend on ground conditions (undercut depth, rock excavation, obstructions under embankments) into unit-price or provisional items in the GSPs rather than lump sums.

When a claim arises, the boring logs, the report’s stated variability and the inspector’s daily records are the evidence the railroad will rely on.

Source: Twort, A. C., and Rees, J. G. (2004). Civil Engineering Project Management, 4th ed. Oxford: Elsevier Butterworth-Heinemann, pp. 212–219, 223–224. Summarized and paraphrased. Full reference under Supplemental References.

Project management · Goldbloom (1989)

Differing Subsurface Conditions Clauses and the Factual/Interpretive Split

Goldbloom argues that subsurface risk belongs mostly with the owner, because only the owner has the time and budget to explore the site. Bidders get a few weeks to price the work and cannot drill their own borings. If each of several bidders had to do that, the owner would pay for the same exploration several times over. Borings and test pits show conditions only at the points sampled, so some differences during construction should be expected. A Differing Subsurface Conditions (changed conditions) article covers this. Its trigger is a condition that (1) differs materially from what the contract documents indicate, or (2) could not reasonably have been anticipated, and that (3) materially affects the cost of the work. The contractor must give notice before the condition is disturbed. The engineer then investigates, and if the claim is justified, an equitable adjustment is made in writing.

The book’s case history comes from a reservoir project that included a railroad relocation. Excavation for the dam was paid under two items, Earth Excavation and Rock Excavation. Rock was defined as ledge that needed drilling and blasting. At one abutment the contractor hit cemented glacial till that a 2½-CY shovel could not dig, and the borings had not shown it. The contract had neither a disclaimer nor a changed-conditions clause. The engineer still recommended paying for the extra drilling and blasting on force account, and the dispute was settled without litigation.

Goldbloom’s disclosure rules:

  • Disclose everything the designer knew, or should have known from records available to it. Withholding information invites misrepresentation claims.
  • State who drilled the borings and when, and where bidders can inspect the samples and cores. Note that samples dry out in storage, and that groundwater readings reflect conditions at the time they were taken.
  • Keep factual data separate from interpretation. In general, do not disclaim the factual data. Recommend that bidders have the interpretations reviewed by their own qualified specialist.
  • Reference reports by others can be furnished “for information only”, clearly marked as not part of the contract documents.

For railroad work: The GDR/FGR split described in this chapter maps onto Goldbloom’s factual/interpretive distinction. Bid packages for undercutting, cut-slope or culvert jobs should include the factual report: logs, lab data, groundwater observations with their dates, and GPR or ballast-fouling records. Interpretive design documents should be labeled as such. The pay-item definitions for excavation classes (common, rock, boulders, unsuitable subgrade) need to match how the logs describe materials, because the cemented-till case turned on that definition. Confirm with the railroad’s contracting group whether its standard agreement includes a changed-conditions article. If it does not, put the gap on the project risk register.

Source: Goldbloom, J. (1989). Engineering Construction Specifications: The Road to Better Quality, Lower Cost, Reduced Litigation. New York: Van Nostrand Reinhold, pp. 37–39, 182–186, 298–300. Summarized and paraphrased. Full reference under Supplemental References.