Price the laboratory program from the test list in the RFP (Chapter 3.3). Where the drilling subconsultant's laboratory runs the tests, carry its lump sum and set the consultant's laboratory lines to zero so the client is not billed twice. Compare the two options when both are possible; on one recent job a reset of the subconsultant's lab quantities to match the RFP (fewer moisture contents and two triaxial tests dropped) took about 8 percent off the laboratory cost.