3.7.1 Task Structure

Estimating the cost of exploration, testing, engineering and stabilization, and checking that the number will hold.
Author: Daniel P. Colwell
3.7.1 Task Structure

The workbook uses a fixed task list so that every estimate can be compared with every other. Only the tasks that apply are filled in.

Table 3.7-2. Cost estimate tasks
TaskSubtasks (typical)
A. Project managementSetup, coordination, meetings, invoicing, quality control
B. Ground hazard risk managementDesktop study, field assessment, risk rating, alternatives
C. Engineer reconnaissanceMobilization, on site, demobilization, reconnaissance expenses
D. Subsurface field explorationUtility clearance, mobilization, on-site exploration, demobilization, field expenses and drilling subconsultant
E. Laboratory testingLaboratory management; soil, soil-cement and rock tests (in-house or subconsultant)
F. Geotechnical engineeringBoring logs, analysis, reporting
G. Pavement designOnly where requested
H to MSurvey; hydrology and hydraulics; structures; environmental permitting; bid package; construction quality assurance
A. Project management28 hrC. Engineer reconnaissance18 hrD. Field exploration91.5 hrE. Laboratory (management)6 hrF. Engineering (logs, analysis, report)92 hrLabor hours by task, 19-boring field investigation with report (235.5 hr total)
Figure 3.7-1. Labor hours by task for a recent 19-boring investigation. Field exploration and engineering each take about 40 percent of the hours; project management about 12 percent.