Sections 3.7.2 to 3.7.8 explain how an estimate is built; this section supplies the unit costs. The database holds 168 geotechnical cost items in 2026 dollars, from drilling footage and laboratory tests through soldier pile walls, rock bolts and wick drains, with a low, typical and high value for each. Each state gets its own price for every item. Where a state DOT or a state contract has published a price, that price is used. Elsewhere the national value is scaled by a location factor for the state.
Use the database the way an experienced estimator uses a bid history: to size a budget before quotes exist, to check a subcontractor's quote line by line, and to show a client how much the same scope costs in a different state. It does not replace quotes. Railroad work in particular tends to price above highway averages, because flagging, work windows and access from the track add time that a highway contractor does not carry.
Equation 3.7-3. Unit cost of an item in a state
Equation 3.7-4. Estimate total
Cnat = national typical unit cost; Fs = state location factor (1.00 = national average); Q = quantity; m = mobilization as a fraction of construction; c = contingency; e = annual escalation; n = years from 2026 to the midpoint of the work.
Three groups are not adjusted by F: laboratory tests, engineering labor and travel. Their rates follow the firm and the laboratory, not the site, and samples are shipped. Railroad flagging is not adjusted either, because each railroad sets its own rate. The low and high values are the national range times F. Where a published state price falls outside that range, the range is widened to include it.
The location factors are area cost factors developed for building construction. They capture the labor and equipment markets that drive most geotechnical costs. They are not meant to be applied to unit prices, which is why a published state price always takes precedence. Hawaii and Alaska factors (above 2.0) reflect remote building work; check them against local quotes before using them.
Every item carries a basis code that tells the user how much to trust it. DOT means a statewide average of recent bid prices. FEE means a published fee schedule or a state drilling contract. LAB means a 2026 regional laboratory fee schedule, with a range of 0.75 to 1.35 times the listed rate. HIST means older bid data escalated to 2026 with the FHWA National Highway Construction Cost Index, which doubled between 2003 and 2021 and has risen more than half again since. EST means a planning value compiled for this manual. Replace EST values with local quotes first.
| Phase | Group | Items | Examples | Basis (count) |
|---|---|---|---|---|
| Design | Drilling and sampling | 19 | Mobilization, HSA and mud-rotary footage, coring, tubes, rig day rate | EST 4, FEE 15 |
| Design | In situ testing and geophysics | 19 | CPTu, DMT, dissipation, vane, MASW, ERT, GPR, piezometers | EST 7, FEE 5, LAB 7 |
| Design | Laboratory testing | 34 | Moisture, Atterberg, gradation, consolidation, triaxial, rock UCS, corrosivity, aggregate durability | LAB 34 |
| Design | Engineering labor (billing rates) | 8 | Principal through administrative | EST 8 |
| Design | Site access, safety and field expenses | 10 | Flagging, right-of-entry, insurance, locates, travel | EST 10 |
| Construction | Earthwork, undercut and fill | 10 | Excavation, rock, undercut, borrow, embankment, haul, waste | DOT 7, EST 3 |
| Construction | Track substructure and aggregates | 4 | Ballast, subballast, track undercutting, HMA underlayment | DOT 1, EST 3 |
| Construction | Geosynthetics | 6 | Separation and stabilization geotextile, geogrid, geocell | DOT 3, EST 3 |
| Construction | Drainage and erosion protection | 11 | Riprap, filter blanket, gabions, underdrains, horizontal drains | DOT 6, EST 4, HIST 1 |
| Construction | Deep foundations | 12 | Drilled shafts, H-piles, micropiles, load tests | DOT 7, EST 5 |
| Construction | Retaining structures | 12 | Soldier pile walls, tiebacks, sheet piles, CIP, MSE, soil nails | DOT 2, EST 6, HIST 4 |
| Construction | Slope and rock stabilization | 9 | Scaling, rock bolts, drapery, barriers, buttresses, reinforced slopes | EST 7, HIST 2 |
| Construction | Ground improvement | 10 | Wick drains, surcharge, lime/cement, mass mixing, stone columns, grouting | DOT 3, EST 7 |
