3.7.13 Earthwork Volumes, Shrinkage and Haul

Estimating the cost of exploration, testing, engineering and stabilization, and checking that the number will hold.
Author: Daniel P. Colwell
3.7.13 Earthwork Volumes, Shrinkage and Haul

Sidings, yard expansions, realignments and slide repairs all start with an earthwork estimate: how much cut, how much fill, whether the cut will make the fill, and how many truckloads go off site or come in from a borrow pit. Volumes come from cross sections at regular stations; the shrinkage of soil compacted into fill and its swell when loaded for hauling turn the neat volumes into the quantities that are bought, moved and paid for.

3.7.13.1 Method

Equation 3.7-2. Earthwork volume between stations

Average end area: V = L(A1 + A2)/2;   Prismoidal: V = L(A1 + 4Am + A2)/6;   Bank volume for fill = Vfill/(1 − shrinkage);   Loose volume = Vbank(1 + swell)

A1, A2 = end areas (ft²); Am = area of the section half-way between them, whose coordinates are the averages of the end sections; L = distance between stations (ft); divide by 27 for cubic yards.

The average-end-area method overestimates where the areas differ greatly; the prismoidal formula corrects this when the middle section is known. The cumulative difference between cut and bank-adjusted fill along the line (the mass diagram) shows where material can be moved within the job and where it must be wasted or borrowed.

3.7.13.2 Worked example

Example 3.7-1: Grading a Siding Extension

A 400-ft siding extension on a Class I railroad located in Kansas runs from fill, through a cut, back into fill. Cross sections every 100 ft give the cut and fill areas below. The cut is a lean clay with 10% shrinkage and 25% swell; trucks carry 14 loose cubic yards.

gradecutfillfill0+001+002+003+004+00end areas every 100 ftGivenStations 0+00 to 4+00 at 100 ftCut and fill end areas (ft²)Shrinkage 10%, swell 25%Truck 14 cy looseRequiredCut and fill volumesWaste or borrowTruckloads
Profile of the siding extension: fill at both ends and a cut through the middle.

Given

VariableValueDescription
Sta 0+00Cut 0, fill 400 ft²
Sta 1+00Cut 300, fill 250 ft²
Sta 2+00Cut 900, fill 0 ft²
Sta 3+00Cut 600, fill 50 ft²
Sta 4+00Cut 0, fill 500 ft²
Shrinkage, swell10%; 25%Lean clay
Truck14 cy loose

Required

  • Cut and fill volumes
  • Waste or borrow
  • Truckloads to haul the cut

Equations

  1. Eq. 3.7-2: V = L(A1 + A2)/(2 × 27) — cy
  2. Eq. 3.7-2: Bank for fill = Vfill/(1 − 0.10)
  3. Eq. 3.7-2: Loose = Vcut × 1.25

Steps

Step 1 · Cut
100/54 × [(0 + 300) + (300 + 900) + (900 + 600) + (600 + 0)]
Vcut = 6,667 cy
↓
Step 2 · Fill
100/54 × [(400 + 250) + (250 + 0) + (0 + 50) + (50 + 500)]
Vfill = 2,778 cy
Spot check: Hicks’ two-section example (areas 1,504 and 2,240 ft², 100 ft apart) gives 6,933 cy by average end area and 6,904 cy prismoidal in the calculator, matching the handbook.
↓
Step 3 · Bank volume for the fill
2,778/0.90
3,086 cy
↓
Step 4 · Balance
6,667 − 3,086
Waste 3,580 cy (bank)
↓
Step 5 · Haul
6,667 × 1.25 = 8,333 loose cy; /14
596 truckloads if all cut is hauled
↓
Solution
Cut 6,667 cy, fill 2,778 cy; about 3,580 cy (bank) of surplus to waste.

Solution

The cut makes all of the fill with about 3,600 cy to spare, so the job needs a waste site, not a borrow pit.

Only the surplus needs to leave the site: about 3,580 × 1.25 / 14 = 320 truckloads. Before planning to reuse the clay as fill, confirm it can be compacted at its natural water content (Section 5.3.2.5); a wet clay that must be dried or replaced changes the balance and the cost.

Open the earthwork volume calculator →
Average-end-area and prismoidal volumes from a table of stations, shrinkage and swell, waste or borrow, truckloads, an optional unit cost, and the mass diagram.

3.7.13.3 Sources

The summaries above are paraphrased in original wording; equations and tabulated values are standard or published. Individual railroads, clients, companies and projects are not named.

  • T.G. Hicks (ed.), Handbook of Civil Engineering Calculations, McGraw-Hill (2000): Section 5, volume of earthwork (average-end-area and prismoidal methods).Find source ↗Library entry
Supplemental reference · Goswami (2015), Ch. 212

Borrow Pit (Grid) Volumes and Areas by Coordinates

Where cut or fill is measured on a grid rather than on cross sections, as for a borrow pit, a yard pad or a slide excavation, the volume is:

V = [ A / (4 × 27) ] ( Σh1 + 2Σh2 + 3Σh3 + 4Σh4 )   (yd³)

A = area of one grid square (ft²); h1, h2, h3, h4 = cut or fill depths (ft) at grid corners shared by one, two, three and four squares.

The area of an irregular end area or site boundary can be computed from the coordinates of its corners: A = ½ | Σ (xi yi+1 − xi+1 yi) |.

For railroad work: Use the grid method for borrow sources, yard and pad grading, and for the volume of a slide mass or remedial excavation from survey grids or lidar differences, then apply shrinkage and swell as in this section.

