2.2.11 Practical Recommendations

Consistent, reproducible classification of soil and rock is the common language shared between field personnel, laboratory technicians, design engineers, and railroad…
Authors: Daniel P. Colwell and Mario Ruel
2.2.11 Practical Recommendations
  1. Require lab-verified USCS classification for all design samples on Class I railroad projects. Field-estimated classifications are acceptable for preliminary boring logs but must be superseded by lab results before any analysis. Submit revised boring logs with laboratory USCS symbols once testing is complete.
  2. Use dual USCS symbols for borderline coarse-grained soils (5–12% fines) and borderline fine-grained soils (PI between 4 and 7, near A-line). ASTM D2487 requires the dual symbol (e.g., CL-ML, SW-SM) in these zones; it is not optional.
  3. Flag A-7-6 soils and GI ≥ 12 immediately upon receipt of lab results on Class I railroad projects. Check whether these values trigger a ground improvement evaluation under the owner railroad's standards. Early flagging allows the project team to add CBR testing (Chapter 7.3) to the lab program before samples are discarded.
  4. Record Activity for all CH soils encountered on Class I railroad projects. Activity > 1.25 requires swell testing per ASTM D4546, and the swell pressure must be documented in the geotechnical data report (Chapter 8.4). Neglecting swell characterization on active clay subgrades leads to recurring track geometry defects.
  5. Include frost susceptibility classification on all Class I railroad projects north of 45°N latitude. Determine FS class from grain-size data (% finer than 0.02 mm) and report alongside the USCS symbol in boring logs.
  6. Provide RMR, GSI, and Q values in tabular format in the geotechnical data report for all Class I railroad rock projects. These values must be cross-referenced to the core run depth and boring ID and supported by photographs of the core box. Report the individual RMR parameter ratings with their justification, not just the final summed score.
  7. Recalibrate hydrometer analysis for local specific gravity on short-line Gulf Coast projects. Gulf Coast soils frequently contain shell fragments and organic matter with G_s values outside the standard 2.65–2.72 range. Use measured G_s (ASTM D854) to correct hydrometer data; failure to do so can shift the reported fines and clay-size fractions.
Empirical equation note · this section

Values from these correlations are estimates, not test results. State the equation ID and source when one is used, confirm the soil or rock is within its range, and calibrate against site testing before design.

  • RK-01 Rock Mass Rating (RMR₈₉) RMRUse: Jointed rock masses; tunnels, foundations; slopes via SMR (RK-06). Limits: Mixed versions (1976 vs 1989) give different values; state which is used.
  • RK-05 GSI from RMR₈₉ GSIUse: Good-quality rock masses, RMR89' > 23. Limits: Not valid for poor rock (RMR89' < 23); estimate GSI directly from the GSI chart instead.