↑ Parent Menu⌂ Main Menu
← Chapter 2.8 Groundwater Characterization and Seepage
GHRM
Railway Ground Hazard Risk Management · 2.0 · The Underworld
Sections · click a car to open it

2.8.14 Construction Dewatering and Track Settlement

Groundwater is the single most consequential subsurface variable in railroad geotechnical engineering.
Authors: Daniel P. Colwell and Mario Ruel
2.8.14 Construction Dewatering and Track Settlement

Excavations for culverts, pump stations, bridge footings and utility crossings next to track often go below the water table. Dewatering keeps the excavation dry and stable, but the drawdown spreads outward, and under the track it raises the effective stress in any soft clay, silt or organic layer that was buoyant before. The track then settles while the pumps run, often unevenly, and pumping can also pull fines out of the subgrade. A first estimate of the inflow, the number of wells and the drawdown at the track belongs in the plan before the railroad is asked for approval. Section 2.8.6 gives the wellpoint yield (Eq. 2.8-19) and Sichardt’s radius of influence (Eq. 2.8-20); this section puts them together for a whole excavation.

2.8.14.1 Method

Equation 2.8-24. Equivalent well and steady inflow

re = √(ab/π);   R = R0 + re, R0 ≈ 5.6s√k;   Unconfined: Q = πk(H² − h²)/ln(R/re);   Confined: Q = 2πkB(H − h)/ln(R/re)

Powers et al. (2007). a, b = plan dimensions of the excavation; s = H − h; k in ft/day; Q in ft³/day (gpm = ft³/day × 7.48/1,440). Suits excavations up to about three times as long as they are wide.

Equation 2.8-25. Sichardt well capacity

qw = 2πrwhw√k / 15  (rw, hw in m, k in m/s, q in m³/s);   English: qw = 2πrwhw√k / (15√0.3048), with k in ft/s

Cashman and Preene (2012). rw = radius of the screen and filter pack; hw = wetted screen length. Number of wells = design flow / qw.

Equation 2.8-26. Drawdown at distance x and settlement under the track

Unconfined: h(x)² = H² − (H² − h²)ln(R/x)/ln(R/re), sx = H − h(x);   Δσ′ ≈ γwsx;   ρ = mvΔσ′Hc

mv from oedometer tests (Chapter 5.2); Hc = thickness of the compressible layer under the track.

2.8.14.2 Worked example

Example 2.8-4: Dewatering a Culvert Excavation Beside Track

A box culvert replacement on a Class I railroad located in Indiana needs an 80 ft by 40 ft excavation in an unconfined sand aquifer. The track centerline is 60 ft from the center of the excavation and sits on 8 ft of soft clay over the sand.

80 × 40 fttrackx = 60 ftH = 40 fth = 22 ftsoft clay 8 ftsx = ?GivenExcavation 80 × 40 ft; k = 30 ft/dayH = 40 ft, h = 22 ft (unconfined)Wells rw 6 in., hw 12 ftTrack 60 ft; clay 8 ft, mv 0.02RequiredInflow Q, number of wellsDrawdown at track sxTrack settlement
Dewatered culvert excavation in an unconfined sand aquifer with the track 60 ft from its center over soft clay.

Given

VariableValueDescription
k30 ft/dayPumping test
H40 ftSaturated thickness before pumping
h22 ftHead required: 2 ft below subgrade
a × b80 ft × 40 ftExcavation
rw, hw6 in.; 12 ftWell radius; wetted screen
Factor on flow1.5Design allowance
x60 ftExcavation center to track
Hc, mv8 ft; 0.02 ft²/kipSoft clay under the track

Required

  • Steady inflow and number of wells
  • Drawdown at the track
  • Settlement of the track

Equations

  1. Eq. 2.8-24: re = √(ab/π); R = 5.6s√k + re
  2. Eq. 2.8-24: Q = πk(H² − h²)/ln(R/re) — unconfined
  3. Eq. 2.8-25: qw = 2πrwhw√k/(15√0.3048) — per well
  4. Eq. 2.8-26: h(x)² = H² − (H² − h²)ln(R/x)/ln(R/re)
  5. Eq. 2.8-26: ρ = mvγwsxHc

Steps

Step 1 · Equivalent radius and R
re = √(3,200/π); s = 18 ft; R0 = 5.6 × 18 × √30
re = 31.9 ft; R0 = 552 ft; R = 584 ft
↓
Step 2 · Inflow
π × 30 × (1,600 − 484) / ln(584/31.9) = 105,180/2.907
Q = 36,180 ft³/day = 188 gpm
Spot check: Halving k halves Q but also shrinks R; the result is not very sensitive to R because it enters through a logarithm (doubling R changes Q by about 20%).
↓
Step 3 · Wells (Eq. 2.8-25)
SI: 2π(0.152)(3.66)√(1.06×10−4)/15 = 0.00240 m³/s; design 1.5 × 188 = 282 gpm
38.1 gpm per well; 282/38.1 → 8 wells at about 30-ft spacing
↓
Step 4 · Drawdown at the track (Eq. 2.8-26)
h² = 1,600 − 1,116 × ln(584/60)/2.907 = 1,600 − 873
h = 26.95 ft; sx = 13.05 ft
↓
Step 5 · Settlement
Δσ′ = 62.4 × 13.05 = 814 psf; 0.02 × 0.814 × 8 ft
ρ = 0.13 ft = 1.6 in.
Spot check: Strain in the clay is 0.02 × 0.814 = 1.6%, reasonable for soft clay under a 0.8-ksf increase.
↓
Solution
About 190 gpm from 8 wells; 13 ft of drawdown and about 1.6 in. of settlement at the track.

Solution

Eight wells of about 38 gpm each will hold the water 2 ft below subgrade, but the drawdown reaches about 13 ft under the track and would settle it about 1.6 in.

That is too much to leave to routine surfacing. Options are a cutoff (sheet piles or a slurry wall) around the excavation to the clay or a deeper low-permeability layer, recharge wells between the excavation and the track, or a shorter pumping period with the track monitored daily and surfaced as needed. Whichever is chosen, set settlement trigger levels with the railroad and filter the discharge so the wells do not pump fines.

Open the dewatering calculator →
Equivalent well radius, Sichardt radius of influence, steady inflow for unconfined or confined aquifers, the number of wells from the Sichardt capacity, the drawdown profile to the track and the settlement it causes.

2.8.14.3 Sources

The summaries above are paraphrased in original wording; equations and tabulated values are standard or published. Individual railroads, clients, companies and projects are not named.

  • J.P. Powers, A.B. Corwin, P.C. Schmall and W.E. Kaeck (2007), Construction Dewatering and Groundwater Control, 3rd ed., Wiley: equivalent-well method, radius of influence.Find source ↗
  • P.M. Cashman and M. Preene (2012), Groundwater Lowering in Construction, 2nd ed., CRC Press: Sichardt well capacity; settlement caused by drawdown.Find source ↗
  • Section 2.8.6 of this chapter: Eqs. 2.8-19 and 2.8-20.Find source ↗
← Previous · 2.0 The Underworld Chapter 2.7 — Rock and Sand: Properties, Typical Values and Behavior
Next · 2.0 The Underworld → Chapter 2.9 — Collapsible Soils: Identification, Testing and Railroad Impacts