Railway Ground Hazard Risk Management · 8.0 · Reporting
Sections · click a car to open it

8.4.3 Report Structure — Required Sections

Formerly Geo Rail Chapter 5.3 — Geotechnical Report Preparation

The geotechnical report is the primary contract deliverable.
Authors: Daniel P. Colwell and Mario Ruel
8.4.3 Report Structure — Required Sections

The following section structure satisfies the requirements of owner railroads when tailored to the specific client format. Sections in bold are mandatory for GDR/FGR; unmarked sections are GDR-only.

8.4.3.1 Cover Page and Title Block

Required elements:

  • Report title (per client naming convention)
  • Railroad client name and project number
  • Project location (county, state, milepost or station)
  • Consultant firm name, address, and project number
  • Report date and revision number
  • Client project engineer name (if known)
  • PE seal block: "Prepared by: [Name, PE, License No., State, Expiration Date]"
Engineering Geology
Engineering Geology
8.4.3.2 Executive Summary

The executive summary is the most-read section of any geotechnical report. Railroad project engineers often read only the executive summary before forwarding to procurement or construction. It must be self-contained and decision-ready.

Executive Summary Framework (PREP Method):

  1. P — Purpose and Scope (2–3 sentences): What was investigated, where, and for what project?
  2. R — Results (3–5 sentences): What conditions were found? What are the key parameters?
  3. E — Engineering Conclusions (3–5 sentences): What do the conditions mean for design? What are the critical findings?
  4. P — Practical Recommendations (numbered list): What should the design and construction teams do?

Length: 1–2 pages maximum. Keep equations and ASTM test numbers out of the executive summary.

Example Executive Summary Opening (Class I railroad format):

"This report presents the results of a geotechnical investigation performed at the Class I railroad subdivision bridge replacement located in the Shenandoah Valley near Waynesboro, Virginia. The investigation included four borings (B-1 through B-4) advanced to depths of 40–55 ft, Standard Penetration Tests at 2.5-ft intervals, and laboratory testing on selected samples. Subsurface conditions consist of 8–12 ft of mixed fill and residual silty clay overlying weathered greenstone bedrock, with competent rock encountered at 14–22 ft depth below existing ground surface..."

Geotechnical Investigation
Geotechnical Investigation
8.4.3.3 Introduction
  • Project description and railroad context
  • Scope of geotechnical services
  • Referenced standards (AREMA MRE Chapters, client engineering standards, ASTM methods, USACE EM 1110-1-1804)
  • Report organization
8.4.3.4 Site Conditions
  • Site location and access (RWP zone, dispatch block)
  • Surface topography and drainage
  • Existing track structure and milepost references
  • Adjacent structures
  • Published geologic mapping reference
  • USGS quadrangle reference
  • FEMA flood zone designation
Top 5 Geo Site Red Flags
Top 5 Geo Site Red Flags
8.4.3.5 Field Investigation Program
  • Boring layout rationale (referenced to investigation plan from Chapter 3.9)
  • Drilling method (HSA, mud rotary, etc. — per Chapter 4.1)
  • SPT procedure and correction chain (N₆₀, (N₁)₆₀ per Chapter 4.1)
  • Sampling: Shelby tube locations, core intervals
  • In situ tests performed (CPT, VST, MASW — per Chapter 5.1)
  • Groundwater observations (date, depth, stabilized level)
  • Boring location plan (plan view drawing — Figure 1)
8.4.3.6 Laboratory Testing Program
  • Summary of tests performed (indexed to boring and sample number)
  • Reference to laboratory test data tables (Appendix B)
  • QC/QA notes (accreditation, split-sample check results)
8.4.3.7 Subsurface Conditions
  • Geologic setting and stratigraphy narrative
  • Soil and rock description by unit (USCS, AASHTO, RQD if applicable)
  • Engineering property summary table (key design parameters by stratum)
  • Groundwater conditions (FEWL, SWL, seasonal assessment)
  • Cross-section profiles (Figure 2 — geologic profiles along track alignment)
8.4.3.8 Engineering Analyses

For GDR/FGR only. One subsection per analysis type performed:

8.4.3.8.1 Foundation Bearing Capacity (cross-reference Chapter 6.1)

  • Vesić equation results for each structure; recommended allowable bearing capacity table; pile capacity results

8.4.3.8.2 Settlement Analysis (cross-reference Chapter 6.2)

  • Sublayer model description; computed S_total per structure; comparison to FRA tolerance; serviceability conclusions
Comparison of Geotechnical Models
Comparison of Geotechnical Models

8.4.3.8.3 Slope Stability (cross-reference Chapter 6.3)

  • Critical cross-sections analyzed; FS results table by condition; minimum FS vs. owner railroad requirements

