Many rail lines follow rivers, cross them below dams, or run along reservoir shores on embankments built when the reservoir was filled. Dams change the river around them: the reservoir traps sediment, raises water levels and saturates the embankments and slopes along its shore, and the river below the dam often degrades because it has been starved of sediment. Removing a dam, drawing down a reservoir for maintenance, or a dam failure reverses those changes quickly. This section summarizes what railroad engineers should look for, using the federal guidelines for analyzing sediment in dam removal (Randle and Bountry 2017). Nearly 1,400 dams had been removed in the United States by 2016, most of them small, and the pace is increasing.
| Location | Effect | Railroad concern |
|---|---|---|
| Reservoir shore | Water level drops during drawdown; the slopes lose the support of the reservoir while still saturated | Rapid drawdown failure of embankments and cut slopes along the former shore (Chapter 6.3, Section 6.3.8); reactivated landslides on the reservoir rim |
| Former reservoir and upstream river | The river cuts a new channel through the reservoir sediment; a knickpoint (headcut) migrates upstream; banks erode and sediment terraces slump | Undermining of bridge piers, culvert outlets and pipeline crossings upstream; new bank erosion at the toe of track embankments that were built above the reservoir level |
| Downstream river | A sediment wave of gravel and sand moves downstream and deposits where the river slows; fine sediment passes through as wash load | Aggradation reduces bridge clearance and culvert capacity and raises flood stages and groundwater beside the track; deposited bars deflect flow into banks and embankment toes; more large wood can block bridge openings and culverts |
| Downstream river, longer term | Channel widening and bank erosion as the river adjusts; ice jams no longer moderated by the reservoir | Scour and bank erosion at embankments and bridge abutments (Section 2.8.5; Chapter 3.5, Section 3.5.11) |
The guidelines measure the probability of sediment impact by the relative reservoir sediment volume, Ts = Vs/Qs: the stored sediment volume (or mass) divided by the river’s average annual sediment load. Ts is the number of years of upstream supply stored behind the dam. On a logarithmic scale, values below about 0.1 year are negligible (common for low-head dams); roughly 0.1 to 1 year is small, 1 to 10 years medium, and more than 10 years large. Contaminated sediment raises the probability.
Risk is then read from a matrix of probability against consequence, the same structure as the GHRM rating matrix (Chapter 3.8):
| Probability | Small consequence | Medium consequence | Large consequence |
|---|---|---|---|
| Small | Low | Low | Moderate |
| Medium | Low | Moderate | High |
| Large | Moderate | High | High |
Effects generally diminish with distance downstream, as tributaries dilute the flow and the sediment wave loses mass by deposition: a bridge just below a dam is at more risk than one several miles away. Coarse sediment that deposits early is reworked by later floods, so the peak impact at a downstream bridge can come a year or more after removal.
The guidelines require the drawdown rate of large reservoirs to be slow enough to avoid a flood wave downstream and to avoid triggering landslides along the reservoir margins or failure of earth dams. The same limit protects railroad embankments and cut slopes along the shore. A flood during removal can overtop a partly removed dam and send a flood wave far larger than the inflow downstream.
Source: Randle and Bountry (2017), Steps 1, 4, 5, 6 and 7. Full reference under Supplemental References.