3.7.9 Budget Tracking

Estimating the cost of exploration, testing, engineering and stabilization, and checking that the number will hold.
Author: Daniel P. Colwell
3.7.9 Budget Tracking

Once the work is authorized, track hours and costs by the same tasks used in the estimate. The budget tracking workbook compares spent to date with the estimate for each task and flags tasks running over, early enough to talk to the client before the money is gone. Where the work grows beyond the scope, the tracking record is the basis for a change order (Chapter 8.2).