8.4.14 Practical Recommendations

Formerly Geo Rail Chapter 5.3 — Geotechnical Report Preparation

The geotechnical report is the primary contract deliverable.
Authors: Daniel P. Colwell and Mario Ruel
8.4.14 Practical Recommendations
  1. Write the executive summary last. It must accurately reflect the analysis, not the assumptions made at the start of the project. Draft it after all calculations are reviewed and conclusions are firm.
  2. Use client-specific terminology throughout. Owner railroads have their own names for project types, task orders and project numbers; use them in document headers. Using client-standard terminology signals familiarity with the client's program and avoids the perception of a generic deliverable.
  3. Never embed critical parameters only in calculation appendices. If a load-bearing recommendation depends on a specific value of φ' or c', that value must appear in the body of Section 6 (engineering properties table) AND in Section 8 (recommendations). Structural engineers who receive the report may not open the calculation appendix.
  4. Submit a draft boring log to the client before the report. For projects with any geologic uncertainty, submit draft boring logs within 5 business days of completion of field work. This allows the client's PE to flag concerns — soft zones, unexpected rock, groundwater anomalies — before the report analysis is finalized. Clients generally welcome early data sharing.
  5. Track all report versions in a single master file list. Use the naming convention in Section 8.4.10.2 consistently. Project records are subject to litigation discovery for years after construction (statutes of repose vary by state). A clear version history prevents confusion about which calculations governed final design.
  6. Document field changes to boring scope in writing. When a boring is terminated early, relocated, or added to address unexpected conditions, document it in a brief field memorandum to the client project engineer on the same day. Do not simply adjust the boring logs after the fact.
  7. Verify PE license currency before sealing. Every sealing PE should confirm their license is active and in good standing in the specific project state before sealing documents. Multi-state projects with tight delivery schedules have failed due to a PE's license lapsing in a required state. Add license verification to the project initiation checklist.
Supplemental reference

When the report is about a failure

Forensic reports are read by lawyers as well as engineers. Rao (2016) recommends a fixed scope. Compulsory: survey and document the distress; review all design documents, the original investigation and the construction records; interview those involved. Optional: additional investigation, special tests and NDT of structural elements. The report should cover authority and scope, history, summary of original documents, data collected, interviews, meteorological and earthquake information, investigations and results, analysis and conclusions. Parameters must represent the actual site condition (avoid unvalidated empirical correlations), because the engineer must be able to justify them in court.

ISSMGE TC302 Task Force 10 reviewed about 100 failures from Asia, South America and Europe. Roughly half were caused by design shortcomings (including the ground model and parameters), about a fifth each by inadequate site investigation and unforeseen phenomena, and about a seventh by construction. In the Asian cases, inadequate investigation caused about half the failures, and in 60% of those no investigation had been done at all. Recommendations that belong in every railroad report’s QA process: a desk study with a geological framework on every project, adequate investigation funding, design by engineers who know their limits, independent checking or peer review of designs and construction methods, qualified oversight during construction, and publishing lessons from failures.

Source: Rao, V. V. S. (2016). “Guidelines for Forensic Investigation of Geotechnical Failures,” and Jessep, R. A., de Mello, L. G. and Rao, V. V. S. (2016). “Technical Shortcomings Causing Geotechnical Failures: Report of Task Force 10, TC 302.” In Rao and Sivakumar Babu (eds.), Forensic Geotechnical Engineering. Springer India

Project management · Hutchings (2004)

Differing Site Conditions and the As-Planned / As-Built / Adjusted Schedule Method

Hutchings describes changed conditions, also called unforeseen or differing site conditions, as a standard clause in federal contracts that is increasingly used by other public owners. The policy behind it is that the owner accepts certain subsurface and latent-condition risks so that bidders do not have to carry large contingencies for them. His examples of qualifying conditions include a buried pipeline that is missing from the drawings or shown in the wrong place, unusually severe weather for the season and location, and expansive clay in the excavation that was not identified in the geologic survey or the prior soil investigations. He notes that severe weather may be ruled excusable (time only) but not compensable.

He also lists constructive changes, informal owner acts or omissions that increase cost or time. These include defective plans and specifications, the engineer’s interpretation of documents, demanding a higher standard than specified, improper rejection of work, changes in method or sequence, and owner nondisclosure of pertinent facts. The contractor must give written notice within the contract period or may waive the claim.

To measure the time effect of a change after the fact, Hutchings uses three schedules:

  1. As-planned – the accepted baseline.
  2. As-built – the historical schedule built from the periodic updates, which contains every effect that actually occurred.
  3. Adjusted – the as-built with the effect of the one change removed from each update.

The difference between the as-built and adjusted completion dates is the time attributable to that change. Before a change is made, a single revised as-planned schedule that includes the change shows its predicted effect on the end date.

For railroad work: the geotechnical report is the baseline against which a differing-condition claim is judged, so write it with that use in mind. Present factual data (logs, groundwater readings, lab results) separately from interpretation. State the limits of the data between borings. Include or reference all relevant information the railroad holds, such as historical borings, earlier slide reports and drainage records, because withholding pertinent facts can itself become a constructive change. During construction, document any suspected differing condition immediately: milepost, station and offset, depth, photographs, samples, and the work affected. Report it to the railroad’s project manager in writing the same day.

Source: Hutchings, J. F. (2004). Project Scheduling Handbook. Civil and Environmental Engineering Series, Vol. 15. New York: Marcel Dekker, Inc., pp. 209–212. Summarized and paraphrased. Full reference under Supplemental References.

Project management · Bissonette (2016)

Assumptions Versus Risks: The Acid Test and the Assumption Register

Bissonette treats the line between a valid assumption and an unrecognized risk as central to planning. An assumption bounds the work to known constraints, or records a condition outside the team’s control that the stakeholders have agreed to. He applies a two-question “acid test” taken from the PMBOK® Guide:

  1. Could the assumption or constraint prove false?
  2. If it were false, would one or more project objectives be harmed?

If both answers are yes, the statement is a risk and must be moved to the risk register or reworded until it passes. A companion sentence form, “<assumption> may prove false, leading to <effect on objectives>,” makes the consequence explicit. His examples show the range of outcomes. One assumption is valid because a contract clause already provides an equitable adjustment if customer-furnished equipment arrives late. Another, “the team assumes no liability for scope omissions,” fails the test and should prompt more planning. He recommends an assumption register on every project, whatever its size. Its columns are number, description, “could it prove false?”, “if false, would it affect the project?” and “convert to a risk?”.

For railroad work: Geotechnical reports are full of assumptions: groundwater at the level measured during drilling, subsurface conditions between borings similar to those at the borings, no undocumented fill or buried timber trestle, drainage outfalls that remain functional, and tie and ballast renewal staying on the maintenance cycle. Run each one through the acid test before the report is sealed. Assumptions that pass belong in the limitations or design-basis section. Those that fail, such as a water level measured in a dry month at a site that seeps in spring, should be stated as a risk with a recommended response, for example a piezometer, a contingency quantity or a construction-phase observation. Including a short assumption register in the report appendix helps the railroad’s reviewers and the contractor see what the recommendations depend on. It also gives a clear basis for comparison if conditions found during construction differ.

Source: Bissonette, M. M. (2016). Project Risk Management: A Practical Implementation Approach. Newtown Square, PA: Project Management Institute, Ch. 3.9, “Assumptions Versus Risks” (unpaginated e-book; PDF pp. 62–65). Summarized and paraphrased. Full reference under Supplemental References.