3.7.14 State Cost Database for Geotechnical Design and Construction

Estimating the cost of exploration, testing, engineering and stabilization, and checking that the number will hold.
Author: Daniel P. Colwell
3.7.14 State Cost Database for Geotechnical Design and Construction

Sections 3.7.2 to 3.7.8 explain how an estimate is built; this section supplies the unit costs. The database holds 168 geotechnical cost items in 2026 dollars, from drilling footage and laboratory tests through soldier pile walls, rock bolts and wick drains, with a low, typical and high value for each. Each state gets its own price for every item. Where a state DOT or a state contract has published a price, that price is used. Elsewhere the national value is scaled by a location factor for the state.

Use the database the way an experienced estimator uses a bid history: to size a budget before quotes exist, to check a subcontractor's quote line by line, and to show a client how much the same scope costs in a different state. It does not replace quotes. Railroad work in particular tends to price above highway averages, because flagging, work windows and access from the track add time that a highway contractor does not carry.

3.7.14.1 Method

Equation 3.7-3. Unit cost of an item in a state

Cs = CDOT,s where a published state price exists; otherwise Cs = Cnat × Fs

Equation 3.7-4. Estimate total

Total = [Σ(Q × Cs)design + Σ(Q × Cs)construction × (1 + m)] × (1 + c) × (1 + e)n

Cnat = national typical unit cost; Fs = state location factor (1.00 = national average); Q = quantity; m = mobilization as a fraction of construction; c = contingency; e = annual escalation; n = years from 2026 to the midpoint of the work.

Three groups are not adjusted by F: laboratory tests, engineering labor and travel. Their rates follow the firm and the laboratory, not the site, and samples are shipped. Railroad flagging is not adjusted either, because each railroad sets its own rate. The low and high values are the national range times F. Where a published state price falls outside that range, the range is widened to include it.

The location factors are area cost factors developed for building construction. They capture the labor and equipment markets that drive most geotechnical costs. They are not meant to be applied to unit prices, which is why a published state price always takes precedence. Hawaii and Alaska factors (above 2.0) reflect remote building work; check them against local quotes before using them.

3.7.14.2 What the database holds

Every item carries a basis code that tells the user how much to trust it. DOT means a statewide average of recent bid prices. FEE means a published fee schedule or a state drilling contract. LAB means a 2026 regional laboratory fee schedule, with a range of 0.75 to 1.35 times the listed rate. HIST means older bid data escalated to 2026 with the FHWA National Highway Construction Cost Index, which doubled between 2003 and 2021 and has risen more than half again since. EST means a planning value compiled for this manual. Replace EST values with local quotes first.

Table 3.7-9. Contents of the cost database (168 items)
PhaseGroupItemsExamplesBasis (count)
DesignDrilling and sampling19Mobilization, HSA and mud-rotary footage, coring, tubes, rig day rateEST 4, FEE 15
DesignIn situ testing and geophysics19CPTu, DMT, dissipation, vane, MASW, ERT, GPR, piezometersEST 7, FEE 5, LAB 7
DesignLaboratory testing34Moisture, Atterberg, gradation, consolidation, triaxial, rock UCS, corrosivity, aggregate durabilityLAB 34
DesignEngineering labor (billing rates)8Principal through administrativeEST 8
DesignSite access, safety and field expenses10Flagging, right-of-entry, insurance, locates, travelEST 10
ConstructionEarthwork, undercut and fill10Excavation, rock, undercut, borrow, embankment, haul, wasteDOT 7, EST 3
ConstructionTrack substructure and aggregates4Ballast, subballast, track undercutting, HMA underlaymentDOT 1, EST 3
ConstructionGeosynthetics6Separation and stabilization geotextile, geogrid, geocellDOT 3, EST 3
ConstructionDrainage and erosion protection11Riprap, filter blanket, gabions, underdrains, horizontal drainsDOT 6, EST 4, HIST 1
ConstructionDeep foundations12Drilled shafts, H-piles, micropiles, load testsDOT 7, EST 5
ConstructionRetaining structures12Soldier pile walls, tiebacks, sheet piles, CIP, MSE, soil nailsDOT 2, EST 6, HIST 4
ConstructionSlope and rock stabilization9Scaling, rock bolts, drapery, barriers, buttresses, reinforced slopesEST 7, HIST 2
ConstructionGround improvement10Wick drains, surcharge, lime/cement, mass mixing, stone columns, groutingDOT 3, EST 7
ConstructionGeneral conditions4Mobilization, flagging, survey, instrument readingsEST 4

