↑ Parent Menu⌂ Main Menu
← Chapter 2.8 Groundwater Characterization and Seepage
GHRM
Railway Ground Hazard Risk Management · 2.0 · The Underworld
Sections · click a car to open it

2.8.6 Dewatering Design

Groundwater is the single most consequential subsurface variable in railroad geotechnical engineering.
Authors: Daniel P. Colwell and Mario Ruel
2.8.6 Dewatering Design

When railroad construction requires excavation below the water table — for bridge footing construction, retaining wall foundation placement, or culvert installation — dewatering is required. Our geotechnical investigation provides the hydraulic conductivity and aquifer geometry data that the dewatering contractor uses to design the system.

Impact of Excavation on Hydrogeologic Regime and Slope Stability
Impact of Excavation on Hydrogeologic Regime and Slope Stability
Figure 2.8-17. Wick-drain installation rigs.
Figure 2.8-17. Wick-drain installation rigs.
2.8.6.1 Dewatering Method Selection
MethodBest Fork Range (ft/day)Max Drawdown
Sump pumpingGravels, cobbles> 1,000Unlimited if pump capacity adequate
WellpointsSands, silty sands1 – 10015–18 ft per stage
Deep wellsConfined aquifers, deep drawdowns0.1 – 1,000Unlimited
Eductor wellsSilts, fine sands0.001 – 1.050–100 ft
Horizontal drainsSlope drainage, moderate k0.01 – 10N/A
Electro-osmosisClays< 0.001Limited
Figure 2.8-13. Horizontal subdrains discharging from a cut slope.
Figure 2.8-13. Horizontal subdrains discharging from a cut slope.

Construction within about 100 ft of a waterway or wetland usually needs a dewatering plan reviewed by the railroad's environmental group. Obtain any dewatering permit and prepare a groundwater monitoring plan before construction dewatering begins on railroad right-of-way.

2.8.6.2 Wellpoint Spacing and Yield

For a wellpoint system, the required spacing is estimated from:

Equation 2.8-19 — Single Wellpoint Yield:

Q_w = π × k × (H² − h_w²) / ln(R_e / r_w)

Where:

  • Q_w = yield per wellpoint (ft³/day)
  • k = hydraulic conductivity (ft/day)
  • H = saturated thickness above the base of the aquifer before pumping (ft)
  • h_w = water depth in the wellpoint during pumping (ft); drawdown s_w = H − h_w
  • R_e = radius of influence (ft) — estimated from Sichardt's formula (Eq. 2.8-20)
  • r_w = effective wellpoint radius (ft)

Source: Dupuit, J. (1863), Études théoriques et pratiques sur le mouvement des eaux; Powers, J.P., Corwin, A.B., Schmall, P.C. and Kaeck, W.E. (2007), Construction Dewatering and Groundwater Control, 3rd ed., Wiley (unconfined well equation).

Inputs: where each value comes from (5)
SymbolWhat it isComes fromHow to get itTypical range
Qwintermediate value computed on this pageAnother equationComputed: Q_w = π × k × (H² − h_w²) / ln(R_e / r_w)project-specific
khydraulic conductivity (ft/day)Field or lab testField: pumping test, slug test (ASTM D4044, withdrawn 2024) or packer test. Lab: constant head (D2434) for sands, flexible-wall (D5084) for clays. Hazen k ≈ C·D102 for clean sands only.clean sand 1–100, clay < 0.001 ft/day · by USCS group
Hsaturated thickness above the base of the aquifer before pumping (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific
hwwater depth in the wellpoint during pumping (ft)Field measurementGroundwater level from boring logs, observation wells or piezometers (ASTM D5092 / D4750); design with the seasonal high level.project-specific
rweffective wellpoint radius (ft)Test setupDimension of the test equipment or specimen: from the test standard or the lab/field test record.project-specific
Equation 2.8-20 — Radius of Influence (Sichardt approximation):

R_e = 1,660 × s_w × √k    (k in ft/s) ≈ 5.6 × s_w × √k    (k in ft/day)

Where s_w = drawdown at the well (ft) and R_e is in ft. This is the English-unit form of Sichardt's R = 3,000 s √k (R and s in m, k in m/s): 3,000 × √0.3048 ≈ 1,656. It is empirical and gives a small, first-cut R_e; check against pumping-test data or a transient (Cooper–Jacob) estimate.