Source: Goswami, I. (2015). Civil Engineering All-In-One PE Exam Guide: Breadth and Depth, 3rd ed. New York: McGraw-Hill Education, Chapter 212, Earthwork.

Supplemental reference · Rajapakse (2016), Ch. 38

Borrow Volume From the Mass of Solids, and the Water to Add

A shrinkage percentage taken from a table is only an estimate. When the density and moisture of the borrow soil and the compaction requirement are known, the borrow quantity can be computed directly. Water can be added to the soil or dried out of it, but the mass of solids does not change between the borrow pit and the fill, so it links the two:

Ws = γd,fill × Vfill    γd,borrow = γwet,borrow / (1 + wborrow)    Vbank = Ws / γd,borrow
Water to add = Ws (wfill − wborrow) / 8.34  (gallons)

where γd,fill is the specified dry unit weight (for example 95% of the Proctor maximum), wfill is the placement moisture content, and the borrow values are measured in the pit. The equivalent shrinkage factor is 1 − γd,borrow/γd,fill. A negative result for the water means the borrow is too wet and must be dried by disking and aeration, which takes dry weather and time. Always work in dry unit weights. Using the ratio of wet unit weights mixes the water change into the volume change and gives the wrong borrow quantity (Example 3.7-3).

For railroad work: Use this method when a borrow source is sampled for a siding, embankment widening or slide repair. Measure the borrow pit’s in-place density and moisture at several depths, because both usually vary down the face. Carry the water quantity into the estimate as its own item, with the water source, hauling and any permit. Large quantities are common on embankment work, and in dry country the water can cost as much as the haul.

Source: Rajapakse, R. (2016). Geotechnical Engineering Calculations and Rules of Thumb, 2nd ed. Oxford: Butterworth-Heinemann, Ch. 38 (earthwork; borrow pit problems, Practice Problem 38.6). Summarized and paraphrased; the shrinkage-factor link and recommendations for railroad work are added by the authors of this manual.

Example 3.7-3: Borrow Quantity and Water for a Siding Embankment

A new passing siding for a Class I railroad located in Missouri needs 12,000 cy of compacted embankment fill. The specification calls for 95% of a standard Proctor maximum dry unit weight of 118 pcf, placed at the optimum moisture of 12.5%. A nearby borrow pit has an in-place wet unit weight of 115 pcf at 8% moisture. The borrow soil swells 25% when loaded, and trucks carry 14 loose cubic yards. The engineer must find the borrow volume, the water to add, and the number of truckloads.

Borrow pitγwet = 115 pcfw = 8%V bank = ? 14 cy loose; swell 25%loads = ? Siding fill12,000 cy95% of 118 pcf at 12.5% water to add = ? gal GivenFill: 12,000 cy compactedγd = 0.95 × 118 pcf; w = 12.5%Borrow: γwet = 115 pcf; w = 8%Swell 25%; truck 14 cy loose RequiredMass of solidsBorrow (bank) volumeWater to addTruckloads Black = given; red = required
Given and required for Example 3.7-3.

Given

VariableValueDescription
Vfill12,000 cy = 324,000 ft³Compacted fill required
γd,fill0.95 × 118 = 112.1 pcfSpecified dry unit weight
wfill12.5%Placement moisture (optimum)
γwet,borrow, wborrow115 pcf, 8%Borrow pit in place
Swell; truck25%; 14 cy looseHaul

Required

  • (a) Weight of solids in the fill
  • (b) Bank volume to excavate, and the equivalent shrinkage
  • (c) Water to add, in gallons
  • (d) Number of truckloads

Equations

  1. Eq. 1: Ws = γd,fill Vfill
  2. Eq. 2: γd,borrow = γwet/(1 + w); Vbank = Ws/γd,borrow
  3. Eq. 3: Water = Ws(wfill − wborrow)/8.34 — gallons
  4. Eq. 4: Loads = Vbank(1 + swell)/14

Steps

Step 1 · (a) Solids (Eq. 1)
112.1 × 324,000
Ws = 36.3 million lb
↓
Step 2 · (b) Bank volume (Eq. 2)
γd,borrow = 115/1.08 = 106.5 pcf; 36.32 × 106/106.5 = 341,100 ft³
Vbank = 12,630 cy; shrinkage = 1 − 106.5/112.1 = 5.0%
Spot check: 12,000/12,630 = 0.950. Using wet unit weights instead (126.1/115 × 12,000) gives 13,160 cy, about 530 cy too much.
↓
Step 3 · (c) Water (Eq. 3)
36.32 × 106 × (0.125 − 0.08) = 1.63 million lb; /8.34
About 196,000 gal (16 gal per cy of fill)
↓
Step 4 · (d) Truckloads (Eq. 4)
12,630 × 1.25 = 15,790 loose cy; /14
About 1,130 loads
↓
Solution
12,630 cy bank, 196,000 gal of water, about 1,130 loads.

Solution

(a) Ws = 36.3 million lb. (b) Excavate about 12,630 cy (bank), an equivalent shrinkage of 5%. (c) Add about 196,000 gallons of water. (d) About 1,130 truckloads.

The low shrinkage reflects a borrow soil that is already fairly dense in place. A table value of 10 to 15% would have overstated the borrow by about 700 to 1,500 cy. The water is a real cost item: at 16 gallons per cubic yard, a water truck of 4,000 gallons covers only about 250 cy of fill. Add the water in the pit or on the spread lift and mix it in before compaction, not as a surface spray. Re-measure the pit moisture after rain, because a few points wetter turns a water-adding job into a drying job.