Pre-Mobilization
- [ ] Seasonal monitoring duration confirmed per client requirements (Section 2.8.3.4)
- [ ] Piezometer installation plan prepared: type, depth, screen interval for each boring
- [ ] VW transducer calibration certificates on file (Class I railroad emergency response)
- [ ] Baseline topographic survey of piezometer installation locations (NAVD 88 elevations)
- [ ] Slug test materials staged: bailer or slug, water-level indicator, stopwatch
During Drilling
- [ ] First-encountered water level depth and clock time recorded in every boring
- [ ] Artesian conditions: overflow rate estimated; FEWL = ground surface (or above) flagged on log
- [ ] Piezometer installation documented: screen depth, sand pack interval, bentonite seal depths, casing diameter
- [ ] Initial water level reading taken immediately after installation
During Monitoring
- [ ] Readings taken to nearest 0.01 ft with calibrated instrument
- [ ] Date, time, weather conditions recorded at each reading event
- [ ] Slug tests conducted in sand or gravel screen intervals; recovery plotted in field before demobilization
- [ ] VW datalogger download confirmed on schedule; battery status checked
Post-Field
- [ ] Seasonal high and low water table elevations (ft NAVD 88) computed from monitoring data
- [ ] Stabilized water levels entered into project GIS (State Plane coordinates, client-required system)
- [ ] Effective stress profile computed for design groundwater level; submitted as pre-design memo
- [ ] Scour analysis initiated for all bridge sites (FHWA HEC-18 per AREMA MRE Chapter 8)
- [ ] Piping FS computed for all embankment/waterway combinations; FS ≥ 4.0 confirmed