Formerly Geo Rail Chapter 5.3 — Geotechnical Report Preparation
The following section structure satisfies the requirements of owner railroads when tailored to the specific client format. Sections in bold are mandatory for GDR/FGR; unmarked sections are GDR-only.
Required elements:
The executive summary is the most-read section of any geotechnical report. Railroad project engineers often read only the executive summary before forwarding to procurement or construction. It must be self-contained and decision-ready.
Executive Summary Framework (PREP Method):
Length: 1–2 pages maximum. Keep equations and ASTM test numbers out of the executive summary.
"This report presents the results of a geotechnical investigation performed at the Class I railroad subdivision bridge replacement located in the Shenandoah Valley near Waynesboro, Virginia. The investigation included four borings (B-1 through B-4) advanced to depths of 40–55 ft, Standard Penetration Tests at 2.5-ft intervals, and laboratory testing on selected samples. Subsurface conditions consist of 8–12 ft of mixed fill and residual silty clay overlying weathered greenstone bedrock, with competent rock encountered at 14–22 ft depth below existing ground surface..."

For GDR/FGR only. One subsection per analysis type performed:
8.4.3.8.1 Foundation Bearing Capacity (cross-reference Chapter 6.1)
8.4.3.8.2 Settlement Analysis (cross-reference Chapter 6.2)

8.4.3.8.3 Slope Stability (cross-reference Chapter 6.3)
8.4.3.8.4 Seismic Hazard and Liquefaction (cross-reference Chapter 6.5)
8.4.3.8.5 Pavement Subgrade / Track Subgrade (cross-reference Chapters 3.8, 2.3)
8.4.3.8.6 Ground Improvement (cross-reference Chapter 7.2)
For track rehabilitation and substructure projects, the analyses section should present the following, so that the maintenance recommendation can be traced to evidence:
After Selig & Waters (1994), chs. 12, 14 and 16. Full reference under Supplemental References.
Numbered list of actionable engineering recommendations. Each recommendation must:
"3. Design spread footings on the dense sand stratum (Stratum B) at a minimum depth of 4.5 ft below existing grade with an allowable bearing pressure of 3,500 psf (gross). Settlement under design load is estimated at 0.5–0.8 in. (see Section 8.2). Confirm footing bearing elevation in the field during excavation. Notify the geotechnical engineer if the sand stratum is not encountered within 1.0 ft of predicted depth."
Standard risk-allocation language required by owner railroads:
Owner railroads may require the limitations clause to include a specific sentence regarding the proprietary nature of client engineering standards referenced in the report.
Source: A Class I railroad (2020). Public Projects Manual, December 2020, incl. Soil and Water Management Policy
Profillidis summarizes investigation results in two deliverables: the geotechnical report and the geotechnical longitudinal section along the alignment. His example is the Channel Tunnel profile, routed within a blue chalk layer that proved resistant to water inflow (Figure 8.4-11). The report should give clear recommendations on:

For linear railway projects, a longitudinal section that carries strata, groundwater, the track profile and the location of structures is often the most-used figure in the report. It belongs in the figures package with the boring location plan.
After Profillidis (2014), §9.2.5, Fig. 9.1. Full reference under Supplemental References.