Chapter 3.6 — Site Accessibility Study

Working out how crews and equipment will physically reach each boring, what has to be cleared or protected, and what that costs.
Author: Daniel P. Colwell

This chapter covers access planning for field work on and next to railroad property: routes and permissions, track access, rig selection, clearing and ground protection, environmental limits, and the effect of access on cost and schedule. Access is often the largest uncertainty in a railroad exploration budget, and on wooded or wet sites clearing and mats can cost more than the drilling.

3.6.0 Purpose and Overview

A boring that cannot be reached cannot be drilled. The access study answers four questions for each boring: how does the rig get there, what has to be cleared, crossed or protected on the way, whose land is it on, and what approvals are needed. It is built from the desktop study (Chapter 3.2), walked and flagged during the reconnaissance (Chapter 3.4), and priced in the cost estimate (Chapter 3.7).

Plot
Borings, parcels, wetlands, utilities on the map
▬▸
Draw
Conceptual routes from public roads and drives
▬▸
Walk and flag
Ribbon routes; cover, slopes, ditches, obstructions
▬▸
Optimize
Shortest-effort network to all borings
▬▸
Quantify
Clearing, trees, crossings, mats
▬▸
Approve
Railroad, landowners, permits
3.6.1 Access Routes and Permissions

Start every route at a public road, a yard road or a track-side drive, and record the length on road and the length off road. Off-road legs drive the cost.

Table 3.6-1. Example route table for toe borings along a siding
BoringAccess startRoad or drive (ft)Off-road leg (ft)Notes
AV-1Public road at a grade crossing189362Shortest leg; drill first from this setup
AV-2Same1891,063Crosses a box-culvert channel
AV-3Same1891,412Crosses the same channel
AV-4Private drive south of the east reach01,820Longest leg; crosses the wet reach to get there
AV-5Same01,508Wetland-adjacent; mats likely

Conceptual routes drawn on the project map before the reconnaissance; every route is verified on the driller's walk.

Overlay each route on county parcels. Where a lane leaves the railroad parcel, written right-of-entry is needed from that owner; where a boring itself plots outside the parcel (in one case 27 ft into public right-of-way), it needs either a public-way permit or relocation onto railroad property. Because phone GPS (about plus or minus 15 ft) and parcel lines are approximate, field-locate lanes inside the property line wherever possible.

3.6.2 Railroad Access
Table 3.6-2. Railroad access requirements
RequirementNotes
Approval of the boring planThe railroad's construction or engineering group approves the revised plan before drilling
Badging and safety trainingEvery person and the driller's crew
Track protectionWherever a route reaches the ballast within the fouling zone; flagging schedules drive the start date
No driving on ballastRigs stay on the right-of-way beside the track; reach the toe without crossing the ballast
Track windows for hi-rail or on-track workArranged through the railroad; usually short
Separate setupsReaches that are miles apart need their own mobilization
3.6.3 Equipment Suitability
Table 3.6-3. Matching the rig to the ground
Ground or routeRigProtection
Paved yard roads, gravel lots, firm shouldersTruck-mountedNone; watch for ruts in soft gravel
Brush, grass, gentle slopesTrack-mounted (rubber tracks)Clearing of a 12-ft lane
Soft, wet ground; phragmites; swale bottomsTrack-mounted or ATV with balloon tiresTimber or composite mats; dry or frozen ground
Steep or confined sitesPortable or tripod rigHand-carried equipment; limited depth
Water tank needed (rotary or coring)Support truck must reach the rig, or tow the tankConfirm the support-truck route as well as the rig route
A narrow strip between the track and a rock cut. There is no room for a truck rig here; borings at the toe are reached with a track rig along the shoulder or from the field side.
Figure 3.6-1. A narrow strip between the track and a rock cut. There is no room for a truck rig here; borings at the toe are reached with a track rig along the shoulder or from the field side.
3.6.4 Clearing and Ground Protection

Quantify clearing from the flagged routes: a 12-ft lane along each route plus a 30 ft x 40 ft work pad at each off-road boring is a reasonable planning basis. Assign each segment the heaviest cover observed (wooded thicket, reed stand or open meadow) and count trees over 4 in., fallen trunks and ditch crossings. Then look for the shortest-effort network: the most direct parts of the flagged lines plus short new connectors.

