Formerly Geo Rail Chapter 5.3 — Geotechnical Report Preparation
Forensic reports are read by lawyers as well as engineers. Rao (2016) recommends a fixed scope. Compulsory: survey and document the distress; review all design documents, the original investigation and the construction records; interview those involved. Optional: additional investigation, special tests and NDT of structural elements. The report should cover authority and scope, history, summary of original documents, data collected, interviews, meteorological and earthquake information, investigations and results, analysis and conclusions. Parameters must represent the actual site condition (avoid unvalidated empirical correlations), because the engineer must be able to justify them in court.
ISSMGE TC302 Task Force 10 reviewed about 100 failures from Asia, South America and Europe. Roughly half were caused by design shortcomings (including the ground model and parameters), about a fifth each by inadequate site investigation and unforeseen phenomena, and about a seventh by construction. In the Asian cases, inadequate investigation caused about half the failures, and in 60% of those no investigation had been done at all. Recommendations that belong in every railroad report’s QA process: a desk study with a geological framework on every project, adequate investigation funding, design by engineers who know their limits, independent checking or peer review of designs and construction methods, qualified oversight during construction, and publishing lessons from failures.
Source: Rao, V. V. S. (2016). “Guidelines for Forensic Investigation of Geotechnical Failures,” and Jessep, R. A., de Mello, L. G. and Rao, V. V. S. (2016). “Technical Shortcomings Causing Geotechnical Failures: Report of Task Force 10, TC 302.” In Rao and Sivakumar Babu (eds.), Forensic Geotechnical Engineering. Springer India
Hutchings describes changed conditions, also called unforeseen or differing site conditions, as a standard clause in federal contracts that is increasingly used by other public owners. The policy behind it is that the owner accepts certain subsurface and latent-condition risks so that bidders do not have to carry large contingencies for them. His examples of qualifying conditions include a buried pipeline that is missing from the drawings or shown in the wrong place, unusually severe weather for the season and location, and expansive clay in the excavation that was not identified in the geologic survey or the prior soil investigations. He notes that severe weather may be ruled excusable (time only) but not compensable.
He also lists constructive changes, informal owner acts or omissions that increase cost or time. These include defective plans and specifications, the engineer’s interpretation of documents, demanding a higher standard than specified, improper rejection of work, changes in method or sequence, and owner nondisclosure of pertinent facts. The contractor must give written notice within the contract period or may waive the claim.
To measure the time effect of a change after the fact, Hutchings uses three schedules:
The difference between the as-built and adjusted completion dates is the time attributable to that change. Before a change is made, a single revised as-planned schedule that includes the change shows its predicted effect on the end date.
For railroad work: the geotechnical report is the baseline against which a differing-condition claim is judged, so write it with that use in mind. Present factual data (logs, groundwater readings, lab results) separately from interpretation. State the limits of the data between borings. Include or reference all relevant information the railroad holds, such as historical borings, earlier slide reports and drainage records, because withholding pertinent facts can itself become a constructive change. During construction, document any suspected differing condition immediately: milepost, station and offset, depth, photographs, samples, and the work affected. Report it to the railroad’s project manager in writing the same day.
Source: Hutchings, J. F. (2004). Project Scheduling Handbook. Civil and Environmental Engineering Series, Vol. 15. New York: Marcel Dekker, Inc., pp. 209–212. Summarized and paraphrased. Full reference under Supplemental References.
Bissonette treats the line between a valid assumption and an unrecognized risk as central to planning. An assumption bounds the work to known constraints, or records a condition outside the team’s control that the stakeholders have agreed to. He applies a two-question “acid test” taken from the PMBOK® Guide:
If both answers are yes, the statement is a risk and must be moved to the risk register or reworded until it passes. A companion sentence form, “<assumption> may prove false, leading to <effect on objectives>,” makes the consequence explicit. His examples show the range of outcomes. One assumption is valid because a contract clause already provides an equitable adjustment if customer-furnished equipment arrives late. Another, “the team assumes no liability for scope omissions,” fails the test and should prompt more planning. He recommends an assumption register on every project, whatever its size. Its columns are number, description, “could it prove false?”, “if false, would it affect the project?” and “convert to a risk?”.
For railroad work: Geotechnical reports are full of assumptions: groundwater at the level measured during drilling, subsurface conditions between borings similar to those at the borings, no undocumented fill or buried timber trestle, drainage outfalls that remain functional, and tie and ballast renewal staying on the maintenance cycle. Run each one through the acid test before the report is sealed. Assumptions that pass belong in the limitations or design-basis section. Those that fail, such as a water level measured in a dry month at a site that seeps in spring, should be stated as a risk with a recommended response, for example a piezometer, a contingency quantity or a construction-phase observation. Including a short assumption register in the report appendix helps the railroad’s reviewers and the contractor see what the recommendations depend on. It also gives a clear basis for comparison if conditions found during construction differ.
Source: Bissonette, M. M. (2016). Project Risk Management: A Practical Implementation Approach. Newtown Square, PA: Project Management Institute, Ch. 3.9, “Assumptions Versus Risks” (unpaginated e-book; PDF pp. 62–65). Summarized and paraphrased. Full reference under Supplemental References.