| Construction | General conditions | 4 | Mobilization, flagging, survey, instrument readings | EST 4 |
| State | F | Prices | State | F | Prices | State | F | Prices |
|---|---|---|---|---|---|---|---|---|
| Alabama | 0.86 | Kentucky | 0.87 | North Dakota | 1.17 | |||
| Alaska | 2.28 | 2 | Louisiana | 0.93 | Ohio | 0.98 | ||
| Arizona | 0.89 | Maine | 1.11 | 2 | Oklahoma | 0.89 | 1 | |
| Arkansas | 0.86 | 13 | Maryland | 1.01 | Oregon | 1.13 | ||
| California | 1.24 | Massachusetts | 1.18 | Pennsylvania | 1.06 | |||
| Colorado | 1.06 | Michigan | 1.03 | Rhode Island | 1.16 | |||
| Connecticut | 1.10 | Minnesota | 1.11 | 2 | South Carolina | 0.95 | ||
| Delaware | 1.09 | Mississippi | 0.83 | South Dakota | 0.98 | |||
| District of Columbia | 1.04 | Missouri | 0.96 | Tennessee | 0.87 | 12 | ||
| Florida | 0.96 | Montana | 1.04 | Texas | 0.82 | |||
| Georgia | 0.88 | Nebraska | 0.98 | Utah | 0.99 | |||
| Hawaii | 2.15 | Nevada | 1.16 | Vermont | 1.03 | |||
| Idaho | 1.04 | New Hampshire | 1.06 | Virginia | 0.88 | 5 | ||
| Illinois | 1.01 | New Jersey | 1.18 | Washington | 1.10 | 4 | ||
| Indiana | 0.92 | New Mexico | 0.90 | West Virginia | 0.97 | 13 | ||
| Iowa | 0.98 | New York | 1.07 | Wisconsin | 1.07 | |||
| Kansas | 0.92 | North Carolina | 0.85 | Wyoming | 0.98 |
The database starts with the published prices below. They come from state DOT average-price reports, a statewide geotechnical drilling bid, a state drilling services contract, a state maximum-cost drilling rule and a published CPT fee schedule. Add to them from the average bid price reports most DOTs publish each year. Look at the quantity behind each average: a price on a few hundred feet of horizontal drains or 18 cy of gabions says little about a large job. Statewide averages also mix mass-grading jobs with small repairs. A low unclassified-excavation average (under $5/cy in one state) reflects large balanced cuts, not a railroad slide repair.
| State | Item | Unit | Price | Year | Pay item / note |
|---|---|---|---|---|---|
| Alaska | Geotextile, separation | SY | $2.35 | 2025 | Geotextile Type A separation, 501-10,000 SY |
| Alaska | Riprap, by weight | TON | $221.42 | 2025 | Riprap Class III, 1-100 ton |
| Arkansas | Unclassified excavation (common) | CY | $17.12 | 2025 | Item 210 unclassified excavation, 502,489 CY |
| Arkansas | Compacted embankment | CY | $20.06 | 2025 | Item 210 compacted embankment |
| Arkansas | Select granular backfill | CY | $50.52 | 2025 | Item 210 select granular backfill |
| Arkansas | Subballast / aggregate base course | TON | $41.04 | 2025 | Item 303 aggregate base course Class 7 |
| Arkansas | Riprap, dumped | CY | $129.02 | 2025 | Item 816 dumped riprap |
| Arkansas | Riprap, by weight | TON | $57.37 | 2025 | Item 816 foundation protection riprap |
| Arkansas | Filter blanket (bedding stone) | SY | $9.86 | 2025 | Item 816 filter blanket |
| Arkansas | Underdrain, 4-6 in. perforated pipe with stone | LF | $19.76 | 2025 | Item 611 4 in. pipe underdrains |
| Arkansas | Steel H-pile HP12x53, furnished and driven | LF | $135.00 | 2025 | Item 805 steel piling HP12x53 (388 LF) |
| Arkansas | Steel H-pile HP14x73, furnished and driven | LF | $147.07 | 2025 | Item 805 steel piling HP14x73 |
| Arkansas | Dynamic pile load test (PDA) | EA | $10,000 | 2025 | Item 805 dynamic pile load test |
| Arkansas | Lime or cement stabilized subgrade, processing | SY | $7.21 | 2025 | Item 308 processing cement-stabilized base |
| Arkansas | Cement for stabilization | TON | $233.91 | 2025 | Item 307 cement in full-depth reclaimed base |
| Maine | Drill rig mobilization, truck rig (within 100 mi) | EA | $550.00 | 2025 | Mobilization (land) |
| Maine | Drill rig and crew, day rate (standby, clearing, extra work) | DAY | $2,550 | 2025 | Drill rig (land), per day |
| Minnesota | Hollow-stem auger boring with SPT at 5-ft intervals, 0-50 ft | LF | $35.00 | 2022 | Hollow-stem auger, per foot beyond 25 ft |
| Minnesota | Mobilization beyond 50 mi, per mile one way | MI | $9.00 | 2022 | Mobilization per mile over 50 mi |
| Oklahoma | Unclassified excavation (common) | CY | $10.80 | 2025 | 202(A) unclassified excavation, all regions |
