2.8.5 Seepage Analysis

Groundwater is the single most consequential subsurface variable in railroad geotechnical engineering.
Authors: Daniel P. Colwell and Mario Ruel
2.8.5 Seepage Analysis
2.8.5.1 Seepage Velocity and Hydraulic Gradient
Equation 2.8-11 — Hydraulic Gradient:

i = Δh / L

Where Δh = head loss (ft) and L = seepage path length (ft).

Inputs: where each value comes from (1)
SymbolWhat it isComes fromHow to get itTypical range
Δhhead loss (ft) and L = seepage path length (ft).Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
Equation 2.8-12 — Darcy Seepage Velocity:

v = k × i

Equation 2.8-13 — Actual (Interstitial) Flow Velocity:

v_a = k × i / n

Where n = porosity (dimensionless); typical values: gravels 0.25–0.40; sands 0.30–0.45; silts 0.35–0.50; clays 0.40–0.70.

Inputs: where each value comes from (1)
SymbolWhat it isComes fromHow to get itTypical range
nporosity (dimensionless)Another equationn = e/(1 + e), from the void ratio.0.25–0.55 for most mineral soils · by USCS group
2.8.5.2 Flow Nets and Seepage Rate

For embankment seepage with a defined flow net (N_f flow channels, N_d equipotential drops):

Equation 2.8-14 — Seepage Rate Per Unit Width:

q = k × H × (N_f / N_d)

Where H = total head loss (ft); q = seepage flow per unit width of embankment (ft²/day).

Evaluate embankments next to waterways for seepage with a flow net or a numerical analysis when site-specific permeabilities are available, particularly at the approaches to scour-critical bridges.

Inputs: where each value comes from (1)
SymbolWhat it isComes fromHow to get itTypical range
Htotal head loss (ft)Field or lab measurementRecorded during the test or monitoring (readings, times, dimensions of the test setup).project-specific
2.8.5.3 Critical Hydraulic Gradient and Piping Risk

Upward seepage beneath a railroad embankment or at the toe of a flood-side levee can cause piping or heave when the upward seepage force exceeds the submerged weight of soil:

Equation 2.8-15 — Critical Hydraulic Gradient:

i_cr = (G_s − 1) / (1 + e) = γ' / γ_w

Where:

  • G_s = specific gravity of solids (typically 2.65 for quartz sand)
  • e = void ratio
  • γ' = buoyant unit weight (pcf)
  • γ_w = 62.4 pcf

For a typical medium sand (G_s = 2.65, e = 0.65):

i_cr = (2.65 − 1) / (1 + 0.65) = 1.65 / 1.65 = 1.00

Inputs: where each value comes from (4)
SymbolWhat it isComes fromHow to get itTypical range
icrintermediate value computed on this pageAnother equationComputed: i_cr = (G_s − 1) / (1 + e) = γ' / γ_wproject-specific
Gsspecific gravity of solids (typically 2.65 for quartz sand)Lab testSpecific gravity of solids (ASTM D854). 2.65–2.70 is usually adequate for mineral soils when untested.2.64–2.80 mineral; lower if organic · by USCS group
evoid ratioAnother equatione = Gsγw/γd − 1, from Gs and γd; e0 for consolidation is reported by the consolidation test (ASTM D2435).sands 0.35–0.85, clays 0.5–2.0 · by USCS group
γ'buoyant unit weight (pcf)Another equationγ' = γsat − γw (γw = 62.4 pcf). Use below the water table.50–75 pcf for most mineral soils · by USCS group
Equation 2.8-16 — Factor of Safety Against Piping:

FS_piping = i_cr / i_exit

This manual recommends FS_piping ≥ 4.0 for permanent embankments adjacent to waterways where the exit is not protected by a filter. USACE EM 1110-2-1901 is written for dams and does not set a railroad criterion; state the criterion used.

2.8.5.4 Scour Analysis (FHWA HEC-18)

AREMA MRE Chapter 8 addresses scour for foundations at waterway crossings; FHWA HEC-18 is the usual method. Total scour depth:

Equation 2.8-17 — Total Scour:

y_total = y_long + y_contr + y_local

Where:

  • y_long = long-term degradation scour (ft) — from channel bed trend analysis
  • y_contr = contraction scour (ft) — from Laursen's equation (FHWA HEC-18 §6)
  • y_local = local pier or abutment scour (ft) — from CSU equation (FHWA HEC-18 §7)
Inputs: where each value comes from (1)
SymbolWhat it isComes fromHow to get itTypical range
ylonglong-term degradation scour (ft) — from channel bed trend analysisHydraulic studyFrom the hydraulic model or study (HEC-RAS, FHWA HEC-18), stream gauge records or the drainage design.project-specific
Equation 2.8-18 — CSU Local Pier Scour Equation:

y_s / y_1 = 2.0 × K₁ × K₂ × K₃ × K₄ × (a/y_1)^0.65 × Fr₁^0.43

Where:

  • y_s = pier scour depth (ft)
  • y_1 = flow depth directly upstream of pier (ft)
  • K₁ = correction for pier nose shape (1.1 for square; 1.0 for round)
  • K₂ = correction for angle of attack of flow
  • K₃ = correction for bed condition (1.1 for clear-water, plane-bed and antidune flow; up to 1.3 for large dunes)
  • K₄ = correction for armoring by bed material size
  • a = pier width (ft)
  • Fr₁ = Froude number at the pier = V₁ / √(g × y₁); g = 32.2 ft/s²

Submit scour analysis results to the owner railroad's bridge engineering group. Railroad bridges are inspected at least annually under 49 CFR Part 237; for bridges the owner designates scour-critical, keep the scour evaluation and a monitoring plan in the bridge file.