3.7.14.3 State location factors

Table 3.7-10. State location factors F (1.00 = national average) and number of published state prices in the database
StateFPricesStateFPricesStateFPrices
Alabama0.86Kentucky0.87North Dakota1.17
Alaska2.282Louisiana0.93Ohio0.98
Arizona0.89Maine1.112Oklahoma0.891
Arkansas0.8613Maryland1.01Oregon1.13
California1.24Massachusetts1.18Pennsylvania1.06
Colorado1.06Michigan1.03Rhode Island1.16
Connecticut1.10Minnesota1.112South Carolina0.95
Delaware1.09Mississippi0.83South Dakota0.98
District of Columbia1.04Missouri0.96Tennessee0.8712
Florida0.96Montana1.04Texas0.82
Georgia0.88Nebraska0.98Utah0.99
Hawaii2.15Nevada1.16Vermont1.03
Idaho1.04New Hampshire1.06Virginia0.885
Illinois1.01New Jersey1.18Washington1.104
Indiana0.92New Mexico0.90West Virginia0.9713
Iowa0.98New York1.07Wisconsin1.07
Kansas0.92North Carolina0.85Wyoming0.98

3.7.14.4 Published state prices

The database starts with the published prices below. They come from state DOT average-price reports, a statewide geotechnical drilling bid, a state drilling services contract, a state maximum-cost drilling rule and a published CPT fee schedule. Add to them from the average bid price reports most DOTs publish each year. Look at the quantity behind each average: a price on a few hundred feet of horizontal drains or 18 cy of gabions says little about a large job. Statewide averages also mix mass-grading jobs with small repairs. A low unclassified-excavation average (under $5/cy in one state) reflects large balanced cuts, not a railroad slide repair.

