An estimate is a model of the work. Each line should be traceable to a part of the scope (Chapter 3.1) and each quantity to the boring plan (Chapter 3.3) or the access study (Chapter 3.6). When the scope changes, the estimate changes with it, and the history of changes is kept so the final number can be explained.
| Type | Basis | Use |
|---|---|---|
| Order of magnitude | Similar past jobs; footage and days | Screening a program or a budget request; ranking alternatives at the desk |
| Proposal estimate | Task-by-task hours, subconsultant quotes, travel plan | Fee for a specific scope; the normal case for field investigations |
| Construction estimate for alternatives | Quantities and unit costs for stabilization | Comparing risk reduction alternatives (Chapter 3.8) |
Accuracy improves as the scope firms up. Say which type an estimate is, and carry a contingency that matches it rather than hiding uncertainty in the hours.