GHRMCalculators · Chapter 3.7, Section 3.7.14Excel master

Geotechnical Design and Construction Cost Database by State

Companion to Chapter 3.7 · Cost Estimates, Section 3.7.14 State Cost Database. 2026 dollars, English units. Planning-level unit costs: use them to size a budget and check a quote, not to replace one.

1. Choose the state

Cost basis: DOT state DOT bid average   FEE published fee schedule or state drilling contract   LAB regional laboratory fee schedule   HIST historical bids escalated   EST planning estimate. A bold state price is a published value for that state; all others are the national value × F.

2. Unit costs and quantities

Enter a quantity against any item to add it to the estimate. Laboratory tests, engineering labor and travel follow the firm and laboratory, not the site, so F is not applied to them.

ItemUnitLowTypicalHighBasisQtyTypical cost

3. Estimate

Same quantities in every state (typical)

Method

Cs = CDOT,s where a published state price exists; otherwise Cs = Cnat × Fs   (Equation 3.7-3)

Total = [Σ(Q × Cs)design + Σ(Q × Cs)constr(1 + m)] (1 + c)(1 + e)n   (Equation 3.7-4)

m = mobilization fraction (construction only), c = contingency, e = annual escalation, n = years from 2026 to the midpoint of the work. Fs is the state location factor (1.00 = national average). The low and high columns carry the national range times F, widened to include a published state value where there is one.

Use and limitations

The location factors are building-construction factors. They are a reasonable first adjustment for labor- and equipment-heavy geotechnical work but are not meant for unit-price items, so a published state DOT price always takes precedence. DOT averages mix small and large jobs; check the quantity behind an average before relying on it, and expect railroad work (flagging, work windows, track access) to price above highway averages. Items marked EST are planning values: replace them with local quotes as they come in. Edit the Excel master to add state prices; the app reads the same data.

Sources

GHRM · Railway Ground Hazard Risk Management · Daniel P. Colwell