Formerly Geo Rail Chapter 5.3 — Geotechnical Report Preparation
Owner railroads recognize — explicitly or implicitly — the distinction between two geotechnical deliverables:
The GDR presents factual subsurface data without interpretation or design recommendations. It is the appropriate deliverable for competitive bid projects where multiple engineering firms will use the same data to develop their own designs, and for early-phase investigations where design parameters have not yet been finalized.
GDR Contents:
GDR Users: Contractors preparing bids; design engineers developing conceptual foundations; railroad project development group.
The GDR/FGR (sometimes called a Final Geotechnical Report or Foundation/Geotechnical Report) presents factual data, interpreted parameters, analysis, and design recommendations. It is the primary deliverable for sole-source design contracts.
GDR/FGR Contents: Everything in the GDR plus:
FHWA adds a timing dimension to the GDR/FGR distinction. Issue a preliminary geotechnical report whenever early data or evaluation can shape the design — typically on large projects or complex sites where alignment or grade might change because of the geotechnical findings. The final report follows once alignment, grade and geometry are fixed and specific recommendations can be made. Whatever the format, FHWA lists five essentials: (1) all exploration data (profile, logs, lab and in-situ results, groundwater); (2) interpretation and analysis; (3) specific design recommendations; (4) discussion of anticipated problems and their solutions; and (5) recommended geotechnical special provisions. FHWA also notes that the report is used during design, during construction and after completion when resolving claims — one reason to write every statement as if it will be read by someone looking for a basis for a claim.
Source: Federal Highway Administration (2017). What is a Geotechnical Report? Geotechnical Engineering fact page
After a slope failure or washout the railroad needs a decision within a day or two, not a GDR. A 2018 preliminary site assessment for a Class I railroad at a main-line milepost (a Class I railroad subdivision located in West Virginia) illustrates the format. It is a two-page letter plus photographs and a sketch, issued the day after a site visit held two days after the event.

The structure — who/when/why, site and problem, observations, assessment, prioritized interim actions, and photos keyed to a sketch — is a useful template for GDR/FGR programs that begin with an emergency.
Source: A consultant (2018). Preliminary Site Assessment of Slope Instability at a main-line milepost, a Class I railroad subdivision, near Clarksburg, WV (draft letter report, April 6, 2018)