2.8.2 Groundwater Measurements in Boreholes

Groundwater is the single most consequential subsurface variable in railroad geotechnical engineering.
Authors: Daniel P. Colwell and Mario Ruel
2.8.2 Groundwater Measurements in Boreholes
2.8.2.1 First-Encountered and Stabilized Levels

Two water level observations are recorded in every boring:

  1. First-encountered water level (FEWL): The depth at which water is first observed in the borehole during drilling. Record depth and clock time. FEWL in an open borehole in sandy soils approaches the true water table quickly; FEWL in clay soils may be unreliable due to seal effects of the clay against the casing or auger.
  2. Stabilized water level (SWL): Measured with a water-level indicator (electronic probe or steel tape) a minimum of 30 minutes after drilling is completed in granular soils and a minimum of 24 hours after completion in cohesive soils. For clay-rich profiles, 48–72 hours is often required. Document the 24-hour stabilized reading.
Equation 2.8-2 — Piezometric Head at Measurement Point:

h = z_m − y_w

Where:

  • h = total piezometric head (ft above datum, typically NAVD 88)
  • z_m = elevation of measurement point (ft NAVD 88) — top of casing or other surveyed reference point
  • y_w = depth to water from measurement point (ft); negative value indicates water level is above the measurement point (artesian)
Measurement While Drilling for Piezometric Levels
Measurement While Drilling for Piezometric Levels
Inputs: where each value comes from (3)
SymbolWhat it isComes fromHow to get itTypical range
hintermediate value computed on this pageAnother equationComputed: h = z_m − y_wproject-specific
zmelevation of measurement point (ft NAVD 88) — top of casing or other surveyed reference pointTest setupDimension of the test equipment or specimen: from the test standard or the lab/field test record.project-specific
ywdepth to water from measurement point (ft)Field measurementGroundwater level from boring logs, observation wells or piezometers (ASTM D5092 / D4750); design with the seasonal high level.project-specific
2.8.2.2 Artesian Conditions

Artesian pressure occurs when the piezometric head at a confined aquifer exceeds the ground surface elevation. Artesian conditions are common beneath Cretaceous and Paleogene clay confining layers in the Atlantic and Gulf Coastal Plain, beneath glacial lake clays in the Great Lakes region, and beneath valley-fill alluvium at mountain river crossings.

Recognition during drilling: When drilling into a confined aquifer, water rises rapidly in the borehole and may overflow the top of casing. The drill crew must be instructed to record the overflow rate and borehole water level carefully. An overflowing borehole shows that the artesian head is at least the elevation of the casing top; extend the casing or fit a pressure gauge to measure it.

Equation 2.8-3 — Artesian Excess Pressure:

u_artesian = γ_w × (h_piezometric − z_ground surface) = 62.4 × Δh

Where Δh = height of artesian water above ground surface (ft). Artesian pressure lowers the effective stress in and above the confining layer, and where the uplift equals the weight of the overlying soil it reduces the effective stress to zero (heave or blowout). Flag it immediately to the railroad project manager.

Inputs: where each value comes from (1)
SymbolWhat it isComes fromHow to get itTypical range
Δhheight of artesian water above ground surface (ft)Project geometryFrom project plans, survey and the design layout; layer depths and thicknesses from the boring logs.project-specific