Source: Kyrieleis, W. and Sichardt, W. (1930), Grundwasserabsenkung bei Fundierungsarbeiten, Springer, Berlin; Powers et al. (2007).

Inputs: where each value comes from (1)
SymbolWhat it isComes fromHow to get itTypical range
swdrawdown at the well (ft) and R_e is in ft. This is the English-unit form of Sichardt's RAnother equationComputed: s_w = 3,000 s √k (R and s in m, k in m/s): 3,000 × √0.3048 ≈ 1,656. It is empirical and gives a small, first-cut R_e; check against pu≈ 1,656. It is empirical and gives a small, first-cut R_e

Railway subdrainage toolbox

  • Horizontal drains drilled from the toe relieve pressure in a hidden granular layer; they can fix a slide quickly but clog over time and need replacing.
  • French drains: washed river rock around perforated pipe wrapped in geotextile, intercepting subsurface water.
  • Lateral (cross) trench drains across the roadbed to an outlet, backfilled with clean stone in compacted lifts; used together with a toe berm at one Class I railroad slide repair.
  • Wick drains shorten the drainage path to speed consolidation of soft saturated ground.
  • Sump pumping removes standing water directly from a low point, in an emergency or permanently.
Figure 2.8-14. French drain cross-section.
Figure 2.8-14. French drain cross-section.
Figure 2.8-15. Lateral trench drain: section and field installation (slide by M. Ruel).
Figure 2.8-15. Lateral trench drain: section and field installation (slide by M. Ruel).
Figure 2.8-16. A gravel subdrain trench lowering the water table.
Figure 2.8-16. A gravel subdrain trench lowering the water table.
Figure 2.8-18. Emergency sump pumping (slide by M. Ruel).
Figure 2.8-18. Emergency sump pumping (slide by M. Ruel).

After Geotechnology for Railroaders Program, Module 6.1, Module 6.2, Module 4; Module 6.1 §02; Module 6.2 §02; Module 4 §05. Full reference under Supplemental References.

Project management · Smith and Hinze (2010)

Dewatering Scope Gaps That Cause Field Problems

Smith and Hinze write from the general contractor’s side, cataloguing scope items that tend to fall between subcontracts. They note that sizing wells to the water table handles most of the inflow, but the remainder often comes from conditions the borings missed, such as a perched sand layer over clay or rock feeding water through the lagging. They also note that dewatering cost is rarely obvious from the drawings, so a contingency for spot dewatering is prudent. Their checklist includes:

Wellpoint dewatering system drawing down the groundwater table through layered sandy loam, clay, silty sand and sand beneath an excavation.
Figure 9-PM1. Wellpoint dewatering system drawing down the groundwater table through layered sandy loam, clay, silty sand and sand beneath an excavation. Source: Smith and Hinze (2010), Figure 4.1.
  • Backup power. A power outage of even a few hours can let water rise into the excavation bottom and pits. An outage of 12–24 hours can undermine shoring designed for dry conditions. Provide an automatic standby generator, exercise it on a schedule, and assign fuel responsibility in writing.
  • Spares and daily checks. Keep spare pumps and pipe on site. Check every well at the start and end of each shift.
  • Well location. Keep wells well back from the excavation edge, or use slotted casings. Open drain-rock-filled holes near the face can cave and destabilize the wall as the excavation deepens.
  • Drawdown time. Estimate the drawdown time and check it against the schedule. In clays, drawdown can become the critical path.
  • Discharge. Settling tanks, discharge permits, testing and treatment of contaminated water are commonly excluded by every bidder. Make sure each is covered once, and only once.
  • Bidding information. Show pit locations and depths to dewatering bidders, since these are often missing from conceptual drawings.
  • Abandonment. Define abandonment in the bid documents: what is removed, the depth at which casings are cut off, and how wells are grouted and backfilled.
  • Contractor selection. Where life safety or adjacent property is at risk, select the dewatering contractor on proven experience rather than price.