Clear every flagged line (acres)1.76Optimized pathway (acres)1.06 of which wooded thicket0.80Clearing area, 13 off-road borings, 19-boring program
Figure 3.6-2. Clearing every flagged line compared with an optimized pathway of 2,508 ft (including 1,448 ft of new connectors) from eight entry points. The optimized network also cut trees over 4 in. from 16 to 6, fallen trunks to be removed from 5 to none, and ditch crossings from 3 to 1.
Table 3.6-4. Clearing quantities and production
ItemOptimized pathwayEvery flagged line
Clearing area1.06 ac (range 0.7 to 1.3)1.76 ac (range 1.2 to 2.1)
Trees over 4 in.616
Fallen trunks to remove05
Ditch crossings13
Mulcher time in dense buckthorn (0.5 to 1.0 ac per day)About 1 to 2 days for the 0.80 ac of thicket, plus half a day of hand cuttingNot estimated

Range: low case a 10-ft lane on 80 percent of the pathway with smaller pads; high case a 14-ft lane with 40 ft x 40 ft pads.

Clear lightly. Flush-cut and mulch without grubbing, and leave cut material on site. Use mats across swales and soft ground and place no fill in ditches or wetlands. This keeps most access clearing outside environmental permitting.
3.6.5 Environmental Limits and Permits
Table 3.6-5. Common environmental limits on access
LimitWhat to do
Mapped wetlandsKeep borings and lanes outside the wetland edge; confirm coverage under the nationwide permit for survey activities (Nationwide Permit 6) with the Corps of Engineers before mechanized clearing near a wetland
FloodplainNo permit expected for borings; fill or mats left in place may need one
Threatened and endangered speciesCheck the IPaC report; most railroad sites have listed species in the county but no critical habitat in the footprint
Migratory birdsClear outside the local migratory bird nesting season (the dates vary by region; the U.S. Fish and Wildlife Service field office gives them), or do a nest check first
Invasive speciesBuckthorn, bush honeysuckle and similar species are often listed as exotic weeds; clearing them is usually welcome, but do not spread cuttings off site
Impacted groundScreen cuttings; drum where readings or odors indicate; cross ditches on mats
3.6.6 Seasonal and Weather Constraints

Schedule the wettest borings after a dry period or on frozen ground, and carry extra mats. Note the season in the cost estimate: the same route may be a mowing job in October and a matting job in April. In regions with hard winters, frozen ground can make a marsh drivable that is impassable in spring.

3.6.7 Access Effects on Cost and Schedule

Carry access in the estimate as its own items: clearing (by area and production), mats (by length and days), rut repair, extra mobilizations for separate setups, and the time the field engineer spends on the clearing day. Ask the driller or a clearing contractor to walk the optimized pathway with the reconnaissance report and price it against the estimate before notice to proceed.

Table 3.6-6. Access items in the estimate
ItemBasis
ClearingAcres of each cover type; mulcher production; hand cutting for trees over 4 in.
MatsLinear feet of soft ground and swale crossings; days on site
Rut repair and restorationAllowance per route on soft ground
MobilizationsOne per separate setup
Permits and right-of-entryPublic-way permit fees; time to obtain
Field engineerClearing-day oversight and re-flagging
Survey the ground at each boring when it is drilled. Lidar elevations used for access planning are for planning only.
3.6.8 Cross-References
Table 3.6-7. Related chapters
TopicRefer to
Reconnaissance and flaggingChapter 3.4
Site conditionsChapter 3.5
Drilling scope and rigsChapter 3.3
Cost estimateChapter 3.7
Scoping assumptionsChapter 3.1