| Tennessee | Unclassified excavation (common) | CY | $14.81 | 2024 | 203-01 road and drainage excavation (unclassified) |
| Tennessee | Undercut and removal of unsuitable material | CY | $10.55 | 2024 | 203-05 undercutting |
| Tennessee | Borrow excavation, common | CY | $19.47 | 2024 | 203-03 borrow excavation (unclassified) |
| Tennessee | Select borrow / select fill | CY | $27.91 | 2024 | 203-03.01 borrow excavation (select material) |
| Tennessee | Subballast / aggregate base course | TON | $37.35 | 2024 | 303-01 mineral aggregate Type A base, Grading D |
| Tennessee | Drilled shaft, 48-72 in., in soil | LF | $1,053 | 2024 | 625-02.01 drilled shaft, soil (per VF) |
| Tennessee | Drilled shaft, rock socket | LF | $2,432 | 2024 | 625-02.13 drilled shaft, rock (per VF) |
| Tennessee | Drilled shaft permanent casing | LF | $1,520 | 2024 | 625-02.25 permanent casing (per VF) |
| Tennessee | Drilled shaft integrity (CSL or thermal) / camera inspection | EA | $1,786 | 2024 | 625-01.11 camera inspection, wet shaft |
| Tennessee | Horizontal drain, drilled | LF | $13.50 | 2024 | 610-12.02 horizontal drains (338 LF only) |
| Tennessee | Steel sheet piling, temporary | SF | $32.44 | 2024 | 606-24.12 temporary sheet piles |
| Tennessee | Cast-in-place concrete retaining wall (wall face) | SF | $173.81 | 2024 | 604-07 retaining wall items, quantity-weighted (12 items, 107,995 SF) |
| Virginia | CPT rig mobilization | EA | $1,200 | 2026 | Truck rig mobilization |
| Virginia | Piezocone sounding (CPTu) | LF | $17.50 | 2026 | CPTu geotechnical sounding, per ft |
| Virginia | Pore pressure dissipation test | EA | $400.00 | 2026 | Pore pressure dissipation test |
| Virginia | Flat dilatometer (DMT) sounding | LF | $30.00 | 2026 | DMT at 20-cm intervals, per ft |
| Virginia | Seismic cone shear-wave test (per depth) | EA | $50.00 | 2026 | Seismic test at 1.0-m intervals |
| Washington | Hollow-stem auger boring with SPT at 5-ft intervals, 0-50 ft | LF | $75.00 | 2022 | Hollow-stem auger with SPT every 5 ft, 0-50 ft |
| Washington | Mud rotary boring with SPT, 0-50 ft | LF | $75.00 | 2022 | Mud rotary 0-50 ft |
| Washington | Rock coring, NQ or HQ, with core boxes | LF | $150.00 | 2022 | Rock coring and sampling 0-50 ft |
| Washington | Casing advance (over water, cobbles, fill) | LF | $150.00 | 2022 | Casing advance 0-50 ft |
| West Virginia | Unclassified excavation (common) | CY | $4.67 | 2025 | 207001-001 unclassified excavation; mass grading jobs pull the average down |
| West Virginia | Borrow excavation, common | CY | $45.27 | 2025 | 211001-000 unclassified borrow excavation |
| West Virginia | Rock excavation | CY | $71.04 | 2025 | 211002-000 rock borrow excavation (CY) |
| West Virginia | Select borrow / select fill | CY | $125.24 | 2025 | 211003-000 select borrow (851 CY) |
| West Virginia | Prefabricated vertical (wick) drains | LF | $1.25 | 2025 | 206001-001 prefabricated wick drains |
| West Virginia | Subballast / aggregate base course | TON | $53.12 | 2025 | 307005-001 aggregate base course, stone or gravel (ton) |
| West Virginia | Riprap, dumped | CY | $151.96 | 2025 | 218001-000 riprap |
| West Virginia | Geotextile, subsurface drainage / filter | SY | $1.40 | 2025 | 207032-000 fabric for subsurface drainage |
| West Virginia | Geotextile, subgrade stabilization | SY | $2.00 | 2025 | 207033-000 fabric for subgrade stabilization |
| West Virginia | Geotextile, separation | SY | $2.39 | 2025 | 207034-000 fabric for separation |
| West Virginia | Gabion | CY | $712.91 | 2025 | 218003-000 gabion (18 CY) |
| West Virginia | Underdrain, 4-6 in. perforated pipe with stone | LF | $21.82 | 2025 | 606025-002 4 in. underdrain pipe |
| West Virginia | Aggregate-filled fabric underdrain / french drain | LF | $49.32 | 2025 | 606020-001 aggregate-filled fabric underdrain |
A slip at the toe of a track embankment is to be repaired with a cantilever soldier pile and lagging wall, 120 ft long with 14 ft exposed, after the soft toe soil is undercut and replaced with select granular backfill on a separation geotextile. An underdrain runs behind the wall and riprap protects the ditch. The same repair is needed at two sites on a Class I railroad, one located in Tennessee and one located in Pennsylvania. The client wants a budget for each before it releases design.