For railroad work: Culvert replacements, bridge foundation work and cut-and-cover crossings under or beside live track add a consequence the building-site checklist does not: loss of dewatering can soften the embankment or subgrade carrying traffic, not just the excavation bottom. In the dewatering GSP and the monitoring plan:

  • Treat backup power and around-the-clock pump monitoring as mandatory.
  • Pair drawdown with settlement points on the track and piezometers at the embankment toe.
  • Name the action, such as notifying the railroad and imposing a slow order, if pumps stop or settlement thresholds are reached.

Coordinate discharge routing with the railroad’s drainage and environmental staff, since ditches along the right-of-way often discharge to regulated waters.

Source: Smith, J. G., and Hinze, J. (2010). Construction Management: Subcontractor Scopes of Work. Boca Raton, FL: CRC Press, pp. 29–35. Summarized and paraphrased; figures reproduced for internal reference. Full reference under Supplemental References.

Supplemental reference · Rajapakse (2016), Ch. 37

Slurry Cutoff Walls and Slurry-Trench Stability

Where dewatering would draw down the groundwater under track, a nearby structure or a wetland, a vertical cutoff wall can be the better answer. It is keyed into an underlying low-permeability layer and stops lateral seepage instead of pumping it out. Slurry cutoff walls are also used to contain contaminated groundwater.

  • Soil–bentonite (SB) walls. A trench is excavated under bentonite slurry, and the excavated soil is mixed with bentonite and slurry beside the trench and pushed back in. The backfill weighs about 120 pcf. The more fines it contains, the lower its permeability, but clay in lumps does not lower it much. A heavy SB backfill can bulge the trench walls.
  • Cement–bentonite (CB) walls. A cement–bentonite slurry, about 70 pcf, both supports the trench and hardens in place to form the wall. No soil is used. CB walls avoid bulging and suit sites with little room for mixing, such as a narrow strip beside an operating track.

Trench stability. The open trench stands because the slurry pressure exceeds the lateral push of the soil and groundwater on its walls. Below the water table, the soil side carries both the effective lateral stress and the full pore-water pressure. A screening check at depth z is:

FS(z) = γf (z − zf) / [Ka σ′v + u + Ka q]

where γf = slurry unit weight, zf = depth of the slurry surface, σ′v = vertical effective stress in the soil, u = pore-water pressure, and q = any surcharge such as track and train loading. Rajapakse’s worked example compares the slurry pressure with Kaσ′v alone and leaves out u. In his own case that gives a safety factor of 3.6 at the base of a 25-ft trench, when including the groundwater gives about 1.1 (Example 2.8-5). Always include the water pressure.

The check is simplified and on the safe side. It ignores the support from the filter cake, the arching of a short panel, and any cohesion. Its trends are the useful part:

  • Below the water table, FS falls with depth toward the limit γf / (Kaγ′ + γw).
  • Keeping the slurry level high, at least several feet above the groundwater, helps more than any other measure.
  • A slurry that thins with time or loses head through a permeable layer can collapse the trench without warning.

For railroad work: A slurry trench near an operating track is a temporary excavation in the zone of influence of the track (Chapter 7.1, Section 7.1.17). Include the train surcharge in the check. Specify the minimum slurry level and slurry unit weight, and require them to be measured and recorded every shift. Hold the slurry level at least 3 ft above the highest groundwater level expected during the work. Keep open panels short and backfill them promptly, and survey the track for settlement while the trench is open. The owner railroad’s criteria for excavations near track govern the offset and any slow order.

Source: Rajapakse, R. (2016). Geotechnical Engineering Calculations and Rules of Thumb, 2nd ed. Oxford: Butterworth-Heinemann, Ch. 37 (slurry cutoff walls, Design Example 37.1). Summarized and paraphrased. The trench-stability check is corrected here to include pore-water pressure, and the surcharge term and recommendations for railroad work are added by the authors of this manual.

Example 2.8-5: Stability of a Slurry Trench for a Cutoff Wall Beside the Track

A Class I railroad located in Florida needs to cut off seepage through a sand layer that is softening the toe of a main-line embankment beside a borrow lake. The plan is a 25-ft-deep soil–bentonite cutoff wall keyed into clay, built with a slurry trench parallel to the track. The sand weighs 120 pcf with φ′ = 30°, and groundwater is 5 ft below the ground surface. The contractor proposes slurry at 90 pcf held 2 ft below the ground surface, the same case as Rajapakse’s Design Example 37.1. The engineer must check the trench walls, see how far Rajapakse’s method overstates the safety, and set the slurry requirements.

clay (key)sand, γ = 120 pcf, φ′ = 30° GW 5 ft slurry 90 pcf track 25 ft 2 ft FS(z) = ? GivenTrench 25 ft deep, keyed into claySand γ = 120 pcf; φ′ = 30°Groundwater 5 ft below surfaceSlurry 90 pcf, surface 2 ft down RequiredFS without pore pressure (Rajapakse)FS with pore pressure at 5, 10, 25 ftEffect of raising the slurrySlurry weight for FS 1.2 Black = given; red = required
Given and required for Example 2.8-5.