Table 3.7-11. Published state prices loaded so far (54 values, 9 states)
StateItemUnitPriceYearPay item / note
AlaskaGeotextile, separationSY$2.352025Geotextile Type A separation, 501-10,000 SY
AlaskaRiprap, by weightTON$221.422025Riprap Class III, 1-100 ton
ArkansasUnclassified excavation (common)CY$17.122025Item 210 unclassified excavation, 502,489 CY
ArkansasCompacted embankmentCY$20.062025Item 210 compacted embankment
ArkansasSelect granular backfillCY$50.522025Item 210 select granular backfill
ArkansasSubballast / aggregate base courseTON$41.042025Item 303 aggregate base course Class 7
ArkansasRiprap, dumpedCY$129.022025Item 816 dumped riprap
ArkansasRiprap, by weightTON$57.372025Item 816 foundation protection riprap
ArkansasFilter blanket (bedding stone)SY$9.862025Item 816 filter blanket
ArkansasUnderdrain, 4-6 in. perforated pipe with stoneLF$19.762025Item 611 4 in. pipe underdrains
ArkansasSteel H-pile HP12x53, furnished and drivenLF$135.002025Item 805 steel piling HP12x53 (388 LF)
ArkansasSteel H-pile HP14x73, furnished and drivenLF$147.072025Item 805 steel piling HP14x73
ArkansasDynamic pile load test (PDA)EA$10,0002025Item 805 dynamic pile load test
ArkansasLime or cement stabilized subgrade, processingSY$7.212025Item 308 processing cement-stabilized base
ArkansasCement for stabilizationTON$233.912025Item 307 cement in full-depth reclaimed base
MaineDrill rig mobilization, truck rig (within 100 mi)EA$550.002025Mobilization (land)
MaineDrill rig and crew, day rate (standby, clearing, extra work)DAY$2,5502025Drill rig (land), per day
MinnesotaHollow-stem auger boring with SPT at 5-ft intervals, 0-50 ftLF$35.002022Hollow-stem auger, per foot beyond 25 ft
MinnesotaMobilization beyond 50 mi, per mile one wayMI$9.002022Mobilization per mile over 50 mi
OklahomaUnclassified excavation (common)CY$10.802025202(A) unclassified excavation, all regions
TennesseeUnclassified excavation (common)CY$14.812024203-01 road and drainage excavation (unclassified)
TennesseeUndercut and removal of unsuitable materialCY$10.552024203-05 undercutting
TennesseeBorrow excavation, commonCY$19.472024203-03 borrow excavation (unclassified)
TennesseeSelect borrow / select fillCY$27.912024203-03.01 borrow excavation (select material)
TennesseeSubballast / aggregate base courseTON$37.352024303-01 mineral aggregate Type A base, Grading D
TennesseeDrilled shaft, 48-72 in., in soilLF$1,0532024625-02.01 drilled shaft, soil (per VF)
TennesseeDrilled shaft, rock socketLF$2,4322024625-02.13 drilled shaft, rock (per VF)
TennesseeDrilled shaft permanent casingLF$1,5202024625-02.25 permanent casing (per VF)
TennesseeDrilled shaft integrity (CSL or thermal) / camera inspectionEA$1,7862024625-01.11 camera inspection, wet shaft
TennesseeHorizontal drain, drilledLF$13.502024610-12.02 horizontal drains (338 LF only)
TennesseeSteel sheet piling, temporarySF$32.442024606-24.12 temporary sheet piles
TennesseeCast-in-place concrete retaining wall (wall face)SF$173.812024604-07 retaining wall items, quantity-weighted (12 items, 107,995 SF)
VirginiaCPT rig mobilizationEA$1,2002026Truck rig mobilization
VirginiaPiezocone sounding (CPTu)LF$17.502026CPTu geotechnical sounding, per ft
VirginiaPore pressure dissipation testEA$400.002026Pore pressure dissipation test
VirginiaFlat dilatometer (DMT) soundingLF$30.002026DMT at 20-cm intervals, per ft
VirginiaSeismic cone shear-wave test (per depth)EA$50.002026Seismic test at 1.0-m intervals
WashingtonHollow-stem auger boring with SPT at 5-ft intervals, 0-50 ftLF$75.002022Hollow-stem auger with SPT every 5 ft, 0-50 ft
WashingtonMud rotary boring with SPT, 0-50 ftLF$75.002022Mud rotary 0-50 ft
WashingtonRock coring, NQ or HQ, with core boxesLF$150.002022Rock coring and sampling 0-50 ft
WashingtonCasing advance (over water, cobbles, fill)LF$150.002022Casing advance 0-50 ft
West VirginiaUnclassified excavation (common)CY$4.672025207001-001 unclassified excavation; mass grading jobs pull the average down
West VirginiaBorrow excavation, commonCY$45.272025211001-000 unclassified borrow excavation
West VirginiaRock excavationCY$71.042025211002-000 rock borrow excavation (CY)
West VirginiaSelect borrow / select fillCY$125.242025211003-000 select borrow (851 CY)
West VirginiaPrefabricated vertical (wick) drainsLF$1.252025206001-001 prefabricated wick drains
West VirginiaSubballast / aggregate base courseTON$53.122025307005-001 aggregate base course, stone or gravel (ton)
West VirginiaRiprap, dumpedCY$151.962025218001-000 riprap
West VirginiaGeotextile, subsurface drainage / filterSY$1.402025207032-000 fabric for subsurface drainage
West VirginiaGeotextile, subgrade stabilizationSY$2.002025207033-000 fabric for subgrade stabilization
West VirginiaGeotextile, separationSY$2.392025207034-000 fabric for separation
West VirginiaGabionCY$712.912025218003-000 gabion (18 CY)
West VirginiaUnderdrain, 4-6 in. perforated pipe with stoneLF$21.822025606025-002 4 in. underdrain pipe
West VirginiaAggregate-filled fabric underdrain / french drainLF$49.322025606020-001 aggregate-filled fabric underdrain

