3.7.5 Engineering and Reporting Labor

Estimating the cost of exploration, testing, engineering and stabilization, and checking that the number will hold.
Author: Daniel P. Colwell
3.7.5 Engineering and Reporting Labor

Engineering hours follow the deliverable. In the example of Figure 3.7-1, 92 hours covered typed logs (14), analysis (42) and reporting (36) for drilled-shaft design, pavement subgrade parameters, undercut and settlement. A memorandum addendum with stability analyses and quantities for a few reaches takes fewer; a full ground hazard assessment with alternatives takes more. Round all hours to the nearest half hour and bill them at the client's current rate schedule.