Given

VariableValueDescription
Trench depth25 ftKeyed into the clay below the sand
γ, φ′120 pcf, 30°Sand; Ka = tan2(45° − φ′/2) = 0.333
zw5 ftDepth to groundwater; γw = 62.4 pcf
γf, zf90 pcf, 2 ftSlurry unit weight and depth of the slurry surface
qNeglected hereTrain surcharge; add Kaq where the track is within the trench’s zone of influence

Required

  • (a) FS at the trench base by Rajapakse’s method, without pore pressure
  • (b) FS with pore pressure at 5, 10 and 25 ft, and its limit with depth
  • (c) FS at the base if the slurry is held at the ground surface
  • (d) Slurry unit weight needed for FS = 1.2 at the base with the slurry 2 ft down

Equations

  1. Eq. 1: σ′v = γzw + (γ − γw)(z − zw); u = γw(z − zw)
  2. Eq. 2: FS = γf(z − zf) / (Kaσ′v + u)
  3. Eq. 3: FS∞ = γf / (Kaγ′ + γw) — limit at depth

Steps

Step 1 · Stresses at 25 ft (Eq. 1)
σ′v = 120 × 5 + 57.6 × 20 = 1,752 psf; u = 62.4 × 20 = 1,248 psf; slurry = 90 × 23 = 2,070 psf
Kaσ′v = 584 psf
↓
Step 2 · (a) Without pore pressure
2,070 / 584 (Rajapakse used Ka = 0.33: 2,070/578)
FS = 3.5 to 3.6: not valid
↓
Step 3 · (b) With pore pressure (Eqs. 2, 3)
5 ft: 270/200 = 1.35; 10 ft: 720/(296 + 312) = 1.18; 25 ft: 2,070/(584 + 1,248) = 1.13; limit 90/(0.333 × 57.6 + 62.4)
FS = 1.35, 1.18, 1.13; FS∞ = 1.10
Spot check: with Rajapakse’s Ka = 0.33, 2,070/(578 + 1,248) = 1.13, the same.
↓
Step 4 · (c) Slurry at the ground surface
90 × 25 = 2,250 psf; 2,250/1,832
FS = 1.23 at the base
↓
Step 5 · (d) Slurry weight for FS 1.2 (slurry 2 ft down)
γf = 1.2 × 1,832 / 23
γf ≈ 96 pcf
↓
Solution
FS ≈ 1.13 at the base, not 3.6; raise the slurry to the surface or make it heavier.

Solution

(a) Without pore pressure, FS appears to be 3.6, which is wrong. (b) With pore pressure, FS = 1.35 at the water table, 1.18 at 10 ft and 1.13 at the base, falling toward 1.10 with depth. (c) Holding the slurry at the ground surface raises the base FS to 1.23. (d) With the slurry 2 ft down, about 96 pcf would be needed for FS = 1.2.

The trench is only marginally stable as proposed. Rajapakse’s method would have hidden that, because it treats the groundwater as if it did not push on the trench wall. Because the check ignores filter-cake support and panel arching, real trenches in this sand will likely stand, but the margin is too thin to count on next to a main line. Specify the slurry level at the ground surface (at least 3 ft above the groundwater), a minimum slurry unit weight with each shift’s measurements recorded, and short open panels. Add the train surcharge if the trench is within about its own depth of the nearest rail, and recheck. Survey the track daily while the trench is open, and agree a slow order with the railroad in advance in case settlement appears.

← Previous · 2.0 The Underworld Chapter 2.7 — Rock and Sand: Properties, Typical Values and Behavior
Next · 2.0 The Underworld → Chapter 2.9 — Collapsible Soils: Identification, Testing and Railroad Impacts