Inputs: where each value comes from (9)
SymbolWhat it isComes fromHow to get itTypical range
yspier scour depth (ft)Hydraulic studyFrom the hydraulic model or study (HEC-RAS, FHWA HEC-18), stream gauge records or the drainage design.project-specific
y1flow depth directly upstream of pier (ft)Hydraulic studyFrom the hydraulic model or study (HEC-RAS, FHWA HEC-18), stream gauge records or the drainage design.project-specific
K₁correction for pier nose shape (1.1 for squareChart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
K₂correction for angle of attack of flowChart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
K₃correction for bed condition (1.1 for clear-waterChart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
K₄correction for armoring by bed material sizeChart, table or correction factorRead from the cited chart or table for the site conditions; values listed in the definition.project-specific
apier width (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
Fr₁Froude number at the pier = V₁ / √(g × y₁)Hydraulic studyFrom the hydraulic model or study (HEC-RAS, FHWA HEC-18), stream gauge records or the drainage design.project-specific
g32.2 ft/s²ConstantPhysical constant or standard value.project-specific
Supplemental reference

Flow nets in anisotropic ground

Water-laid soils are usually more permeable horizontally than vertically (wind-blown silts can be the reverse because of root holes). A flow net is only valid for isotropic conditions, so USACE draws it on a transformed section: multiply every horizontal dimension by √(kv/kh), draw a square flow net, then map it back to the true section. Seepage quantity uses the equivalent permeability k′ = √(khkv). Pore pressures and uplift can be read from either section, but gradients and seepage forces must be taken from the true section — the exit gradient in Eq. 2.8-16 is understated if it is scaled from the transformed net. Figure 9-S1 shows the same net for kh = kv, 4kv and 9kv.

Flow nets drawn on a transformed section and redrawn on the true section for k<sub>h</sub> = k<sub>v</sub>, k<sub>h</sub> = 4k<sub>v</sub> and k<sub>h</sub> = 9k<sub>v</sub> (after Cedergren).
Supplemental Figure 9-S1. Flow nets drawn on a transformed section and redrawn on the true section for kh = kv, kh = 4kv and kh = 9kv (after Cedergren). Source: U.S. Army Corps of Engineers (1986, Change 1 1993). Seepage Analysis and Control for Dams. EM 1110-2-1901, p. 4-15.

At boundaries between soils of different permeability, flow channels narrow and equipotential spacing widens as water passes into the more permeable layer — head is lost mainly in the tighter soil.

Soil Permeability
Soil Permeability

Why a lab k can miss by five orders of magnitude

USACE cites Cedergren’s case of a dam foundation logged from borings as uniform sandy gravel: lab tests on disturbed samples gave k ≈ 3 × 10−3 ft/day and a predicted underseepage of 3 ft3/day. The cutoff trench exposed streaks of openwork gravel (k ≈ 85,000 ft/day); without the cutoff, seepage would have been about 1,000,000 ft3/day. Grain-size sampling in drill holes washes out the very feature that controls flow. For railroad embankments beside rivers and at bridge approaches in alluvial gravel, rely on pumping tests and groundwater response to river stage, not lab permeability of disturbed samples. The reverse is also true: a thin continuous clay seam can control vertical flow through an otherwise pervious site.

Permeability controls everything below ground
Permeability controls everything below ground
Seepage Control
Seepage Control
Influence of openwork gravel on underseepage: (a) profile surmised from drill holes, 3 ft<sup>3</sup>/day; (b) profile revealed by cutoff trench, about 1,000,000 ft<sup>3</sup>/day without the cutoff (after Cedergren).
Supplemental Figure 9-S2. Influence of openwork gravel on underseepage: (a) profile surmised from drill holes, 3 ft3/day; (b) profile revealed by cutoff trench, about 1,000,000 ft3/day without the cutoff (after Cedergren). Source: U.S. Army Corps of Engineers (1986, Change 1 1993). Seepage Analysis and Control for Dams. EM 1110-2-1901, p. 2-10.
Figure 2.8-12. A settling embankment with an exposed culvert and active seepage.
Figure 2.8-12. A settling embankment with an exposed culvert and active seepage.