| Variable | Value | Description |
|---|---|---|
| Aw | 1,680 sf | Soldier pile and lagging wall face |
| Vu | 600 cy | Undercut unsuitable toe soil |
| Vb | 600 cy | Select granular backfill |
| Ag | 900 sy | Separation geotextile |
| Vr | 150 cy | Riprap at the ditch |
| Ld | 240 lf | Underdrain behind the wall |
| Nf | 20 days | Railroad flagging |
| FTN, FPA | 0.87; 1.06 | State location factors (Table 3.7-10) |
| m, c | 7%; 20% | Mobilization (construction only); contingency |
| e, n | 3% per year; 1 yr | Escalation to the midpoint of construction |
| Item | Qty | Unit | Unit cost basis | Unit cost | Cost |
|---|---|---|---|---|---|
| Tennessee | |||||
| Soldier pile and lagging wall face | 1,680 | SF | $110 × 0.87 | $96 | $160,776 |
| Undercut unsuitable toe soil | 600 | CY | published TN price (2024) | $11 | $6,330 |
| Select granular backfill | 600 | CY | $50 × 0.87 | $44 | $26,100 |
| Separation geotextile | 900 | SY | $2.50 × 0.87 | $2.17 | $1,957 |
| Riprap at the ditch | 150 | CY | $130 × 0.87 | $113 | $16,965 |
| Underdrain behind the wall | 240 | LF | $22 × 0.87 | $19 | $4,594 |
| Railroad flagging | 20 | DAY | not location-adjusted | $1,200 | $24,000 |
| Pennsylvania | |||||
| Soldier pile and lagging wall face | 1,680 | SF | $110 × 1.06 | $117 | $195,888 |
| Undercut unsuitable toe soil | 600 | CY | $18 × 1.06 | $19 | $11,448 |
| Select granular backfill | 600 | CY | $50 × 1.06 | $53 | $31,800 |
| Separation geotextile | 900 | SY | $2.50 × 1.06 | $2.65 | $2,385 |
| Riprap at the ditch | 150 | CY | $130 × 1.06 | $138 | $20,670 |
| Underdrain behind the wall | 240 | LF | $22 × 1.06 | $23 | $5,597 |
| Railroad flagging | 20 | DAY | not location-adjusted | $1,200 | $24,000 |
Budget about $318,000 for the Tennessee site and $386,000 for the Pennsylvania site.
The wall is about 67% of the construction cost in both states, so the location factor on that one item drives most of the difference. Flagging is the same in both because the railroad sets the rate. Report the range ($190,000 to $534,000 in TN) with the typical figure until the wall is designed: pile size and embedment can move the wall unit cost by half in either direction. When the drilling and wall contractors quote, replace the database values with the quotes. The Estimate sheet of the Excel master is set up with these quantities and reproduces the PA total.
Open the state cost database and estimator → Download the Excel master
Pick a state, filter the items, enter quantities and get low, typical and high totals with mobilization, contingency and escalation, plus the same estimate in every state. The Excel master holds the same data with live formulas, so new state prices can be added as they are collected.
Treat the database as a living bid history. When a quote or bid comes in, add it to the State Prices sheet of the Excel master with its year and quantity, and it replaces national × F for that state. Escalate all values each year with the change in the NHCCI or the state's own cost index (Section 3.7.8). Review EST items against actual quotes at least once a year, and retire any published price older than about five years.
Unit costs are compiled from the public sources below; the summaries are in original wording. Individual railroads, clients, companies and projects are not named.