3.7.14.5 Worked example

Example 3.7-2: Pricing a Toe Wall Repair in Two States

A slip at the toe of a track embankment is to be repaired with a cantilever soldier pile and lagging wall, 120 ft long with 14 ft exposed, after the soft toe soil is undercut and replaced with select granular backfill on a separation geotextile. An underdrain runs behind the wall and riprap protects the ditch. The same repair is needed at two sites on a Class I railroad, one located in Tennessee and one located in Pennsylvania. The client wants a budget for each before it releases design.

track Aw = 1,680 sf (120 ft × 14 ft) Vu = Vb = 600 cy Ld = 240 lf, Ag = 900 sy Vr = 150 cy ? Cost in TN and PA Given Quantities Aw, Vu, Vb, Ag, Vr, Ld Flagging Nf = 20 days FTN = 0.87, FPA = 1.06 m = 7%, c = 20%, e = 3%/yr, n = 1 Required ? Construction cost in each state ? Low-high bounds ? Difference between the states black = given · red ? = required
Toe wall repair: wall, undercut and backfill, underdrain and ditch riprap.

Given

VariableValueDescription
Aw1,680 sfSoldier pile and lagging wall face
Vu600 cyUndercut unsuitable toe soil
Vb600 cySelect granular backfill
Ag900 sySeparation geotextile
Vr150 cyRiprap at the ditch
Ld240 lfUnderdrain behind the wall
Nf20 daysRailroad flagging
FTN, FPA0.87; 1.06State location factors (Table 3.7-10)
m, c7%; 20%Mobilization (construction only); contingency
e, n3% per year; 1 yrEscalation to the midpoint of construction

Required

  • Construction cost in each state, with mobilization, contingency and escalation
  • Low and high bounds
  • How much the location changes the budget

Equations

  1. Eq. 3.7-3: Cs = CDOT,s if published; else Cnat × Fs
  2. Eq. 3.7-4: Total = [Σ(Q Cs)design + Σ(Q Cs)constr(1 + m)](1 + c)(1 + e)n

Steps

Step 1 · Unit cost of each item in each state
Uses Eq. 3.7-3 and Table 3.7-11
Tennessee has a published undercut price ($10.55/cy, 2024), so it is used directly. Every other item is national typical × F; flagging is not adjusted.
See Table 3.7-12
Spot check: wall in PA: $110 × 1.06 = $116.60/sf; 1,680 × $116.60 = $195,888.
↓
Step 2 · Construction subtotal
Σ Q × Cs
TN: $240,722; PA: $291,788
↓
Step 3 · Mobilization
0.07 × construction
TN: $16,851; PA: $20,425
Spot check: 0.07 × $240,722 = $16,851.
↓
Step 4 · Contingency and escalation
Uses Eq. 3.7-4
(subtotal) × 1.20 × 1.031
TN: $257,573 × 1.236 = $318,360; PA: $312,213 × 1.236 = $385,895
Spot check: 1.20 × 1.03 = 1.236.
↓
Step 5 · Bounds
Repeat Steps 2-4 with every item at its low, then its high value
TN: $189,927 to $533,966; PA: $225,628 to $640,182
↓
Solution
About $318,000 in Tennessee and $386,000 in Pennsylvania; the PA job costs about 21% more.
Table 3.7-12. Example 3.7-2 line items, Tennessee and Pennsylvania
ItemQtyUnitUnit cost basisUnit costCost
Tennessee
Soldier pile and lagging wall face1,680SF$110 × 0.87$96$160,776
Undercut unsuitable toe soil600CYpublished TN price (2024)$11$6,330
Select granular backfill600CY$50 × 0.87$44$26,100
Separation geotextile900SY$2.50 × 0.87$2.17$1,957
Riprap at the ditch150CY$130 × 0.87$113$16,965
Underdrain behind the wall240LF$22 × 0.87$19$4,594
Railroad flagging20DAYnot location-adjusted$1,200$24,000
Pennsylvania
Soldier pile and lagging wall face1,680SF$110 × 1.06$117$195,888
Undercut unsuitable toe soil600CY$18 × 1.06$19$11,448
Select granular backfill600CY$50 × 1.06$53$31,800
Separation geotextile900SY$2.50 × 1.06$2.65$2,385
Riprap at the ditch150CY$130 × 1.06$138$20,670
Underdrain behind the wall240LF$22 × 1.06$23$5,597
Railroad flagging20DAYnot location-adjusted$1,200$24,000