8.4.3.8.4 Seismic Hazard and Liquefaction (cross-reference Chapter 6.5)

  • USGS NSHM site class; screening result; FS_L table if triggered

8.4.3.8.5 Pavement Subgrade / Track Subgrade (cross-reference Chapters 3.8, 2.3)

  • CBR/M_r results; design section recommendation; FI data if ballast was sampled

8.4.3.8.6 Ground Improvement (cross-reference Chapter 7.2)

  • Method justification; design parameters; expected performance

Trackbed findings the design report should carry

For track rehabilitation and substructure projects, the analyses section should present the following, so that the maintenance recommendation can be traced to evidence:

  • A layer profile for each pit or trench: thickness, ASTM D2488 description, color, and the fouling index of each ballast zone.
  • The identified source of fouling or mud (ballast breakdown, subgrade pumping, spillage), with the test that supports it.
  • The drainage condition: outlets, ditch flow lines, and the critical rainfall rate implied by the measured fouling (Chapter 2.3, Table 2-SW5).
  • Reclaimable stone against undercut depth, where cleaning is an option.
  • The remedy matched to the cause, with short-term and long-term options separated (Section IV, Table 4-SW1).
  • For any geosynthetic recommendation, the basis for the AOS, a field-trial or monitoring plan, and the alternative granular design.

After Selig & Waters (1994), chs. 12, 14 and 16. Full reference under Supplemental References.

8.4.3.9 Conclusions and Recommendations

Numbered list of actionable engineering recommendations. Each recommendation must:

  1. State what to do
  2. Give the governing parameter (e.g., "allowable bearing pressure = 3,500 psf")
  3. Reference the supporting section or calculation
  4. Note any special condition or caveat
Example format:

"3. Design spread footings on the dense sand stratum (Stratum B) at a minimum depth of 4.5 ft below existing grade with an allowable bearing pressure of 3,500 psf (gross). Settlement under design load is estimated at 0.5–0.8 in. (see Section 8.2). Confirm footing bearing elevation in the field during excavation. Notify the geotechnical engineer if the sand stratum is not encountered within 1.0 ft of predicted depth."

8.4.3.10 Limitations and Conditions of Use

Standard risk-allocation language required by owner railroads:

  • Scope limitation: investigation was performed for stated project only; not valid for other locations
  • Temporal limitation: conditions valid at time of investigation; seasonal groundwater variability may affect design
  • Data density: borings are point data; conditions may vary between borings
  • Changed conditions: if excavation reveals conditions differing from report, notify geotechnical engineer before proceeding
  • Report ownership: report prepared for named client; reliance by third parties without written consent is not permitted

Owner railroads may require the limitations clause to include a specific sentence regarding the proprietary nature of client engineering standards referenced in the report.

Supplemental reference

Owner requirements that shape the field program and the report (Class I railroad Public Projects Manual)

  • Access: borings and other investigative work on Class I railroad property need a Temporary Right-of-Entry agreement. That agreement expressly excludes environmental investigation: no soil, sediment, groundwater or surface water sampling for chemical analysis without a separate Environmental Right-of-Entry. Keep geotechnical sampling clearly geotechnical and say so in the report.
  • Overhead bridges: at least one boring for each substructure unit adjacent to the track must accompany the design submittal, with enough information to design shoring and foundations.
  • Shoring next to track: not required only if the excavation stays outside a 1H:1V line from the bottom corner of the tie and the track is on level ground or in a cut on stable soil. Excavating the toe of an embankment without shoring is not permitted. Design shoring for active pressure plus a 1,882-psf live-load surcharge on an 8.5-ft-wide strip, distributed by the AREMA Ch. 8 strip-load formula — much higher than a uniform equivalent surcharge (compare Section 7.1.3).
  • Soil and water: soil generated on Class I railroad property must be reused on Class I railroad property (with Environmental Department approval) or disposed of at a railroad-approved facility; contractors may not take it off-property. Dewatering discharges need prior approval. The report’s earthwork and dewatering recommendations should assume these constraints.

Source: A Class I railroad (2020). Public Projects Manual, December 2020, incl. Soil and Water Management Policy

Report content and the geotechnical longitudinal section

Profillidis summarizes investigation results in two deliverables: the geotechnical report and the geotechnical longitudinal section along the alignment. His example is the Channel Tunnel profile, routed within a blue chalk layer that proved resistant to water inflow (Figure 8.4-11). The report should give clear recommendations on:

Figure 8.4-11. Geotechnical longitudinal section along the Channel Tunnel, United Kingdom to France. Profillidis Fig. 9.1.
Figure 8.4-11. Geotechnical longitudinal section along the Channel Tunnel, United Kingdom to France. Profillidis Fig. 9.1.
  • geotechnical description of each layer;
  • hydrogeological data: maximum and minimum piezometric levels and drainage requirements;
  • construction methods, earthwork heights and suitability of excavated soils for reuse;
  • recommended slopes, embankment design and any special techniques such as reinforced soil;
  • mechanical properties of the soils and bearing capacity of the subgrade.

For linear railway projects, a longitudinal section that carries strata, groundwater, the track profile and the location of structures is often the most-used figure in the report. It belongs in the figures package with the boring location plan.

After Profillidis (2014), §9.2.5, Fig. 9.1. Full reference under Supplemental References.