2.8.15 Dams, Reservoir Drawdown and Dam Removal Near the Railroad

Groundwater is the single most consequential subsurface variable in railroad geotechnical engineering.
Authors: Daniel P. Colwell and Mario Ruel
2.8.15 Dams, Reservoir Drawdown and Dam Removal Near the Railroad

Many rail lines follow rivers, cross them below dams, or run along reservoir shores on embankments built when the reservoir was filled. Dams change the river around them: the reservoir traps sediment, raises water levels and saturates the embankments and slopes along its shore, and the river below the dam often degrades because it has been starved of sediment. Removing a dam, drawing down a reservoir for maintenance, or a dam failure reverses those changes quickly. This section summarizes what railroad engineers should look for, using the federal guidelines for analyzing sediment in dam removal (Randle and Bountry 2017). Nearly 1,400 dams had been removed in the United States by 2016, most of them small, and the pace is increasing.

2.8.15.1 How dam removal affects the track

Table 2.8-15. Dam removal and drawdown effects on railroad infrastructure
LocationEffectRailroad concern
Reservoir shoreWater level drops during drawdown; the slopes lose the support of the reservoir while still saturatedRapid drawdown failure of embankments and cut slopes along the former shore (Chapter 6.3, Section 6.3.8); reactivated landslides on the reservoir rim
Former reservoir and upstream riverThe river cuts a new channel through the reservoir sediment; a knickpoint (headcut) migrates upstream; banks erode and sediment terraces slumpUndermining of bridge piers, culvert outlets and pipeline crossings upstream; new bank erosion at the toe of track embankments that were built above the reservoir level
Downstream riverA sediment wave of gravel and sand moves downstream and deposits where the river slows; fine sediment passes through as wash loadAggradation reduces bridge clearance and culvert capacity and raises flood stages and groundwater beside the track; deposited bars deflect flow into banks and embankment toes; more large wood can block bridge openings and culverts
Downstream river, longer termChannel widening and bank erosion as the river adjusts; ice jams no longer moderated by the reservoirScour and bank erosion at embankments and bridge abutments (Section 2.8.5; Chapter 3.5, Section 3.5.11)

2.8.15.2 How much sediment, and how likely an impact

The guidelines measure the probability of sediment impact by the relative reservoir sediment volume, Ts = Vs/Qs: the stored sediment volume (or mass) divided by the river’s average annual sediment load. Ts is the number of years of upstream supply stored behind the dam. On a logarithmic scale, values below about 0.1 year are negligible (common for low-head dams); roughly 0.1 to 1 year is small, 1 to 10 years medium, and more than 10 years large. Contaminated sediment raises the probability.

Risk is then read from a matrix of probability against consequence, the same structure as the GHRM rating matrix (Chapter 3.8):

Table 2.8-16. Risk of sediment impact (after Randle and Bountry 2017, Table 6)
ProbabilitySmall consequenceMedium consequenceLarge consequence
SmallLowLowModerate
MediumLowModerateHigh
LargeModerateHighHigh

Effects generally diminish with distance downstream, as tributaries dilute the flow and the sediment wave loses mass by deposition: a bridge just below a dam is at more risk than one several miles away. Coarse sediment that deposits early is reworked by later floods, so the peak impact at a downstream bridge can come a year or more after removal.

2.8.15.3 How fast the reservoir sediment erodes

  • Erosion happens in two phases. First, the amount and rate of reservoir lowering control how fast the channel cuts down through the deposit. Afterwards, floods that overtop the new banks widen the channel toward its long-term width.
  • In case histories, an average of about 28% (range 8% to 65%) of the stored sediment eroded in the first year after removal of twelve mostly low-head dams. For coarse deposits the first-year average was about 43% (range 1% to 77%); for deposits with more than 30% fines it was about 25% (8% to 72%). Erosion continued for two to four years at a declining rate.
  • Less sediment erodes from wide reservoirs (deposit width more than about 2.5 times the channel width) and from fine, consolidated or vegetated deposits; coarse, unvegetated deposits erode fast and wide. Loose fine sediment can erode faster than sand.
  • Rapid lowering can cause mass wasting of saturated sediment terraces, which adds sediment and can affect slopes near the shore.
  • If the incising channel reaches resistant material (bedrock, an old structure, boulders, clay), down-cutting stops and erosion turns sideways into the banks.

2.8.15.4 Drawdown rate and embankments on the shore

The guidelines require the drawdown rate of large reservoirs to be slow enough to avoid a flood wave downstream and to avoid triggering landslides along the reservoir margins or failure of earth dams. The same limit protects railroad embankments and cut slopes along the shore. A flood during removal can overtop a partly removed dam and send a flood wave far larger than the inflow downstream.

2.8.15.5 What to do when a dam near the line is to be removed or drawn down

  • Desktop study. Identify dams upstream and downstream of the line and of each bridge from the National Inventory of Dams and state dam safety records, and note any removal, drawdown or rehabilitation plans (Chapter 3.2).
  • Engage early. Dam removal projects follow a stepwise process with a communication plan and stakeholder review; ask to have the railroad’s bridges, culverts and embankments listed among the infrastructure concerns in Step 1, and obtain the predicted sediment volume, Ts, drawdown schedule and erosion and deposition predictions.
  • Check the structures. For bridges upstream, check foundations against the predicted channel incision (knickpoint) with scour added. For bridges and culverts downstream, check waterway opening and freeboard against predicted aggradation and wood loads. For embankments on the shore, check rapid drawdown stability at the planned drawdown rate (Chapter 6.3, Section 6.3.8).
  • Screen the risk. Question 2.8-6 (Section 2.8.12) works an example: stored sediment, first-year erosion, risk rating and loss of bridge freeboard.
  • Monitor. Survey channel cross sections at railroad bridges before removal and after floods for several years; inspect embankment toes and shore slopes during and after drawdown; add the removal schedule to the live rating triggers (Chapter 3.8).

Source: Randle and Bountry (2017), Steps 1, 4, 5, 6 and 7. Full reference under Supplemental References.