Source: U.S. Army Corps of Engineers (1986, Change 1 1993). Seepage Analysis and Control for Dams. EM 1110-2-1901

Supplemental reference

Designing the filter that prevents piping (USACE / NRCS)

A drain at the toe of an embankment, behind a wall, or around an edge-drain pipe must keep the protected soil in place while passing water. USACE EM 1110-2-1901 (App. D, adopted from the NRCS 1986 filter guide) sizes the filter from the protected (“base”) soil:

Erosion Around Foundations
Erosion Around Foundations
Scour Protection Around Structures
Scour Protection Around Structures

Table 9-S1. USACE filter criteria (d = base soil, D = filter)

Base soil category% finer than No. 200*Retention criterion
1 – fine silts and clays> 85D15 ≤ 9 × d85
2 – sands, silts, clays, silty/clayey sands40–85D15 ≤ 0.028 in.
3 – silty and clayey sands and gravels15–39D15 ≤ [(40 − A)/(40 − 15)] × [(4 × d85) − 0.028 in.] + 0.028 in. (A = % passing No. 200)
4 – sands and gravels< 15D15 ≤ 4 to 5 × d85

* After regrading the base soil on the minus No. 4 fraction when it contains gravel.

  • Permeability: minimum D15 ≥ 3 to 5 × maximum d15 of the base soil (before regrading), and not less than 0.0039 in.. The maximum D15 need not be smaller than 0.0079 in..
  • Filter limits: maximum particle size 3 in.; ≤ 5% passing No. 200; the minus No. 40 fraction must be non-plastic (PI = 0).
  • Perforated pipe: filter D50 / hole diameter (or slot width) ≥ 1.0. Where one filter cannot satisfy both the soil and the pipe, use a graded (two-layer) filter.
  • Gap-graded base: design to protect the fine matrix, not the whole gradation. Never specify a gap-graded filter — piping can run through its loosely filled voids.
  • A small initial movement of fines into the filter when seepage starts is normal and should stop quickly; have qualified staff observe first operation of new drains.

These criteria are more specific than the Terzaghi ratios used for subballast in Chapter 2.3 and are the ones to cite for edge drains, wall drains and toe filters in railroad embankments.

Source: U.S. Army Corps of Engineers (1986, Change 1 1993). Seepage Analysis and Control for Dams. EM 1110-2-1901

Seepage through railway fill: what the field sees

A head difference of more than about 6 ft across an embankment forces flow beneath the track. Seepage zones appear at the downhill toe within days, depending on fill permeability. Thin, permeable granular layers hidden in a fill can carry water deep into it unseen; an April 2013 slope failure followed exactly that path from a wet uphill ditch. Dirty or milky water and sand fans mean piping is underway. When seepage appears, do not plug it with clay. Let it out through ballast, geotextile and gravel so pressure cannot build.

Figure 2.8-10. High differential water level driving seepage beneath the track.
Figure 2.8-10. High differential water level driving seepage beneath the track.
Figure 2.8-11. Water in the uphill ditch, seepage below the tracks, and the partial slip that followed (illustrative risk rating: High).
Figure 2.8-11. Water in the uphill ditch, seepage below the tracks, and the partial slip that followed (illustrative risk rating: High).

After Geotechnology for Railroaders Program, Module 7.1, Module 4, Module 2; Module 7.1 §04–05; Module 4 §08; Module 2 §06. Full reference under Supplemental References.

2.8.5.5 Flow Nets, Layered Permeability and Piping Checks

The library's course notes on flow nets and on seepage through heterogeneous soil cover the three calculations most often needed when water stands against a railroad fill: the quantity of seepage, the exit gradient at the toe, and the equivalent permeability of a layered foundation. Layering matters more than any single permeability value: a thin sand seam under a clay-capped fill carries most of the flow and sets where it comes out.

2.8.5.5.1 Method

Equation 2.8-21. Seepage from a flow net

q = k ΔH Nf/Nd per unit length;  for anisotropic soil use k' = √(khkv) on a section transformed by √(kv/kh) horizontally

Equation 2.8-22. Equivalent permeability of layered soil

kh = ΣkiHi / ΣHi   kv = ΣHi / Σ(Hi/ki)

Equation 2.8-23. Exit gradient and piping

ie = (ΔH/Nd)/lexit;  ic = γ'/γw;  FS = ic/ie (commonly 3 or more)

2.8.5.5.2 Worked example: water ponded against an embankment

Table 2.8-3. 8 ft of ponded water over a three-layer foundation (calculator output)
ResultValue
Equivalent kh / kv8.257 ft/day / 0.1847 ft/day
Seepage per foot3.293 ft³/day/ft
Total over 300 ft5.13 gpm
Exit gradient0.267
FS against piping3.76

The layered foundation (sand over a thin clay over clean sand) has a horizontal permeability more than forty times its vertical value, so seepage concentrates in the lower sand and can surface beyond the toe. A factor of safety near 3.8 is adequate for this water level, but the chart in the calculator shows it falls below 3 if the pond rises a little over 2 ft, which is the kind of threshold that belongs in the site's live rating (Section 3.8.26).

Open the seepage calculator →
Flow-net seepage quantity, layered (anisotropic) permeability, exit gradient and factor of safety against piping, and a Hazen check of k from D10.

2.8.5.5.3 Sources in the library

These documents are in the reference library. The method summaries above are paraphrased; equations are standard forms.