Solution

Budget about $318,000 for the Tennessee site and $386,000 for the Pennsylvania site.

The wall is about 67% of the construction cost in both states, so the location factor on that one item drives most of the difference. Flagging is the same in both because the railroad sets the rate. Report the range ($190,000 to $534,000 in TN) with the typical figure until the wall is designed: pile size and embedment can move the wall unit cost by half in either direction. When the drilling and wall contractors quote, replace the database values with the quotes. The Estimate sheet of the Excel master is set up with these quantities and reproduces the PA total.

Open the state cost database and estimator → Download the Excel master
Pick a state, filter the items, enter quantities and get low, typical and high totals with mobilization, contingency and escalation, plus the same estimate in every state. The Excel master holds the same data with live formulas, so new state prices can be added as they are collected.

3.7.14.6 Keeping the database current

Treat the database as a living bid history. When a quote or bid comes in, add it to the State Prices sheet of the Excel master with its year and quantity, and it replaces national × F for that state. Escalate all values each year with the change in the NHCCI or the state's own cost index (Section 3.7.8). Review EST items against actual quotes at least once a year, and retire any published price older than about five years.

3.7.14.7 Sources

Unit costs are compiled from the public sources below; the summaries are in original wording. Individual railroads, clients, companies and projects are not named.

  • Arkansas Department of Transportation, Weighted Average Unit Prices, 1/15/2025 to 11/5/2025.Find source ↗
  • Tennessee Department of Transportation, Average Unit Prices, Awarded Contracts, January to December 2024.Find source ↗
  • West Virginia Division of Highways, Average Unit Bid Prices, 2025.Find source ↗
  • Oklahoma Department of Transportation, Weighted Average Item Price Report, January 2024 to June 2025.Find source ↗
  • Maine Department of Transportation, statewide geotechnical drilling bid tabulation, 2025.Find source ↗
  • Washington state drilling services contract price sheet, 2022; Minnesota Rules 2890.3100 and 2890.3300 (2022), maximum drilling costs.Find source ↗
  • A published CPT and DMT fee schedule, 2026; a county drilling fee schedule; a municipal average bid tabulation, 2025.Find source ↗
  • Geo-Institute, GeoTechTools technology cost pages: drilled and grouted soil nails; rock slope stabilization; prefabricated vertical drains.Find source ↗
  • Federal Highway Administration, National Highway Construction Cost Index (NHCCI).Find source ↗
  • Department of Defense, UFS 3-701-01, DoD Facilities Pricing Guide (2026), Table 4-1 area cost factors.Find source ↗
← Previous · 3.0 Risk Management Chapter 3.6 — Site Accessibility Study
Next · 3.0 Risk Management → Chapter 3.8 — Risk Ratings and Ground Hazard Risk Assessment