↑ Parent Menu⌂ Main Menu
← Chapter 8.4 Geotechnical Report Preparation
GHRM
Railway Ground Hazard Risk Management · 8.0 · Reporting
Sections · click a car to open it

8.4.11 Worked Examples

Formerly Geo Rail Chapter 5.3 — Geotechnical Report Preparation

The geotechnical report is the primary contract deliverable.
Authors: Daniel P. Colwell and Mario Ruel
8.4.11 Worked Examples
Example E-1: Class I railroad Embankment — Executive Summary (PREP Method)

Purpose and Scope: This Geotechnical Design Report presents the results of a subsurface investigation for the proposed Class I railroad subdivision track extension located in the central region near Macon, Georgia. The investigation, performed in March 2026, included six borings (B-1 through B-6) advanced to depths of 20–40 ft, SPT testing at 2.5-ft intervals, Shelby tube sampling at three locations, and laboratory consolidation, triaxial, and Atterberg limit testing on selected samples.

Results: Subsurface conditions consist of 3–8 ft of loose to medium-dense silty fine sand fill (Stratum A) overlying soft to firm brown kaolin-rich clay (Stratum B, SPT N = 2–6 blows/ft, s_u = 320–480 psf) extending to 18–28 ft depth. Dense residual silty sand (Stratum C, N > 30 blows/ft) was encountered beneath Stratum B at all boring locations. Groundwater was encountered at 4–6 ft depth and stabilized at 3.5 ft below existing grade.

Engineering Conclusions: The soft Stratum B clay presents two critical design challenges: (1) total consolidation settlement of 8.4–11.2 in. under the proposed 12-ft embankment load, and (2) a factor of safety against slope failure of 0.82 under rapid fill placement — well below the assumed end-of-construction minimum of 1.3 (Chapter 6.3). The dense Stratum C is adequate for spread footing or driven pile support of bridge structures within this project segment.

Practical Recommendations:

  1. Implement staged embankment construction with PVDs at 6-ft triangular spacing (see Section 7 and Appendix C-7); allow minimum 80% consolidation between stages before advancing fill.
  2. Design spread footings on Stratum C with allowable bearing capacity of 4,000 psf (see Appendix C-2); minimum embedment 3.5 ft into Stratum C.
  3. Do not use end-bearing piles in Stratum A or B; tip elevation must be confirmed in Stratum C.
  4. Install settlement plates and piezometers per instrumentation plan (Figure 5); provide monitoring data to the railroad's project engineer within 24 hours of each reading.
Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • IS-07 Undrained shear strength of clay from SPT SᵤUse: Insensitive, overconsolidated clays and weak rocks (U.K. data); PI ≈ 15–65%. Limits: Very large scatter; not reliable in soft or sensitive clays where N is very low. Use CPT, vane, or lab tests for design Su.
Example E-2: Class I railroad Structure — Calculation Appendix Header Format

A typical header format for each calculation subsection:

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

CALCULATION APPENDIX C-2: BEARING CAPACITY — PIER 2 FOOTING

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

Project: Class I railroad Columbia River Bridge Replacement

Project No.: [project number]

Client: Class I railroad

Location: Main line milepost, Oregon

Date: June 1, 2026

Prepared by: [Name], PE, Oregon License No. XX-XXXX

Checked by: [Name], PE

DESIGN BASIS

Design load: Dead: 180 kips; Live: 220 kips (Cooper E-80, DLF 1.3)

Footing geometry: B = 8 ft, L = 10 ft, D_f = 4.5 ft (embedment)

Soil parameters: φ' = 34°, c' = 0 psf, γ = 121 pcf (from Table 3.9-2, Stratum C)

Water table: 7.5 ft below grade (SWL, boring B-3, 03/15/26)

References: Vesić (1975); AREMA MRE Ch. 8; owner railroad standards

CALCULATION

[Step-by-step calculation follows using all variables defined above]

RESULT

Allowable bearing capacity: q_allow = 4,200 psf (gross)

Applied pressure: q_applied = (180,000 + 220,000) / (8 × 10) = 5,000 psf — EXCEEDS

Action required: Increase footing to B = 10 ft, L = 12 ft → q_applied = 3,333 psf < 4,200 psf ✓ (recheck q_allow for the larger footing)

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

Example E-3: Comment Resolution: Revising a Compression Index

A reviewer questions the compression index used for Stratum B. The example shows the calculation behind the response, and then the response itself, which must give the basis, the change and its effect on the recommendations.

0.100.200.300.400.500.280.310.390.42Compression index Cc Rev01 used 0.35 (8.4–11.2 in.)Basis of 0.35? Revised value and settlement = ?GivenLab Cc = 0.28, 0.31, 0.39, 0.42Stratum B, four testsRev01 value 0.35 (Section 8.3)Rev01 settlement 8.4–11.2 in.RequiredBasis of the Rev01 valueRevised design value and settlementBlack = given; red = required
Given and required for Example E-3.

Given

VariableValueDescription
Lab Cc0.28, 0.31, 0.39, 0.42Four tests, Stratum B
Rev01 value0.35Used in Section 8.3
Rev01 settlement8.4 to 11.2 in.

Required

  • Basis of the Rev01 value
  • Revised design value and settlement

Equations

  1. Eq. 1: Cc,mean = ΣCc/n
  2. Eq. 2: Snew = Sold × Cc,new/Cc,old — settlement is proportional to Cc

Steps

Step 1 · Rev01 basis (Eq. 1)
(0.28 + 0.31 + 0.39 + 0.42)/4
0.35, the mean
↓
Step 2 · Revised value
Mean of the two higher values: (0.39 + 0.42)/2
0.40
↓
Step 3 · Revised settlement (Eq. 2)
8.4 × 0.40/0.35; 11.2 × 0.40/0.35
9.6 to 12.8 in.
↓
Solution
Cc = 0.40; settlement 9.6 to 12.8 in.; recommendations unchanged.

Solution

Response to Comment No. 07: “Comment accepted. The Rev01 value of 0.35 was the mean of the four tests, but the text did not say so. For a conservative representative value we have revised to Cc = 0.40, the mean of the two higher results, which reflect the softer material likely to govern total settlement, and updated Section 8.3 and Appendix C-3. The settlement estimate is revised to 9.6 to 12.8 in. (was 8.4 to 11.2 in.). Recommendation 1 (staged construction with PVDs) is unchanged. See Section 8.3 and Appendix C-3, Rev02.”

A good response does three things: it states what was done and why, it makes the change (or explains why not), and it says whether the change alters any recommendation. Here it does not, which the reviewer most needs to know.

← Previous · 8.0 Reporting Chapter 8.3 — Memorandums
Next · Appendices → Appendices